Gamuda Gets Nod To Begin Work On Penang LRT
The Mutiara Line LRT project is now officially in motion, entering its construction phase after receiving the Notice to Proceed (NTP), awarded to Gamuda Bhd on Tuesday.
MRT Corp CEO Datuk Mohd Zarif Hashim told NST that the green light was given after all contract conditions were met.
“We’ve already begun early groundwork ahead of the NTP to make sure everything moves smoothly into the next phase. This includes soil tests, pile checks, environmental monitoring, and site surveys," he says in the NST report. The project’s first phase has been awarded to the SRS Consortium, led by Gamuda (60%), with Loh Phoy Yen Holdings and Ideal Property Development each holding 20%.
Early works like utility relocation, piling, and site prep are set to begin next month, with full-scale civil construction expected to start in Q4 2026.
“Projects like this typically follow an S-curve. It's not a sudden jump. Progress starts slow, and we expect the real upward momentum to show after 2027 or 2028,” he explained.
The Mutiara Line broke ground on January 10, launched by Prime Minister Datuk Seri Anwar Ibrahim, marking a major push to modernise Penang’s public transport.
Econpile (M) Sdn Bhd has also secured a RM42.82 million contract from Irama Duta Sdn Bhd for bored piling and related works.
The 29.5km line will feature 21 stations, linking Penang Silicon Island to Komtar and Penang Sentral, aiming to reduce congestion and boost connectivity between the island and the mainland.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPK4921
SELANGOR
BSG3576
JOHOR
JYD3902
PULAU PINANG
PRS4507
PERAK
ANX8093
PAHANG
CFC6396
KEDAH
KGB4116
NEGERI SEMBILAN
NEG4760
KOTA KINABALU
SJL7383
KUCHING
QAB6928L
Last updated 18 Jul, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.21
+0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.91
+0.03
EURO 5 B7
RM 3.11
+0.03
Last updated 17 Jul, 2025
Related News
Penang Still Waiting For Green Light From MOT For LRT project
Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.
02-07-2025
Penang Bus Ridership Now Exceeds 46,000 Daily
Penang bus average daily ridership has reached 46,333 after the introduction of on-demand van service and free bus travel.
22-05-2025
Penang LRT Project Progressing Steadily - MRT Corp
Construction of the Mutiara Line Penang LRT project is on track, according to MRT Corp.
21-04-2025
Penang LRT: Nine “Park and Ride” Facilities With 1,100 Parking Space
Penang LRT line to offer 1,100 parking spaces at nine "Park and Ride” Facilities.
27-11-2024
Penang Confirms LRT Work Construction To Begin In December
December will see the start of work on Penang's LRT project, with Lebuh Macallum serving as the location of the first station.
09-10-2024
Analysts: Penang Mutiara LRT Important To Improve Urban Mobility And Tourism
Transport analysts say Penang Mutiara LRT would help improve mobility and tourism.
11-04-2024
Green Light For Penang LRT Project, Says PM
The Federal Government would set aside funding for Penang to build its first LRT.
08-05-2023
TNB And Gamuda Land, Building Electron Stations For EVs In Selangor
An alliance has recently been formed between Tenaga Nasional Berhad (TNB) and Gamuda Land to build two Electron Stations for electric vehicle (EV) charging in Selangor.
27-10-2022
Latest News
Suspended PSV, GDL Drivers To Undergo Mandatory Rehab Starting Nov
JPJ will launch a rehab course in November for suspended PSV, GDL drivers to regain licences.
18-07-2025
Singapore’s Driverless Bus Cleared To Run Without Safety Officer
Singapore approves WeRide’s driverless Robobus to run in Sentosa without a safety officer onboard.
18-07-2025
Rapid KL Expands On-Demand Van Service To 12 New Areas In Selangor
Rapid KL’s on-demand van service is expanding to 12 more areas in Shah Alam and Klang starting Friday.
18-07-2025
MRT3 Gets MOT Approval, Completion Set for 2026
The 51.6 KM MRT Circle Line is officially approved, full rollout expected by end of 2026.
18-07-2025
JPJ Plans Major Reform For Kejara System
JPJ is wrapping up its review of long-awaited improvements for the Kejara system.
18-07-2025
4-Vehicle Pile-Up On Besraya Partly Caused By Deployed Airbag
Deployed airbag partly to blame for viral four-vehicle pile-up on Besraya earlier this week.
17-07-2025
No SST-Linked Price Hike for Honda Models in 2025
Honda Malaysia commits to shielding customers from SST-related cost increases.
17-07-2025
Next-Gen Perodua Bezza Rendered Again, Could Launch Soon Too
Render artist extraordinaire Theottle (Chin Swee Hoe) gives us updated vision of upcoming new Perodua Bezza.
17-07-2025
Show More
trending_flat