Gamuda Gets Nod To Begin Work On Penang LRT
The Mutiara Line LRT project is now officially in motion, entering its construction phase after receiving the Notice to Proceed (NTP), awarded to Gamuda Bhd on Tuesday.
MRT Corp CEO Datuk Mohd Zarif Hashim told NST that the green light was given after all contract conditions were met.
“We’ve already begun early groundwork ahead of the NTP to make sure everything moves smoothly into the next phase. This includes soil tests, pile checks, environmental monitoring, and site surveys," he says in the NST report. The project’s first phase has been awarded to the SRS Consortium, led by Gamuda (60%), with Loh Phoy Yen Holdings and Ideal Property Development each holding 20%.
-full_normal.jpg)
Early works like utility relocation, piling, and site prep are set to begin next month, with full-scale civil construction expected to start in Q4 2026.
“Projects like this typically follow an S-curve. It's not a sudden jump. Progress starts slow, and we expect the real upward momentum to show after 2027 or 2028,” he explained.
The Mutiara Line broke ground on January 10, launched by Prime Minister Datuk Seri Anwar Ibrahim, marking a major push to modernise Penang’s public transport.
Econpile (M) Sdn Bhd has also secured a RM42.82 million contract from Irama Duta Sdn Bhd for bored piling and related works.

The 29.5km line will feature 21 stations, linking Penang Silicon Island to Komtar and Penang Sentral, aiming to reduce congestion and boost connectivity between the island and the mainland.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQD1217
SELANGOR
BSK7284
JOHOR
JYM5237
PULAU PINANG
PRW4540
PERAK
APD2513
PAHANG
CFE4086
KEDAH
KGD3764
NEGERI SEMBILAN
NEH8405
KOTA KINABALU
SJP2249
KUCHING
QAB7207M
Last updated 10 Dec, 2025
Fuel Price
Petrol
RON 95
RM 2.66
+0.03
RON 97
RM 3.29
+0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.08
EURO 5 B7
RM 3.28
Last updated 04 Dec, 2025
Related News
Penang Police Strengthen Security For Mutiara LRT Project
Penang police are coordinating with agencies to ensure the Mutiara LRT project proceeds safely without compromising public security.
18-11-2025
Penang Traffic Woes Persist Despite PTMP - Penang Gerakan
Penang Gerakan urges an independent review of the PTMP, saying poor planning has worsened traffic instead of easing it.
29-09-2025
MRT Corp Justifies RM16.8b Penang LRT Budget
MRT Corp says the RM16.8 billion ceiling for Penang LRT reflects market realities, but MCA wants clearer answers on taxpayers’ money.
21-08-2025
Penang Still Waiting For Green Light From MOT For LRT project
Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.
02-07-2025
Penang Bus Ridership Now Exceeds 46,000 Daily
Penang bus average daily ridership has reached 46,333 after the introduction of on-demand van service and free bus travel.
22-05-2025
Penang LRT Project Progressing Steadily - MRT Corp
Construction of the Mutiara Line Penang LRT project is on track, according to MRT Corp.
21-04-2025
Penang LRT: Nine “Park and Ride” Facilities With 1,100 Parking Space
Penang LRT line to offer 1,100 parking spaces at nine "Park and Ride” Facilities.
27-11-2024
Penang Confirms LRT Work Construction To Begin In December
December will see the start of work on Penang's LRT project, with Lebuh Macallum serving as the location of the first station.
09-10-2024
Latest News
BYD Malaysia Charts Over 25,000 Units Sales In Just 3 Years
BYD Malaysia reveals it has shifted over 25,000 units of BYD and Denza vehicles in Malaysia in just under 3 years.
09-12-2025
Perodua Traz/Nexis D66B Teased Online – Launching Soon?
Perodua has published a short video teaser featuring the upcoming Traz/Nexis D66B SUV. Launch imminent?
09-12-2025
“Pay Early, Pay Less” Can Curb Habitual Traffic Offenders - Experts
Experts agree the new “pay early, pay less” system could improve compliance and road safety.
09-12-2025
KTMB’s ETS3 To JB Sentral Launches Dec 12 with 30% Discount
KTMB will start operating its ETS3 to JB Sentral on 12 Dec 202 with a 30% discount for travel on this route.
09-12-2025
Works Ministry Denies Removing Barriers at Fatal Terengganu Crash Site
Works minister has refuted claims that his ministry removed the safety signs and concrete barriers at the fatal Terengganu crash site.
08-12-2025
Extended PHEV Battery Warranties From Chery
Extended PHEV battery warranties headline festive year-end deals on offer from Chery Malaysia.
08-12-2025
Continental Tyre Malaysia Introduces Tyre Lifetime Manufacturing Warranty
All Continental, General Tire, and Viking tyres sold in Malaysia now come standard with a lifetime manufacturing warranty.
08-12-2025
Prasarana Set To Roll Out 1,045 Electric Buses By 2030
Prasarana is set to roll out more than 1,045 electric buses across Kuala Lumpur and Penang by 2030.
08-12-2025
Show More
trending_flat