Penang LRT Stays Within RM16 Billion Budget - MRT Corp
The Penang Mutiara LRT Line will move ahead with a firm budget cap of RM16 billion, despite inflation and escalating construction costs, said MRT Corp chief executive Datuk Mohd Zarif Hashim.
Speaking at a media luncheon, Zarif explained that the earlier RM10 billion estimate, made prior to the federal government's involvement, did not factor in key costs such as land acquisition. He added that even the RM13 billion budget approved by the Cabinet had not fully accounted for inflation, rising material prices, and land-related expenses.
“If we included everything without strict cost controls, the project could reach RM19 billion
“But we won’t let that happen. Through competitive tenders and careful planning, we’re determined to keep it under RM16 billion,” he said.
Zarif added that the Mutiara Line is expected to be the most cost-efficient LRT system in the country. To manage land expenses, MRT Corp is working with the Penang government to secure nominal charges for state-owned land.
The 29.5-kilometre line will run from Silicon Island to Komtar, then cross the channel to Penang Sentral in Butterworth. It will feature 21 stations, including a five-kilometre sea bridge standing 62 metres above sea level, designed to accommodate large shipping vessels.
The line will also include an open-air walkway for pedestrians and cyclists, which will be closed during adverse weather. An optimised depot site at Pesta has been downsized from 37 acres to 11 acres through design efficiency.
The trains will use a Level 3 autonomous system that operates without a driver but includes an onboard attendant, allowing for reduced operational and maintenance costs.
Zarif said the Mutiara Line must become financially self-sufficient within five years of operation, funded through fare collection and advertising revenue. He added that this would free up public funds for future transit lines.
“The Mutiara Line won’t solve everything, but it’s a vital first step
“Penang needs at least four LRT lines to see real change. Once all are in place, the impact will be dramatic,” he was quoted as saying.
The Mutiara Line is scheduled for completion in 2031, with the full four-line network expected by 2050.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPM4730
SELANGOR
BSG7431
JOHOR
JYE4425
PULAU PINANG
PRT569
PERAK
ANY6659
PAHANG
CFD365
KEDAH
KGB6235
NEGERI SEMBILAN
NEG6290
KOTA KINABALU
SJL9999*
KUCHING
QAB8348L
Last updated 02 Aug, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.17
-0.04
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.91
EURO 5 B7
RM 3.11
Last updated 31 Jul, 2025
Related News
Penang Still Waiting For Green Light From MOT For LRT project
Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.
02-07-2025
Mutiara LRT Issues Resolved , Earthworks Commencing Soon
Transport Minister announced that all outstanding issues regarding the Mutiara LRT project have been resolved.
11-06-2025
Penang LRT Project Progressing Steadily - MRT Corp
Construction of the Mutiara Line Penang LRT project is on track, according to MRT Corp.
21-04-2025
Mutiara Line LRT: Penang’s RM8.3 Billion Connectivity Investment
Penang’s RM8.31 billion Mutiara Line LRT project begins with the first phase contract signing.
14-01-2025
Penang Mutiara LRT Project Poised To Commence In 2025
Loke announces phase 1 of Penang Mutiara LRT project will commence early next year.
11-11-2024
Penang Confirms LRT Work Construction To Begin In December
December will see the start of work on Penang's LRT project, with Lebuh Macallum serving as the location of the first station.
09-10-2024
Maslan: 15 KM Juru-Sungai Dua Elevated Highway To Cost RM1.8B
The Juru-Sungai Dua Elevated Highway is set to cost RM1.8B, project will be undertaken by PLUS on a Public-Private Partnership basis.
06-06-2024
Penang Mutiara Line LRT Won’t Be Like Kelana Jaya LRT
Penang’s Mutiara Line LRT would run only 2-car train when it begins and would scale up if required.
31-05-2024
Latest News
Malaysian-Bound Toyota Yaris Cross Receives 5-Star ASEAN NCAP Score
The DNGA-based Toyota Yaris Cross just received a five-star score for the ASEAN NCAP crash test. Coming to Malaysia soon?
02-08-2025
Chery’s Lepas Brand Entering Malaysia Soon? ‘Official’ IG Page Sighted
New ‘official’ IG page we sighted by chance indicates Chery’s new Lepas sub-brand is set to enter Malaysia very soon.
01-08-2025
Govt Looking To Revive MEX II Highway With New Completion Plan
The government is working with bondholders to restart the long-delayed MEX II Highway.
01-08-2025
2025 Proton X50 Facelift Sees 999 Units Shifted In 5 Days
2025 Proton X50 Facelift sees 999 units delivered in just five days, production hits 2,000 units mark as of end of July too.
01-08-2025
Bridgestone Turanza 6 Tyres Launched in Malaysia – 14 to 21 Inches, EV-Ready
Bridgestone Malaysia has introduced the new Turanza 6 tyres in Malaysia, with sizes ranging from 14 to 21 inches.
01-08-2025
Johor Proposes RTS2 Link Between Iskandar Puteri and Tuas
With Bukit Chagar terminal nearing completion, Johor eyes new RTS2 link to Tuas to further ease cross-border travel.
01-08-2025
PAC to KKR: Avoid Costly Missteps in Delayed MLFF Rollout
PAC wants KKR to ensure no hidden costs to government or road users in the upcoming MLFF toll system rollout.
01-08-2025
Klang’s Hop-On Hop-Off Bus Launching This Aug
Klang’s open-top hop-on hop-off bus launches mid-August, covering heritage sites and Port Klang’s mangroves.
01-08-2025
Show More
trending_flat