Kulai-Sedenak Upgrade Begins, 4KM Stretch Opens By 2026
Motorists using the North-South Expressway (PLUS) can look forward to a smoother drive soon, with a four-kilometre stretch from Kulai to Sedenak set to open in phases as early as next year.
This forms part of Phase 1, Package 1 of the highway widening project which is a 14-kilometre upgrade costing RM249 million, aimed at easing congestion along one of the country’s busiest routes.
“Construction began on June 28 last year and is scheduled to be completed by June 28, 2027
“Currently, progress stands at 16.44%, slightly behind the projected 20.02%, with a 3.58% delay,” said Johor’s Public Works, Transport, Infrastructure and Communications chairman, Mohamad Fazli Mohamad Salleh. He added that the state government has held discussions with LLM, PLUS Malaysia Berhad, and contractors to get the project back on track by September.
Meanwhile, Phase 1, Package 2 which is a seven-kilometre stretch from Sedenak to Simpang Renggam began on June 22 with a budget of RM160 million, and is currently in its early stages. Completion is expected by December 22, 2027.

Phase 2, which spans 16 kilometres from Simpang Renggam to Machap, officially kicks off July 27, following the appointment of the main contractor on July 1. With a cost of RM439 million, this phase is targeted for completion by July 27, 2029.
The multibillion-ringgit widening effort is part of the Maju Johor 2030 agenda, aimed at upgrading infrastructure and improving traffic flow along the southern corridor, a critical artery for both commuters and logistics.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQN8214
SELANGOR
BSM8749
JOHOR
JYS4243
PULAU PINANG
PSA2314
PERAK
APF6142
PAHANG
CFF5608
KEDAH
KGE5759
NEGERI SEMBILAN
NEJ6525
KOTA KINABALU
SJQ5882
KUCHING
QAB3601N
Last updated 04 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
PLUS Road Diversions at Kulai–Sedenak from Oct 27–30
PLUS diverting traffic at Kulai–Sedenak to facilitate bridge beam installation from Oct 27 to 30.
25-10-2025
PLUS Surpasses 2025 Target with 112 EV Chargers
PLUS has rolled out 112 EV charging points across its highways, surpassing its 2025 target months ahead of schedule.
18-08-2025
Work To Expand Stretch Of PLUS Expressway In Johor Will Commence In June
Work on the PLUS Malaysia expansion project for the North-South Expressway is scheduled to start in June.
20-02-2024
Yinson Greentech Pens MoU with PLUS to Develop DC EV Charging Hub
Yinson Greentech pens an MoU with PLUS Malaysia to develop a DC fast charging hub along the PLUS highway.
23-06-2023
PLUS Issues TTA Schedule For 'Balik Kampung' Trips
PLUS has issued the Travel Time Advisory (TTA) for the North-South Expressway.
14-04-2023
Over 300 Merchants Along PLUS Highway Begin Accepting Cashless Payment
300 stalls along the PLUS Highway’s R&R would now be accepting cashless mode of payments
24-01-2023
TNB Electron EV Charging Stations Ayer Keroh & Paka Now Open - FREE Charging During Test Pilot Period
TNB Electron facilities would be open to the public on a test pilot basis starting today on a FREE to use basis
20-01-2023
12 New RFID Lanes Location Announced By PLUS, Roll Out By April 2023
A total of 12 RFID lanes will be added to tolls under PLUS by April 2023
13-01-2023
Latest News
Wolfgang Egger’s Masterpiece: Denza Z9 GT Confirmed for Malaysia Launch in Q2 2026
BYD Malaysia has officially confirmed that the Denza Z9 GT is set to launch in the local market in early 2026 (expected Q2). As the flagship luxury "shooting brake" for the brand, the Z9 GT is designed to offer a tech-forward alternative to the Porsche Panamera and BMW 5 Series Touring.
03-03-2026
Kelana Jaya LRT trains “out of service” but line running normally - RapidRail
Rapid Rail clarified that temporary train withdrawals on the Kelana Jaya LRT line are part of standard safety procedures.
27-02-2026
Leapmotor C10 Plus Debuts In Malaysia - 299 hp, 510 km Range, From RM139k
The 2026 Leapmotor C10 PLUS and exclusive Night Edition arrive in Malaysia with longer range, faster charging, and upgraded performance.
27-02-2026
Chery Malaysia Teams Up with Lee Chong Wei for Youth Badminton Cup
Chery Malaysia joins forces with Lee Chong Wei to sponsor the inaugural national youth tournament with RM100,000 in prizes.
27-02-2026
Updated Fuel Prices From 26 February To 4 March
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 26 February to 4 March, 2026, the rates are as such.
25-02-2026
APAD to Investigate Kelana Jaya LRT Breakdowns, Prasarana Ordered to Explain
Transport Minister has directed APAD to probe recent Kelana Jaya LRT disruptions and warned action may be taken against Prasarana.
25-02-2026
Chery TIGGO CROSS HEV Grand Prize Winner Announced
Joan Gan became the grand prize winner of a Chery TIGGO CROSS HEV, chosen from over 1,300 participants in Chery Malaysia’s year-end PHEV lucky draw.
24-02-2026
LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays
The Shah Alam LRT3 line is targeted to begin operations by June 2026, with contractors liable for RM2.73 million per day in delay penalties.
24-02-2026
Show More
trending_flat