KLIA Aerotrain Delayed, MAHB Project Management & Efficiency Questioned
The Automated People Mover System (Aerotrain) at Kuala Lumpur International Airport (KLIA) faces further delays, with no clear completion date in sight.
Transport Minister Anthony Loke Siew Fook revealed recently that while the project was initially expected to be completed by Jan 31, 2025, the timeline remains uncertain as key testing stages are still ongoing.
Currently, the system is undergoing dynamic testing, with full system testing and integration yet to follow. Only after these stages are completed can the system be handed over to the authorities for final approval.
Loke further expressed his dissatisfaction and frustration over Malaysia Airports Holdings Bhd’s (MAHB) role in overseeing the airport. He also criticized MAHB for its slow progress, suggesting that more could have been done to expedite the project.
He went on to acknowledge the public's frustration, stating that he is left to address the matter despite the project beginning long before his return to the Transport Ministry.
He also noted that in Sept 2023, assurances were given by MAHB that the aerotrain would be operational by the end of Jan 2024, especially since two train sets had already arrived.
The KLIA Aerotrain Replacement Project was first awarded in Mar 2022 with a three-year timeline for completion. However, significant delays ensued.
A new consortium comprising Alstom, Aerotrain’s original equipment manufacturer and JMC-Pestech was appointed in Jan 2024 to rescue the stalled project.
While the Aerotrain is a vital infrastructure upgrade for KLIA, the repeated setbacks raise questions with regards to project management, accountability and the efficiency of MAHB’s in handling critical national infrastructure.
Source: MalayMail
Written By
KS
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well! https://www.linkedin.com/in/kumeran-sagathevan/
JPJ Running Numbers
KUALA LUMPUR
VPK2905
SELANGOR
BSG2903
JOHOR
JYD2639
PULAU PINANG
PRS3990
PERAK
ANX6954
PAHANG
CFC5904
KEDAH
KGB3831
NEGERI SEMBILAN
NEG4591
KOTA KINABALU
SJL6908
KUCHING
QAB6772L
Last updated 16 Jul, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.18
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.03
EURO 5 B7
RM 3.08
+0.03
Last updated 10 Jul, 2025
Related News
KLIA Aerotrain Finally Returns, Earns PM’s Nod Too
PM Anwar rides the upgraded KLIA Aerotrain, inter-terminal travel time now takes less than three minutes.
01-07-2025
KLIA Aerotrain Set To Resume Service On July 1
KLIA Aerotrain is set to resume operations on July 1, following successful trials after years of suspension.
21-06-2025
KLIA Aerotrain Delay Resulted From Leadership, Govt Changes - MAHB Chairman
The delay in the KLIA aerotrain project is due to several leadership and governmental transitions, says MAHB chairman.
25-04-2025
PAC To Summon Loke Over Aerotrain Delay and More
PAC will probe EPF’s RM500 million loss in MAHB shares and other key issues, summoning figures like Transport Minister Anthony Loke.
03-02-2025
KLIA Aerotrain Will Return In Q2 2025, MAHB Confirms
KLIA aerotrain service is anticipated to start operating again by the second quarter of this year.
24-01-2025
KLIA's New Aerotrain Set To Be Operational in Q1 2025
KLIA’s new Aerotrain service is expected to be completed in January 2025.
17-07-2024
KLIA Aerotrains Is 90% Completed - Anthony Loke
The first set of Aerotrains is almost 90% done with several new features, says Loke.
23-10-2023
KLIA Aerotrain Services Suspended Due To Mechanical & Electronic Failure
KLIA Aerotrain is already 25 years old making issues like parts supply a major concern
03-03-2023
Latest News
KTMB Focuses On Service Over Profit - Loke
KTMB remains unprofitable due to subsidised fares, but profit isn’t the priority for now, says Transport Minister.
16-07-2025
ECRL Set To Receive First Two EMU Trains, E-Locos By Year-End
ECRL is expected to receive its first two EMU trains and two E-Loco by the end of this year.
16-07-2025
PNB Weighs RM3 Billion Sale of PROLINTAS
PNB is said to be considering a sale of its toll road operator, PROLINTAS, in a deal potentially worth RM3 billion.
16-07-2025
New Marang Bridge 55% Done, Set to Finish By Jan 2027
The RM338mil Marang Bridge project is over halfway complete and on track for January 2027.
15-07-2025
KKR: RM94 Million Spent on Restoring Roads After 2024 Floods
The government spent RM94 million to restore roads and infrastructure damaged by the 2024 floods, with most repairs now completed.
15-07-2025
Experts Urge Used Car Reforms To Protect Buyers
Experts urge a vehicle history database and consumer laws to protect Malaysians from buying damaged used cars.
15-07-2025
22 Nabbed In Singapore For Illegal Cross-Border Ride-Hailing To Malaysia
Singapore authorities have caught 22 drivers offering unlicensed ride-hailing services at Changi Airport and Gardens by the Bay.
15-07-2025
Loke: No ETS For East Coast
Transport Minister Loke confirms ETS will not be extended to the east coast due to single-track, unelectrified rail lines.
15-07-2025
Show More
trending_flat