Kulai-Sedenak Upgrade Begins, 4KM Stretch Opens By 2026
Motorists using the North-South Expressway (PLUS) can look forward to a smoother drive soon, with a four-kilometre stretch from Kulai to Sedenak set to open in phases as early as next year.
This forms part of Phase 1, Package 1 of the highway widening project which is a 14-kilometre upgrade costing RM249 million, aimed at easing congestion along one of the country’s busiest routes.
“Construction began on June 28 last year and is scheduled to be completed by June 28, 2027
“Currently, progress stands at 16.44%, slightly behind the projected 20.02%, with a 3.58% delay,” said Johor’s Public Works, Transport, Infrastructure and Communications chairman, Mohamad Fazli Mohamad Salleh. He added that the state government has held discussions with LLM, PLUS Malaysia Berhad, and contractors to get the project back on track by September.
Meanwhile, Phase 1, Package 2 which is a seven-kilometre stretch from Sedenak to Simpang Renggam began on June 22 with a budget of RM160 million, and is currently in its early stages. Completion is expected by December 22, 2027.
Phase 2, which spans 16 kilometres from Simpang Renggam to Machap, officially kicks off July 27, following the appointment of the main contractor on July 1. With a cost of RM439 million, this phase is targeted for completion by July 27, 2029.
The multibillion-ringgit widening effort is part of the Maju Johor 2030 agenda, aimed at upgrading infrastructure and improving traffic flow along the southern corridor, a critical artery for both commuters and logistics.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPS2194
SELANGOR
BSH7390
JOHOR
JYG6210
PULAU PINANG
PRT9760
PERAK
APB1984
PAHANG
CFD4665
KEDAH
KGC2615
NEGERI SEMBILAN
NEH1067
KOTA KINABALU
SJM5844
KUCHING
QAB1584M
Last updated 14 Sep, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.18
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.90
+0.02
EURO 5 B7
RM 3.10
+0.02
Last updated 11 Sep, 2025
Related News
PLUS Announces Partial Lane Closures On NKVE, 10-11 Sept
Closures between Jalan Duta and Bukit Lanjan will take place from 11PM to 5AM for billboard gantry installation.
09-09-2025
PLUS Surpasses 2025 Target with 112 EV Chargers
PLUS has rolled out 112 EV charging points across its highways, surpassing its 2025 target months ahead of schedule.
18-08-2025
Police Investigating Viral Video Of Cars Blocking Traffic On PLUS Highway
Police are investigating a video showing three cars blocking traffic near Pedas-Linggi R&R on the southbound PLUS Highway.
03-07-2025
PLUS Highway Anticipates Over Two Million Vehicles For Hari Raya
PLUS Highway poised to see over two million cars using its highways during peak periods of upcoming Hari Raya Aidilfitri holiday travels.
19-03-2025
PLUS Will Begin Trial Runs On MLFF In April
PLUS aims to commence testing a prototype of its MLFF system by April of this year.
12-02-2025
PLUS Begins Smartlane Trials on ELITE Lingkaran Putrajaya
PLUS will begin trialling the Smartlane function on the ELITE Highway at Lingkaran Putrajaya, from KM P3.0 to KM P4.0.
14-01-2025
Loose Lorry Tyre Caused Deadly Pile-Up That Killed 7 In Melaka
A detached lorry tyre was to blame for a deadly accident that claimed 7 lives and 33 injuries at North-South Expressway northbound.
24-12-2024
PLUS Activates Smart Lanes At 25 Locations During Christmas Festive
PLUS will activate Smart Lanes at 25 strategic points along the highway from Dec 20, 2024, to Jan 2, 2025
20-12-2024
Latest News
Proton Iriz Production Ends – No Successor Planned, But Should There Be One?
Proton Iriz hatch production ends without a successor, leaving automaker without a new hatch model since 1994.
12-09-2025
West Ipoh Span Expressway Construction Will Begin After 2026
Construction of the West Ipoh Span Expressway is set to start after 2026, providing an alternative to the busy Menora Tunnel route.
12-09-2025
SSLR2 Highway Launched: RM7.6b Project Will Link Sarawak and Sabah
The 335km Sarawak–Sabah Link Road Phase 2 will connect key towns across northern Sarawak into Sabah.
12-09-2025
Proton: We Are Prepared To Serve New X50 After Sales In East Malaysia
Proton reassures it is more than capable of handling after sales coverage for face-lifted new X50 model in East Malaysia.
12-09-2025
PLUS: Up to 2.2 Million Vehicles Daily This Malaysia Day Weekend
PLUS expects traffic to hit 2.2 million vehicles per day on Sept 12, 13, 19 and 20,motorists urged to plan journeys with the MyPLUS-TTA app.
12-09-2025
Prasarana Rail Reliability Hits Record High, Disruptions Halved
Prasarana reports its best rail performance yet, with service reliability more than doubling since 2024.
12-09-2025
Caricarz Automall Sunday Car Market Returns Sept 21 After Strong Debut
Caricarz Automall Sunday Car Market returns Sept 21 to help owners beat lowball trade-ins with direct sales.
12-09-2025
Nadi Willer Introduces New Mobility-as-a-Service Platform in Malaysia
Nadi Willer introduces its new Japanese-quality MaaS platform that integrates mass transit with on-demand DRT services.
12-09-2025
Show More
trending_flat