KL-Karak Highway Expansion Project Set to Begin in Q2 2025


AFA Prime Berhad announces that the KL-Karak highway expansion project is set to commence in Q2 2025.
AFA Prime Berhad, the concessionaire of the KL-Karak Expressway (KLK) and East Coast Expressway 1 (LPT1), just announced that the KLK Widening Project is scheduled to begin in Q2 2025. At the same time, the highway concessionaire has also begun the Flood Mitigation Project along LPT1, ensuring uninterrupted highway operations during periods of extreme weather.
The KLK expansion project will cover a stretch from KM19.2 to KM64.5, between the Gombak Toll Plaza and Bentong Toll Plaza, and was mulled in response to rapidly growing traffic volumes along the route, especially during weekends and festive periods.
According to AFA Prime, the whole project is designed to accommodate future demand while prioritising safety and efficiency. With a construction timeline of 48 months, preparatory works such as slope trimming, drainage upgrades, flood mitigation, and retaining wall construction are already in progress, the concessionaire added.
-full_normal.jpg)
-full_normal.jpg)
Among the key features of this expansion project are the addition of one lane in each direction and the widening of road shoulders from 2.5 metres to 3 metres on both sides, in compliance with guidelines set by the Malaysian Highway Authority (LLM). To strengthen emergency response and prevent secondary incidents, the project includes the addition of eight new emergency bays, allowing vehicles with breakdowns to be quickly cleared from active lanes.
Recognising the Genting Sempah Tunnel as a high-traffic zone, the concessionaire has also ensured that construction in this area will be limited to non-peak hours. Night visibility will also be improved with floodlights, while existing lighting will be repositioned for maximum effect upon completion.

AFA Prime Berhad Executive Director Ir. Vijayaraj
“The expansion is about rethinking how a highway should serve its people, not just in terms of capacity, but in reliability, safety, and long-term resilience. Our goal is to build a future-ready expressway. We have incorporated real-time monitoring systems, contingency planning, and emergency response protocols to ensure that motorists remain safe and informed even during construction.” said Ir. Vijayaraj, Executive Director of AFA Prime Berhad.
-full.jpg)
-full.jpg)
Besides the KLK expansion project, AFA Prime has also begun the Flood Mitigation Project along LPT1. These ongoing efforts include comprehensive risk assessments, drainage upgrades, and infrastructure enhancements to reduce the risk of flash flooding along the route.
To manage traffic effectively throughout the construction phase, the concessionaire has appointed Edgenta PROPEL Berhad as its traffic management partner. The company will be responsible for deploying safety assets along the construction areas, including barriers, cones, signage, flagmen, and patrol teams.
Additionally, Digital Variable Message Systems (VMS) will also be installed along the routes to display traffic alerts and emergency notices, which will be reinforced by regular updates on AFA Prime Berhad’s social media platforms.
-full.jpg)
Gallery
Written By
Mukhlis Azman
An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman
JPJ Running Numbers
KUALA LUMPUR
VQJ5481
SELANGOR
BSL9184
JOHOR
JYQ3080
PULAU PINANG
PRY105
PERAK
APE4955
PAHANG
CFE8961
KEDAH
KGD9718
NEGERI SEMBILAN
NEJ3570
KOTA KINABALU
SJP8461
KUCHING
QAB837N
Last updated 25 Jan, 2026
Fuel Price
Petrol
RON 95
RM 2.54
+0.02
RON 97
RM 3.10
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.04
EURO 5 B7
RM 3.08
+0.04
Last updated 22 Jan, 2026
Related News
Kuantan-Bound KL-Karak Lanes Diverted For ECRL Work Until Aug 31
Kuantan-bound lanes (KM25.75–KM26.39) are being diverted for ECRL works until Aug 31.
10-07-2025
TTA: 63% Traffic Surge On KLK and LPT1 Expected During CNY 2025
KLK and LPT1 expects traffic volume to increase by 63% and has issued Travel Time Advisory starting 25 Jan to 2 Feb, 2025.
23-01-2025
KL-Karak Highway Tolls Now Accept Debit and Credit Cards
KL-Karak Highway tolls now accept debit and credit card payments at its Gombak and Bentong Plazas.
03-01-2025
AFA Allocates RM2.1b For KL-Karak Highway Widening Project; Scheduled To Begin Jan 2025
AFA allocates RM2.1 billion for the KL-Karak highway widening project which is set to begin in Jan 2025.
29-11-2024
KL-Karak Highway Road Widening Set to Begin in Jan 2025
KL-Karak Highway road widening exercise to begin in Jan 2025 at the cost of RM2.1 Billion.
04-11-2024
Smart Lane Not Implemented on KLK Due to Hilly Conditions – KKR
Works Minister says that Smart Lanes cannot be implemented on the KL-Karak highway due to its hilly conditions.
30-07-2024
No Plans To Abolish Karak, Gombak Tolls To Alleviate Traffic - Nanta Linggi
Works minister Datuk Seri Alexander Nanta Linggi has confirmed that the government has no plan to abolish Gombak and Karak tolls.
11-03-2024
KL-Karak Highway Widening Project Starts This Year
The federal government has approved a project to widen the Kuala Lumpur-Karak Expressway as a means of reducing traffic congestion.
02-02-2024
Latest News
UPSI Bus Crash: Brake Fade, Speed Cited as Key Factors
Mechanical faults, speeding, and poor oversight behind deadly Gerik bus crash, according to report.
23-01-2026
Volvo Teases ES90 Launch With ‘SELAMAT’ Campaign
Volvo Malaysia briefly presented “SELAMAT” as a new brand before revealing it as a safety-themed teaser campaign ahead of the ES90 launch.
23-01-2026
LEPAS Confirms 20-Outlets Ahead of 2026 Malaysia Launch
LEPAS signals serious intent ahead of its 2026 launch, confirming 20 sales and service outlets across Malaysia.
23-01-2026
JPJ Lifts Travel Proof Rule for Physical Driving Licence
JPJ lifts the travel proof rule, allowing motorists to apply for a physical licence without overseas travel justification.
23-01-2026
KL’s Lalaport Hub Nears Approval for Singapore Express Buses
KL’s Lalaport transport hub nears approval, set to streamline express bus travel to Singapore by February.
22-01-2026
Overloaded Lorry Crackdown Reduces Road Deaths
Stricter JPJ checks on overloaded lorries are helping make Malaysian roads safer with fewer fatal accidents.
22-01-2026
Bukit Chagar RTS Link Station Roof Completed, Final Facade Works Underway
Bukit Chagar station reaches a major milestone as the RTS Link roof is completed.
22-01-2026
Puspakom - New Brake Inspection Rules for Heavy Vehicles
Puspakom’s new brake inspection rules for heavy vehicles target unsafe brake settings that increase accident risks.
22-01-2026
Show More
trending_flat