LTU Expressway Not Opening For Aidilfitri - Works Minister
Works Minister Datuk Seri Alexander Nanta Linggi denied claims that the Lingkaran Tengah Utama (LTU) Expressway would be open for Aidilfitri, as seen in a recent video circulating online.
He stated that Section 4A, between Raub, Kuala Lipis, and Gua Musang, is still under construction and is expected to be completed on August 26.
“I was informed by the Public Works Department (PWD) that construction progress on this route has reached 83.21 per cent,” he said in a Bernama report.
Nanta cautioned that sharing unverified information could jeopardize the safety of other motorists and lead to potential dangers. He acknowledged that road users were keen to utilize the new route, especially for their Aidilfitri travels, but advised against spreading unconfirmed information.
The LTU is a high-impact project under the works ministry that consists of six packages spanning over 300 kilometres from Kelantan to Pahang, with a RM10 billion budget allocation. Section 3J, among other things, calls for the construction of a new four-lane two-way road spanning 6.95 kilometres from Kampung Seberang Jelai to Kampung Relong, as well as the construction of five bridges, all of which are planned to be finished by July 2024.
When completely finished in 2026, the expressway is estimated to benefit two million road users, particularly during the festive season.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPN3592
SELANGOR
BSG9581
JOHOR
JYE8640
PULAU PINANG
PRT2629
PERAK
APA1447
PAHANG
CFD1685
KEDAH
KGB7404
NEGERI SEMBILAN
NEG6951
KOTA KINABALU
SJM792
KUCHING
QAB9029L
Last updated 12 Aug, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.17
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.94
+0.03
EURO 5 B7
RM 3.14
+0.03
Last updated 07 Aug, 2025
Related News
Four Temporary R&R Stops will be Built on LTU Highway
The Pahang state government is planning to build four temporary R&R stops along the Central Spine Road (LTU).
20-03-2025
KKR Seeking RM20 Million To Build R&R Along LTU Highway
Works Ministry seeks RM20 million budget allocation to set-up R&R along LTU Highway.
11-10-2024
Govt Yet to Decide on Toll-Free Travel for Next Year’s Festive Season
Govt has yet to decide on bringing back toll-free travel for next year’s festive season, says the Works Minister.
25-07-2025
East-West Highway Safe, More Upgrades Coming - Works Minister
The Works Ministry told Bernama the JRTB is safe for users, but more upgrades are on the way under the 13th Malaysia Plan.
22-07-2025
New Marang Bridge 55% Done, Set to Finish By Jan 2027
The RM338mil Marang Bridge project is over halfway complete and on track for January 2027.
15-07-2025
KKR Only Gets Half of RM4B Needed for Road Repairs – Ahmad Maslan
The Public Works Ministry only received half of the RM 4 billion required to repair the damaged roads in Malaysia.
30-06-2025
RM4b Needed, Critical Road Repairs Come First
Road repairs will be done in stages due to budget limits, with priority on the most severe sections.
19-06-2025
Bukit Kayu Hitam ICQS-Sadao CIQ Project On Track For Completion This Year
Bukit Kayu Hitam ICQS-Sadao CIQ project is 47% finished and expected to be completed by Sept.
06-05-2025
Latest News
Perodua Introduces ‘Flexiplan’ Shariah-Compliant Agility Financing Scheme
New Perodua Flexiplan launched as country’s first Shariah-compliant agility financing scheme.
12-08-2025
MP Urges Talks To Lift Ban On JB-SG E-Hailing Rides
Johor MP urges Putrajaya to negotiate lifting Singapore’s e-hailing ban, warning it’s hurting commuters and travellers.
12-08-2025
SDAC Ford Teases New Model – Ford Ranger V6 Coming Soon?
SDAC Ford has put up a new model teaser at its official website. V6-powered Ford Ranger coming soon?
12-08-2025
Odometer Tampering Still Rife In Local Used Car Market
Up to 70% of used cars in Malaysia may have rolled-back mileage to appear newer and fetch higher prices.
12-08-2025
Bas.My Pink Bus Fleet Replaces Rapid Kuantan Starting Dec 16
Kuantan’s public bus network will transition to Bas.My under the SBST 2.0 programme, thus ending Rapid Kuantan’s 13-year service.
12-08-2025
Scrapping Road Tax For Bikes Under 150cc Could Backfire - Expert
Abolishing road tax for bikes under 150cc may help B40 riders but could worsen traffic, pollution, and accident risks.
12-08-2025
JPJ Unveils “SIS” Plate Series, Bidding Starts Aug 15
JPJ launches SIS plate series honouring Sultan Selangor, bidding runs Aug 15 to 19.
12-08-2025
Proton Closes July 2025 By Shifting 13,518 Units
Proton monthly sales up by 22.1% in July 2025 with 13,518 units shifted, pushing YTD total up to 85,674 units.
12-08-2025
Show More
trending_flat