ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
-full_normal.jpg)
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
The theft and vandalism cases along the East Coast Rail Link (ECRL) project continue, with the 32nd case along its alignment from Kota Bharu, Kelantan, to Port Klang, Selangor, recently recorded.
As reported by The Star, October alone saw more than nine cases take place, with the last two taking place just within 24 hours in Maran, Pahang. On Oct 10, thieves cut off a 30-metre stretch of contact wire that is part of the overhead line equipment (OHLE), thus requiring it to be replaced with a cable that is nearly a mile long.
The following day, on Oct 11, a signalling cable in a trench was cut but was not removed, where several hundred metres of cables are needed to replace them.


According to a spokesperson of China Communications Construction Company (CCC-ECRL), Shi Liang Hui, October alone saw a total of nine cases take place in various project sites, thus accumulating to 32 cases since the first one back in May this year.
The number of theft and vandalism cases for ECRL for May, June, August, Sept, and Oct are six, seven, one, nine, and nine, respectively, with no incidents in July. Going state-by-state, Pahang leads with 24 cases, followed by Terengganu at 7, and only one case has taken place in Kelantan so far this year.
Combined, these cases have led to cumulative losses amounting to around RM3 million, with all losses being borne by the contractor, at least for now.
Cable thefts and vandalism aren’t exactly a new issue in our local railway industry, as similar cases also took place in numerous railway projects, including KTM and Express Rail Link Sdn Bhd (ERL).

-full_normal.jpg)
Despite these incidents, the ECRL project is still expected to begin its commercial service in early 2027, with the whole project completion hitting 87% as of August this year.
Source: The Star
Gallery
Written By
Mukhlis Azman
An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman
JPJ Running Numbers
KUALA LUMPUR
VQJ4751
SELANGOR
BSL8945
JOHOR
JYQ2710
PULAU PINANG
PRX9482
PERAK
APE4703
PAHANG
CFE8867
KEDAH
KGD9571
NEGERI SEMBILAN
NEJ3497
KOTA KINABALU
SJP8418
KUCHING
QAB760N
Last updated 23 Jan, 2026
Fuel Price
Petrol
RON 95
RM 2.54
+0.02
RON 97
RM 3.10
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.04
EURO 5 B7
RM 3.08
+0.04
Last updated 22 Jan, 2026
Related News
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%
ECRL project's Kuantan Tunnel will be completed by the end of April.
08-03-2023
Latest News
UPSI Bus Crash: Brake Fade, Speed Cited as Key Factors
Mechanical faults, speeding, and poor oversight behind deadly Gerik bus crash, according to report.
23-01-2026
Volvo Teases ES90 Launch With ‘SELAMAT’ Campaign
Volvo Malaysia briefly presented “SELAMAT” as a new brand before revealing it as a safety-themed teaser campaign ahead of the ES90 launch.
23-01-2026
LEPAS Confirms 20-Outlets Ahead of 2026 Malaysia Launch
LEPAS signals serious intent ahead of its 2026 launch, confirming 20 sales and service outlets across Malaysia.
23-01-2026
JPJ Lifts Travel Proof Rule for Physical Driving Licence
JPJ lifts the travel proof rule, allowing motorists to apply for a physical licence without overseas travel justification.
23-01-2026
KL’s Lalaport Hub Nears Approval for Singapore Express Buses
KL’s Lalaport transport hub nears approval, set to streamline express bus travel to Singapore by February.
22-01-2026
Overloaded Lorry Crackdown Reduces Road Deaths
Stricter JPJ checks on overloaded lorries are helping make Malaysian roads safer with fewer fatal accidents.
22-01-2026
Bukit Chagar RTS Link Station Roof Completed, Final Facade Works Underway
Bukit Chagar station reaches a major milestone as the RTS Link roof is completed.
22-01-2026
Puspakom - New Brake Inspection Rules for Heavy Vehicles
Puspakom’s new brake inspection rules for heavy vehicles target unsafe brake settings that increase accident risks.
22-01-2026
Show More
trending_flat