Penang LRT: Major Road Diversions in Bayan Lepas from Jan 2026

Kumeran Sagathevan

Share via

Penang-LRT-Caricarz-(12).jpg


Major traffic diversions will take place in Bayan Lepas from mid-Jan 2026 as construction of the Penang LRT Mutiara Line gets underway.

According to SRS Consortium project director Adil Putra Ahmad, the first phase will affect Jalan Sultan Azlan Shah between Kampung Jawa and Mayang Pasir. Traffic will be cut from three to two lanes in both directions to allow work on the elevated tracks. 

The stretch, over 1KM long, will take about 38 months to complete, with the target set for Dec 2028.


Penang-LRT-Caricarz-(5).jpgPenang-LRT-Caricarz-(6).jpg


Traffic control will focus on three main areas: Komtar, Sunny Point and the Free Industrial Zone (FIZ). Adil warned that congestion is unavoidable, while state infrastructure and transport committee chairman Zairil Khir Johari said the state would keep the public updated so drivers can better plan their routes. 

He also assured that contractors will follow strict safety measures, especially during the monsoon.


Penang-LRT-Caricarz-(11).jpg


The new line will serve key points across the island. Stations are planned at the FIZ, Penang International Airport, Universiti Sains Malaysia, SPICE, and the upcoming Penang Waterfront Convention Centre, with stops through Jelutong, Sungai Pinang and Macallum Street. 

A channel crossing will link the island to Penang Sentral, connecting directly to the national rail network.


Penang-LRT-Caricarz-(8).jpgPenang-LRT-Caricarz-(7).jpg


“This means someone from Sungai Petani or Padang Besar can take a commuter train to Penang Sentral, transfer to the LRT and continue straight to the airport, USM, Bayan Lepas or Komtar,” Zairil explained.

He described the Mutiara Line as a game-changer, with daily ridership expected to start at 70,000 and grow past 100,000 over time. The system is also expected to cut traffic along the Tun Dr Lim Chong Eu Expressway and surrounding routes.


Source: MalayMail

Gallery

Share This Article

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

JPJ Running Numbers

KUALA LUMPUR

VQH2149

SELANGOR

BSL5615

JOHOR

JYP5011

PULAU PINANG

PRX4850

PERAK

APE430

PAHANG

CFE7261

KEDAH

KGD7503

NEGERI SEMBILAN

NEJ2478

KOTA KINABALU

SJP6849

KUCHING

QAB105N

Last updated 10 Jan, 2026

Fuel Price

Petrol

RON 95

RM 2.54

-0.02

RON 97

RM 3.11

-0.05

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.89

-0.05

EURO 5 B7

RM 3.09

-0.05

Last updated 08 Jan, 2026

Related News

Auto News

Penang Police Strengthen Security For Mutiara LRT Project

Penang police are coordinating with agencies to ensure the Mutiara LRT project proceeds safely without compromising public security.

18-11-2025
Auto News

Mutiara Line LRT: Penang’s RM8.3 Billion Connectivity Investment

Penang’s RM8.31 billion Mutiara Line LRT project begins with the first phase contract signing.

Auto News

Penang Mutiara Line LRT Project Set to Complete in 2030

The cabinet has approved the construction of the Penang Mutiara Line LRT Project, with completion expected by 2023.

Auto News

Anwar: 13MP Pushes for Improved Connectivity – Better Buses, Trains and Roads

The 13th Malaysia Plan focuses on better connectivity through buses, trains, roads, and smarter planning.

Auto News

Penang On Track And Well-Prepared For Large Scale Projects

Penang will implement extensive traffic management measures to mitigate disruptions from upcoming large-scale projects.

04-06-2025
Auto News

Mutiara Line LRT: Penang’s RM8.3 Billion Connectivity Investment

Penang’s RM8.31 billion Mutiara Line LRT project begins with the first phase contract signing.

Auto News

Penang Mutiara Line LRT Won’t Be Like Kelana Jaya LRT

Penang’s Mutiara Line LRT would run only 2-car train when it begins and would scale up if required.

Auto News

Penang Mutiara Line LRT Project Set to Complete in 2030

The cabinet has approved the construction of the Penang Mutiara Line LRT Project, with completion expected by 2023.

Latest News

Auto News

BHPetrol Unveils Refreshed BHPetromart and eNak Concept

BHPetrol launches refreshed BHPetromart and eNak concepts, present more modern and customer-centric retail direction.

Auto News

Chery Kicks Off CNY With SUV Deals Starting RM88,800

Chery Malaysia launches Lunar New Year SUV deals, with top models discounted and extra perks for red cars.

09-01-2026
Auto News

Jetour T2 Secures 5-Star ASEAN NCAP Rating

Jetour T2 secures 5-Star ASEAN NCAP rating, setting a strong safety benchmark ahead of its expected Malaysian launch.

Auto News

MyDigital ID Becomes Mandatory Login For MyNIISe From Jan 15

From Jan 15, Malaysians must use MyDigital ID as the single login to access the MyNIISe immigration app.

09-01-2026
Auto News

Hyundai Tucson Headlines CNY Promotions, Priced From RM125,888

Hyundai Malaysia announced festive CNY promotions, sees Hyundai Tucson tagged from RM125,888 and more.

Auto News

Proton B&P Fire: No Casualties, Incident Under Investigation

Proton acknowledges fire incident that occurred at its B&P facility, says investigation underway and no casualties reported.

08-01-2026
Auto News

Fallen Tree Disrupts KTMB Services Again, Safety Concerns Grow

Another track obstruction has caused major delays on KTM routes, renewing concerns over tree management and rail safety.

08-01-2026
Auto News

Public Transport Ridership Surges, Safety Delays Remain A Challenge

Prasarana’s record-breaking passenger numbers in 2025 show that public confidence in public transport is back on track.

08-01-2026

Show More

trending_flat
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2026 CariCarz.com. All Rights Reserved.