Proton Launches New EV Plant in Tanjung Malim – e.MAS 7 CKD Begins


Proton has launched its first EV plant in Tanjung Malim, with the local assembly of the e.MAS 7 EV already started.
Less than a year since its groundbreaking ceremony, national automaker Proton has finally launched its first-ever EV production facility in Tanjung Malim. The new EV plant launch was officiated by Prime Minister Datuk Seri Anwar Ibrahim, with the local assembly (CKD) operation for the Proton e.MAS 7 EV already underway at this facility.
With its construction completed ahead of schedule, the new RM82 million facility will boast an initial annual production capacity of 20,000 units, which can be ramped up to 45,000 units annually, thanks to its scalable design and layout.


Compared to Proton’s ICE production facility, the new EV plant has dedicated areas for battery assembly, high-voltage safety, and electrical testing, with layouts designed specifically to accommodate the flat EV platform. The scalability and modularity of the whole facility also allow for a multi-model production in a single line, while its storage systems are already optimised to support both local and export markets, Proton says.
Proton also says that scaling up works for this facility won’t require any significant redesign, as infrastructures like the utility system, material handling paths, and digital traceability tools like manufacturing execution system (MES) and warehouse management system (WMS) are all already in place.


For the EV production itself, parent company Geely has stepped in by providing technical guidance on production systems, as well as helping with equipment selection and deploying experts to assist with installation and trial runs. The Chinese automaker also facilitated overseas training for Proton staff and ensured that the new EV plant is in line with Geely’s global manufacturing standards.


With the opening of this new EV plant, Proton is expected to generate up to 200 new jobs. More importantly, given that this facility will play an integral part in the whole Automotive High-Tech Valley (ATHV) initiative, more jobs are expected to be created in the future once the whole ecosystem is fully operational.


Besides the e.MAS 7, this new EV plant will also be in charge of assembling the upcoming Proton e.MAS 5, which is bound for debut anytime later this year. Beyond these two Proton EVs, there’s no news on whether this facility will also be in charge of assembling other Geely products or models from other Geely-owned brands.

Gallery
Written By
Mukhlis Azman
An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman
JPJ Running Numbers
KUALA LUMPUR
VQP1152
SELANGOR
BSM9440
JOHOR
JYS5137
PULAU PINANG
PSA2897
PERAK
APF6624
PAHANG
CFF5870
KEDAH
KGE6064
NEGERI SEMBILAN
NEJ6716
KOTA KINABALU
SJQ6190
KUCHING
QAB3685N
Last updated 06 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
AHTV Succeeds Shah Alam As Proton’s Next-Generation Manufacturing Hub
AHTV poised to position Proton as regional export hub and boost local supplier networks through high-value jobs.
07-10-2025
DRB-HICOM, Geely Partners With MIDA, MARii To Transform Tanjong Malim AHTV
DRB-HICOM, Geely inks partnership with MIIDA, MARii to transform Tanjong Malim AHTV into NxGV hub.
17-12-2024
Proton Announces Expansion of Stamping Facilities in Tanjong Malim
Proton announces addition of two new stamping lines at Tanjong Malim to increase local parts stamping volume.
26-07-2024
Proton e.MAS 7 Remains Malaysia’s Top-Selling EV, CKD Starts Soon
Proton e.MAS 7 retains No. 1 spot as Malaysia’s best-selling EV with over 5,800 units delivered as of Aug 2025.
18-09-2025
Proton EV Plant Nears Completion, Operation Starts in September 2025
Proton’s new EV production plant achieves 90.4% completion and is set to commence operation later in September.
18-08-2025
Proton Breaks Ground For New EV Production Plant
Proton breaks ground for its first dedicated EV production plant that will be operational by year-end for e.MAS 7 CKD.
07-02-2025
Proton EV Plant Nears Completion, Operation Starts in September 2025
Proton’s new EV production plant achieves 90.4% completion and is set to commence operation later in September.
18-08-2025
Latest News
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far
The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.
05-03-2026
EV King is Here: How Proton e.MAS 5 Dethroned Popular Petrol Cars in 60 Days
PRO-NET has announced that the Proton e.MAS 5 has officially surpassed the 5,000-unit delivery milestone in just two months.
05-03-2026
Wolfgang Egger’s Masterpiece: Denza Z9 GT Confirmed for Malaysia Launch in Q2 2026
BYD Malaysia has officially confirmed that the Denza Z9 GT is set to launch in the local market in early 2026 (expected Q2). As the flagship luxury "shooting brake" for the brand, the Z9 GT is designed to offer a tech-forward alternative to the Porsche Panamera and BMW 5 Series Touring.
03-03-2026
Kelana Jaya LRT trains “out of service” but line running normally - RapidRail
Rapid Rail clarified that temporary train withdrawals on the Kelana Jaya LRT line are part of standard safety procedures.
27-02-2026
Leapmotor C10 Plus Debuts In Malaysia - 299 hp, 510 km Range, From RM139k
The 2026 Leapmotor C10 PLUS and exclusive Night Edition arrive in Malaysia with longer range, faster charging, and upgraded performance.
27-02-2026
Chery Malaysia Teams Up with Lee Chong Wei for Youth Badminton Cup
Chery Malaysia joins forces with Lee Chong Wei to sponsor the inaugural national youth tournament with RM100,000 in prizes.
27-02-2026
Updated Fuel Prices From 26 February To 4 March
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 26 February to 4 March, 2026, the rates are as such.
25-02-2026
APAD to Investigate Kelana Jaya LRT Breakdowns, Prasarana Ordered to Explain
Transport Minister has directed APAD to probe recent Kelana Jaya LRT disruptions and warned action may be taken against Prasarana.
25-02-2026
Show More
trending_flat