Five LRT3 Stations Set To Be Operational In 2027
According to Transport Minister Anthony Loke, the five Light Rail Transit Line 3 (LRT3) stations that were previously cancelled should be operational by 2027.
He stated that these new stations' construction cannot be finished or put into service by the following year because it is not feasible to finish it in a year because the stations have not been constructed. "These are optional stations to be reintroduced, with implementation expected to take two or three years." He added.
The government will resurrect the plan to construct the five previously cancelled LRT3 stations, Tropicana, Raja Muda, Temasya, Bukit Raja, and Bandar Botanik. The project is estimated to cost RM4.7 billion, according to Prime Minister Datuk Seri Anwar Ibrahim, who made the announcement during the presentation of the 2024 Budget.
Beginning on March 1, 2025, work on the LRT3 construction project in Klang, Selangor, will move from Bandar Utama to Johan Setia. This massive transportation project, which is expected to benefit two million residents, is expected to cost about RM16 billion.
Regarding the LRT3 project's status, Loke stated that as of December 25 of last year, it had reached 91.68 percent completion. The LRT Shah Alam line's scheduled launch date is March 1 of the following year.
Furthermore, the Rapid Transit System (RTS) Link construction, which connects Johor Baru and Singapore, is progressing well. Over 33% of the system aspect and 65% of the infrastructure have been completed. The full completion target is set for December 31, 2026, Loke stated.
Four kilometers of rail connect Bukit Chagar, Johor Baru Station, and Woodlands in Singapore. Of the three hundred fifty daily commuters who use the Johor Causeway, thirty-five percent are expected to use the RTS Link.
Regarding the Bandaraya station's repair status, Loke stated that work has been finished and is presently going through a trial phase by the Land Public Transport Agency (APAD). By the end of February, operations are anticipated to resume.
Prasarana funded the RM30 million repair work, according to Loke, adding that the company plans to take the contractor or project owner to court to hold them liable for the station's damages.
The Ampang LRT line experienced delays on January 27, 2018, as a result of a misaligned track near the Bandaraya LRT station. The viaduct's structural damage was ascribed to construction activities in the vicinity.
The route between Masjid Jamek and Bandaraya stations was temporarily closed by Rapid Rail as a result of this incident, forcing LRT passengers to choose buses or other alternate modes of transportation in order to get to their destinations.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPG2486
SELANGOR
BSF4611
JOHOR
JYA4079
PULAU PINANG
PRR4578
PERAK
ANW6126
PAHANG
CFC1078
KEDAH
KGA9157
NEGERI SEMBILAN
NEG2183
KOTA KINABALU
SJL2710
KUCHING
QAB5039L
Last updated 16 Jun, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.07
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.74
EURO 5 B7
RM 2.94
Last updated 12 Jun, 2025
Related News
LRT 3 Will Cost RM9.7 Billion Less Despite 5 Key Station Reinstatement
LRT 3 will cost RM9.72 Billion less even with the reinstatement of five key stations compared to initial 2015 cost quoted.
29-10-2024
Federal Highway Lane Closure For LRT 3 Project Construction Works
Federal Highway sees lane closures to facilitate the LRT 3 project works from July 26 to July 28.
24-07-2024
LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug
LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).
24-08-2023
LRT Service Will Resume At 6 Stations On May 12 , 6Am
Stesen Bandaraya, Sultan Ismail, PWTC, Titiwangsa, Sentul, and Sentul Timur LRT services will resume on May 12th at 6 a.m.
11-05-2023
Rapid KL Boosts Peak Hours Operations Ahead of ASEAN Summit
Rapid KL extends peak hours train frequency to support commuters during the ASEAN Summit.
21-05-2025
Cabinet Committee Set To Tackle Road Congestion and Safety in 2025
JK-MKKJR outlines major infrastructure and enforcement plans to reduce traffic issues and accidents.
14-05-2025
Platform Automatic Gate System At KL Sentral & Tun Sambathan Now Operational
Prasarana announced that PAGS are now fully operational at KL Sentral and Tun Sambanthan stations.
26-11-2024
Prasarana Updates Peak Hour Operations For Ramadan
Prasarana has announced that the peak hours for its rail and bus services will be extended throughout Ramadan.
12-03-2024
Latest News
Gerik Crash: No signs Of Brake, Steering Failure
Preliminary investigations into the fatal June 9 bus crash in Gerik, have not revealed any technical malfunctions.
15-06-2025
Gerik Crash: Motac Urges Return Of Authority Over Tourism Vehicles
In response to the fatal bus crash involving UPSI students, Motac aimed to regain control over tourism transport for safety reasons.
13-06-2025
Loke: KEJARA System A Failure, Major Revamp Coming
KEJARA system has failed to penalise traffic offenders who ignore their summonses, admits Loke.
13-06-2025
New MD & Co-MD Announced At VPCM and PHSAM
Volkswagen Passenger Cars Malaysia (VPCM) and PHS Automotive Malaysia (PHSAM) announces new MD and co-MD.
13-06-2025
New Speed Limit Device Mandatory In Heavy Vehicles Starting Oct 2025
Speed Limitation Device (SLD) will be compulsory for commercial vehicles starting Oct 2025 to meet national road safety targets.
13-06-2025
FRU Crash: Lorry Exceeds Weight Limit By 70%
Investigation into the fatal Teluk Intan road accident that killed nine FRU personnel last month found the tipper lorry was overloaded.
13-06-2025
WCE Sec 2 Toll Enabled; Responds to Klang Eviction Claims
WCE starts toll operations in Seksyen 2 and clarifies illegal evictions claims.
13-06-2025
Maxim Malaysia Files Final Appeal To APAD
Maxim Malaysia has made an appeal to APAD, requesting permission to maintain its operations within the Malaysian market.
12-06-2025
Show More
trending_flat