KL-Karak Highway Expansion Project Set to Begin in Q2 2025

Mukhlis Azman

Share via

AFA-Prime-Berhad-Logo.jpgKLC_LEBUHRAYAKARAK001.jpg

AFA Prime Berhad announces that the KL-Karak highway expansion project is set to commence in Q2 2025.

AFA Prime Berhad, the concessionaire of the KL-Karak Expressway (KLK) and East Coast Expressway 1 (LPT1), just announced that the KLK Widening Project is scheduled to begin in Q2 2025. At the same time, the highway concessionaire has also begun the Flood Mitigation Project along LPT1, ensuring uninterrupted highway operations during periods of extreme weather.

The KLK expansion project will cover a stretch from KM19.2 to KM64.5, between the Gombak Toll Plaza and Bentong Toll Plaza, and was mulled in response to rapidly growing traffic volumes along the route, especially during weekends and festive periods. 

According to AFA Prime, the whole project is designed to accommodate future demand while prioritising safety and efficiency. With a construction timeline of 48 months, preparatory works such as slope trimming, drainage upgrades, flood mitigation, and retaining wall construction are already in progress, the concessionaire added.

KL-Karak-Expressway-(2).pngKL-Karak-Expressway-(1).png

Among the key features of this expansion project are the addition of one lane in each direction and the widening of road shoulders from 2.5 metres to 3 metres on both sides, in compliance with guidelines set by the Malaysian Highway Authority (LLM). To strengthen emergency response and prevent secondary incidents, the project includes the addition of eight new emergency bays, allowing vehicles with breakdowns to be quickly cleared from active lanes.

Recognising the Genting Sempah Tunnel as a high-traffic zone, the concessionaire has also ensured that construction in this area will be limited to non-peak hours. Night visibility will also be improved with floodlights, while existing lighting will be repositioned for maximum effect upon completion.

Ir.-Vijayaraj,-Executive-Director-of-AFA-PRIME-Berhad.jpg

AFA Prime Berhad Executive Director Ir. Vijayaraj

“The expansion is about rethinking how a highway should serve its people, not just in terms of capacity, but in reliability, safety, and long-term resilience. Our goal is to build a future-ready expressway. We have incorporated real-time monitoring systems, contingency planning, and emergency response protocols to ensure that motorists remain safe and informed even during construction.” said Ir. Vijayaraj, Executive Director of AFA Prime Berhad.

LPT1-Expressway-AFAPrime-(2).jpgLPT1-Expressway-AFAPrime-(7).jpg

Besides the KLK expansion project, AFA Prime has also begun the Flood Mitigation Project along LPT1. These ongoing efforts include comprehensive risk assessments, drainage upgrades, and infrastructure enhancements to reduce the risk of flash flooding along the route.

To manage traffic effectively throughout the construction phase, the concessionaire has appointed Edgenta PROPEL Berhad as its traffic management partner. The company will be responsible for deploying safety assets along the construction areas, including barriers, cones, signage, flagmen, and patrol teams.

Additionally, Digital Variable Message Systems (VMS) will also be installed along the routes to display traffic alerts and emergency notices, which will be reinforced by regular updates on AFA Prime Berhad’s social media platforms.

LPT1-Expressway-AFAPrime-(1).jpg


Gallery

Share This Article

Written By

Mukhlis Azman

An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman

Share via

JPJ Running Numbers

KUALA LUMPUR

VPG7574

SELANGOR

BSF5922

JOHOR

JYA7292

PULAU PINANG

PRR5978

PERAK

ANW7894

PAHANG

CFC2081

KEDAH

KGA9813

NEGERI SEMBILAN

NEG2740

KOTA KINABALU

SJL3620

KUCHING

QAB5314L

Last updated 21 Jun, 2025

Fuel Price

Petrol

RON 95

RM 2.05

RON 97

RM 3.14

+0.07

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.81

+0.07

EURO 5 B7

RM 3.01

+0.07

Last updated 19 Jun, 2025

Related News

Auto News
TTA: 63% Traffic Surge On KLK and LPT1 Expected During CNY 2025

TTA: 63% Traffic Surge On KLK and LPT1 Expected During CNY 2025

KLK and LPT1 expects traffic volume to increase by 63% and has issued Travel Time Advisory starting 25 Jan to 2 Feb, 2025.

23-01-2025
Auto News
KL-Karak Highway Tolls Now Accept Debit and Credit Cards

KL-Karak Highway Tolls Now Accept Debit and Credit Cards

KL-Karak Highway tolls now accept debit and credit card payments at its Gombak and Bentong Plazas.

03-01-2025
Auto News
AFA Allocates RM2.1b For KL-Karak Highway Widening Project; Scheduled To Begin Jan 2025

AFA Allocates RM2.1b For KL-Karak Highway Widening Project; Scheduled To Begin Jan 2025

AFA allocates RM2.1 billion for the KL-Karak highway widening project which is set to begin in Jan 2025.

29-11-2024
Auto News
KL-Karak Highway Road Widening Set to Begin in Jan 2025

KL-Karak Highway Road Widening Set to Begin in Jan 2025

KL-Karak Highway road widening exercise to begin in Jan 2025 at the cost of RM2.1 Billion.

04-11-2024
Auto News
Smart Lane Not Implemented on KLK Due to Hilly Conditions – KKR

Smart Lane Not Implemented on KLK Due to Hilly Conditions – KKR

Works Minister says that Smart Lanes cannot be implemented on the KL-Karak highway due to its hilly conditions.

30-07-2024
Auto News
No Plans To Abolish Karak, Gombak Tolls To Alleviate Traffic  - Nanta Linggi

No Plans To Abolish Karak, Gombak Tolls To Alleviate Traffic - Nanta Linggi

Works minister Datuk Seri Alexander Nanta Linggi has confirmed that the government has no plan to abolish Gombak and Karak tolls.

11-03-2024
Auto News
KL-Karak Highway Widening Project Starts This Year

KL-Karak Highway Widening Project Starts This Year

The federal government has approved a project to widen the Kuala Lumpur-Karak Expressway as a means of reducing traffic congestion.

02-02-2024
Auto News
KL-Karak Expressway Sinkhole Caused By ECRL Tunnel Work - Minister

KL-Karak Expressway Sinkhole Caused By ECRL Tunnel Work - Minister

Investigations revealed that the sinkhole on KLK was caused by the ECRL underground tunnel construction works.

26-07-2023

Latest News

Auto News
CIMB Predicts Minimum Impact Of SST Expansion In Auto Sector

CIMB Predicts Minimum Impact Of SST Expansion In Auto Sector

Analysts at CIMB Securities reportedly predict minimum direct impact to local auto sector from SST expansion.

20-06-2025
Auto News
JPJ Wins Digital Transformation Award For MyJPJ App

JPJ Wins Digital Transformation Award For MyJPJ App

JPJ won the ‘Digital Transformation of the Year – Transportation’ award at the GovMedia Awards 2025 for its MyJPJ app.

20-06-2025
Auto News
Jaecoo J7 PHEV – Over 800 Units Registered in Four Months

Jaecoo J7 PHEV – Over 800 Units Registered in Four Months

The Jaecoo J7 PHEV has charted over 800 registrations since its debut, with early adopters celebrated in a special event.

20-06-2025
Auto News
Taxi Touting At KLIA Still On The Rise Despite Crackdowns

Taxi Touting At KLIA Still On The Rise Despite Crackdowns

A 55-year-old taxi driver, caught touting at KLIA, begged JPJ for leniency due to hardship and e-hailing competition.

20-06-2025
Auto News
JPJ Services Offline from June 20-22 – MySIKAP, MyJPJ, VEP Affected

JPJ Services Offline from June 20-22 – MySIKAP, MyJPJ, VEP Affected

All JPJ counters, apps, portals and systems will be temporarily inaccessible for essential upgrades.

20-06-2025
Auto News
OMV Tax Fears Set to Boost Late 2025 Car Sales

OMV Tax Fears Set to Boost Late 2025 Car Sales

Looming OMV duty is expected to pull car purchases forward into Q4 2025.

20-06-2025
Auto News
PM: No RON95 Price Hike Despite Global Tensions

PM: No RON95 Price Hike Despite Global Tensions

Malaysia will keep RON95 prices steady despite rising global oil tensions, says PM.

20-06-2025
Auto News
PLUS: Lane Closure & Contraflow on Penang’s Tun Dr Lim Chong Eu Expressway

PLUS: Lane Closure & Contraflow on Penang’s Tun Dr Lim Chong Eu Expressway

Full lane closure plus contraflow in effect on stretch of Tun Dr Lim Chong Eu expressway from Penang Bridge towards Georgetown until June 20.

19-06-2025

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.