Kulai-Sedenak Upgrade Begins, 4KM Stretch Opens By 2026
Motorists using the North-South Expressway (PLUS) can look forward to a smoother drive soon, with a four-kilometre stretch from Kulai to Sedenak set to open in phases as early as next year.
This forms part of Phase 1, Package 1 of the highway widening project which is a 14-kilometre upgrade costing RM249 million, aimed at easing congestion along one of the country’s busiest routes.
“Construction began on June 28 last year and is scheduled to be completed by June 28, 2027
“Currently, progress stands at 16.44%, slightly behind the projected 20.02%, with a 3.58% delay,” said Johor’s Public Works, Transport, Infrastructure and Communications chairman, Mohamad Fazli Mohamad Salleh.
He added that the state government has held discussions with LLM, PLUS Malaysia Berhad, and contractors to get the project back on track by September.
Meanwhile, Phase 1, Package 2 which is a seven-kilometre stretch from Sedenak to Simpang Renggam began on June 22 with a budget of RM160 million, and is currently in its early stages. Completion is expected by December 22, 2027.

Phase 2, which spans 16 kilometres from Simpang Renggam to Machap, officially kicks off July 27, following the appointment of the main contractor on July 1. With a cost of RM439 million, this phase is targeted for completion by July 27, 2029.
The multibillion-ringgit widening effort is part of the Maju Johor 2030 agenda, aimed at upgrading infrastructure and improving traffic flow along the southern corridor, a critical artery for both commuters and logistics.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPX4936
SELANGOR
BSJ7826
JOHOR
JYK3816
PULAU PINANG
PRV3385
PERAK
APC2139
PAHANG
CFD9272
KEDAH
KGC8013
NEGERI SEMBILAN
NEH4929
KOTA KINABALU
SJN4574
KUCHING
QAB4428M
Last updated 31 Oct, 2025
Fuel Price
Petrol
RON 95
RM 2.60
RON 97
RM 3.20
+0.06
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.95
+0.06
EURO 5 B7
RM 3.15
+0.06
Last updated 30 Oct, 2025
Related News
PLUS Road Diversions at Kulai–Sedenak from Oct 27–30
PLUS diverting traffic at Kulai–Sedenak to facilitate bridge beam installation from Oct 27 to 30.
25-10-2025
PLUS Announces Partial Lane Closures On NKVE, 10-11 Sept
Closures between Jalan Duta and Bukit Lanjan will take place from 11PM to 5AM for billboard gantry installation.
09-09-2025
PLUS Surpasses 2025 Target with 112 EV Chargers
PLUS has rolled out 112 EV charging points across its highways, surpassing its 2025 target months ahead of schedule.
18-08-2025
Police Investigating Viral Video Of Cars Blocking Traffic On PLUS Highway
Police are investigating a video showing three cars blocking traffic near Pedas-Linggi R&R on the southbound PLUS Highway.
03-07-2025
PLUS Highway Anticipates Over Two Million Vehicles For Hari Raya
PLUS Highway poised to see over two million cars using its highways during peak periods of upcoming Hari Raya Aidilfitri holiday travels.
19-03-2025
PLUS Will Begin Trial Runs On MLFF In April
PLUS aims to commence testing a prototype of its MLFF system by April of this year.
12-02-2025
PLUS Begins Smartlane Trials on ELITE Lingkaran Putrajaya
PLUS will begin trialling the Smartlane function on the ELITE Highway at Lingkaran Putrajaya, from KM P3.0 to KM P4.0.
14-01-2025
Loose Lorry Tyre Caused Deadly Pile-Up That Killed 7 In Melaka
A detached lorry tyre was to blame for a deadly accident that claimed 7 lives and 33 injuries at North-South Expressway northbound.
24-12-2024
Latest News
KPDN Busts Pig Slaughterhouse For Illegal Diesel Storage
Authorities seized 2,000L of subsidised diesel hidden inside a Perak pig slaughterhouse.
30-10-2025
Govt Won’t Suspend KLIA Aerotrain, MAHB Facing Action - Loke
Loke says the government won’t halt the KLIA Aerotrain, but MAHB is facing action.
30-10-2025
ECRL Project On Track Despite RM2.9mil Theft Losses
MRL boosts security after 38 theft cases but says the ECRL project remains on schedule.
30-10-2025
MOT Eyes Rail Expansion, Road Safety and Airport Improvements
Transport Minister YB Loke Siew Fook outlines major transport projects and safety reforms under the 2026 Budget.
30-10-2025
Malaysia’s First Drag Racing Circuit in Sepang by 2026
Malaysia will soon have its first purpose-built drag racing circuit in Sepang by 2026, a RM2 million pilot project led by SIC.
30-10-2025
Updated Fuel Prices From 30 October To 5 November
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 30 October to 5 November, 2025, the rates are as such.
29-10-2025
MACC Open To Probing KLIA Aerotrain
MACC says it will investigate the KLIA Aerotrain project if corruption is found, following months of repeated breakdowns.
29-10-2025
Use Only Approved Reflective Devices Or Face Action - JPJ
JPJ has warned commercial vehicle owners to use only approved reflective devices, with strict enforcement set to begin this Nov.
29-10-2025
Show More
trending_flat