Gamuda Gets Nod To Begin Work On Penang LRT
The Mutiara Line LRT project is now officially in motion, entering its construction phase after receiving the Notice to Proceed (NTP), awarded to Gamuda Bhd on Tuesday.
MRT Corp CEO Datuk Mohd Zarif Hashim told NST that the green light was given after all contract conditions were met.
“We’ve already begun early groundwork ahead of the NTP to make sure everything moves smoothly into the next phase. This includes soil tests, pile checks, environmental monitoring, and site surveys," he says in the NST report. The project’s first phase has been awarded to the SRS Consortium, led by Gamuda (60%), with Loh Phoy Yen Holdings and Ideal Property Development each holding 20%.
-full_normal.jpg)
Early works like utility relocation, piling, and site prep are set to begin next month, with full-scale civil construction expected to start in Q4 2026.
“Projects like this typically follow an S-curve. It's not a sudden jump. Progress starts slow, and we expect the real upward momentum to show after 2027 or 2028,” he explained.
The Mutiara Line broke ground on January 10, launched by Prime Minister Datuk Seri Anwar Ibrahim, marking a major push to modernise Penang’s public transport.
Econpile (M) Sdn Bhd has also secured a RM42.82 million contract from Irama Duta Sdn Bhd for bored piling and related works.

The 29.5km line will feature 21 stations, linking Penang Silicon Island to Komtar and Penang Sentral, aiming to reduce congestion and boost connectivity between the island and the mainland.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRC7294
SELANGOR
BSQ8604
JOHOR
JYY8176
PULAU PINANG
PSD1512
PERAK
APJ2687
PAHANG
CFG7950
KEDAH
KGG5421
NEGERI SEMBILAN
NEK6706
KOTA KINABALU
SJS4392
KUCHING
QAB152P
Last updated 21 Jun, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Penang Police Strengthen Security For Mutiara LRT Project
Penang police are coordinating with agencies to ensure the Mutiara LRT project proceeds safely without compromising public security.
18-11-2025
Penang Traffic Woes Persist Despite PTMP - Penang Gerakan
Penang Gerakan urges an independent review of the PTMP, saying poor planning has worsened traffic instead of easing it.
29-09-2025
MRT Corp Justifies RM16.8b Penang LRT Budget
MRT Corp says the RM16.8 billion ceiling for Penang LRT reflects market realities, but MCA wants clearer answers on taxpayers’ money.
21-08-2025
Penang Still Waiting For Green Light From MOT For LRT project
Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.
02-07-2025
Penang Bus Ridership Now Exceeds 46,000 Daily
Penang bus average daily ridership has reached 46,333 after the introduction of on-demand van service and free bus travel.
22-05-2025
Penang LRT Project Progressing Steadily - MRT Corp
Construction of the Mutiara Line Penang LRT project is on track, according to MRT Corp.
21-04-2025
Penang LRT: Nine “Park and Ride” Facilities With 1,100 Parking Space
Penang LRT line to offer 1,100 parking spaces at nine "Park and Ride” Facilities.
27-11-2024
Penang Confirms LRT Work Construction To Begin In December
December will see the start of work on Penang's LRT project, with Lebuh Macallum serving as the location of the first station.
09-10-2024
Latest News
42 Clauses Are Changing: M'sia Is Facing Its Biggest Road Law Overhaul Since 2020, And Yes, It Affects Your Saman
Malaysia is introducing 42 new clauses to the Road Transport Act in its biggest traffic law overhaul since 2020. Here is how it affects your fines and roadblocks.
19-06-2026
Good News For 5 Million Perodua Owners! Don't Go To Outside Workshops As Service Prices Just Dropped
Thinking of visiting an outside mechanic? Perodua is slashing overall service maintenance parts and labor costs by 10% nationwide starting 19 June.
18-06-2026
It’s Happening! After Years Of Delays, The LRT3 Is Finally Ready To Start Operations
The long-awaited LRT3 Shah Alam Line is officially set to begin operations by the end of this month, as confirmed by Transport Minister Anthony Loke.
18-06-2026
No More Just 'Screwing Parts Together', Malaysia Wants Local Talents To Design The Next Big ASEAN Car Tech
At KLIMS 2026, Deputy Transport Minister Datuk Hasbi Habibollah urged Malaysia's automotive industry to evolve from car assemblers into technology creators.
18-06-2026
It Costs Up To RM300K To Protect One School Zone, And The Government Is Inviting Private Companies To Step Up
Why does a single Safe School Zone cost up to RM300K to build? Transport Minister Anthony Loke breaks down the new physical 30km/h traffic-calming blueprint and why private companies are being asked to step up.
17-06-2026
Prime, Premium, Or Premium Plus? 4 Major Differences Between The 3 Proton e.Mas 7 Tiers
Prime, Premium, or Premium Plus? We break down the 4 massive differences in battery range, price, and luxury features across the new Proton eMas 7 EV tiers.
12-06-2026
15 Drug Records But Still Driving?! Malaysians Are Furious Over The Viral Penang Highway Triton Rampage
Shocking details emerge on the viral Mitsubishi Triton highway crash in Penang. The drugged driver has 17 prior convictions, leaving 18 cars damaged.
10-06-2026
Don't Buy A Car Full Price! Perodua Just Quietly Slashed Prices On 5 Models & The Discounts Vanish After June 30
Perodua just quietly slashed prices on 5 popular models for June 2026! Check out the exact cash rebates for the Myvi, Ativa, Aruz, Bezza, and Axia here.
09-06-2026
Show More
trending_flat