ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
-full_normal.jpg)
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
The theft and vandalism cases along the East Coast Rail Link (ECRL) project continue, with the 32nd case along its alignment from Kota Bharu, Kelantan, to Port Klang, Selangor, recently recorded.
As reported by The Star, October alone saw more than nine cases take place, with the last two taking place just within 24 hours in Maran, Pahang. On Oct 10, thieves cut off a 30-metre stretch of contact wire that is part of the overhead line equipment (OHLE), thus requiring it to be replaced with a cable that is nearly a mile long.
The following day, on Oct 11, a signalling cable in a trench was cut but was not removed, where several hundred metres of cables are needed to replace them.


According to a spokesperson of China Communications Construction Company (CCC-ECRL), Shi Liang Hui, October alone saw a total of nine cases take place in various project sites, thus accumulating to 32 cases since the first one back in May this year.
The number of theft and vandalism cases for ECRL for May, June, August, Sept, and Oct are six, seven, one, nine, and nine, respectively, with no incidents in July. Going state-by-state, Pahang leads with 24 cases, followed by Terengganu at 7, and only one case has taken place in Kelantan so far this year.
Combined, these cases have led to cumulative losses amounting to around RM3 million, with all losses being borne by the contractor, at least for now.
Cable thefts and vandalism aren’t exactly a new issue in our local railway industry, as similar cases also took place in numerous railway projects, including KTM and Express Rail Link Sdn Bhd (ERL).

-full_normal.jpg)
Despite these incidents, the ECRL project is still expected to begin its commercial service in early 2027, with the whole project completion hitting 87% as of August this year.
Source: The Star
Gallery
Written By
Mukhlis Azman
An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman
JPJ Running Numbers
KUALA LUMPUR
VRP6928
SELANGOR
BST6190
JOHOR
JE948J
PULAU PINANG
PSF4790
PERAK
APL4185
PAHANG
CFH7041
KEDAH
KGJ390
NEGERI SEMBILAN
NEL7955
KOTA KINABALU
SJU507
KUCHING
QAB5470P
Last updated 14 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%
ECRL project's Kuantan Tunnel will be completed by the end of April.
08-03-2023
Latest News
40,595 Summonses, RM12.18 Million Unpaid. JPJ's Patience Is Running Out
JPJ has given 945 transport companies 14 days to settle 40,595 outstanding summonses worth RM12.18 million or face tougher enforcement.
11-09-2026
Use The Kelana Jaya LRT? Here's Why Some Stations Won't Open Until 9.30AM
Kelana Jaya LRT track replacement works run from Sept 2026 to Sept 2027. Check the affected stations, Sunday dates and 9.30AM opening times.
10-09-2026
Your Car's Windscreen Isn't Just Glass, And This Crash Test Shows Why
Malaysia's first live windscreen crash test at MIROS shows why proper installation, adhesive and curing time matter for vehicle safety.
10-09-2026
Would You Trust Malaysia's MLFF System To Charge The Right Car, Every Time?
Malaysia's MLFF is moving forward, but how will barrier-free tolls identify and charge the right car? Here's how RFID, ANPR and the system could work.
09-09-2026
Is "Adjusting" Used-Car Mileage Really Normal In Malaysia?
A Bro Wong-SCRUT dispute has put used-car mileage adjustment back in focus. How common is odometer tampering in Malaysia, and are buyers protected?
09-09-2026
AI Is Now Monitoring 3 Malaysian Highways - Could Automated Summonses Be Next?
AI is now monitoring BESRAYA, NPE and LEKAS, detecting traffic offences and incidents in real time. Could automated summonses eventually follow?
09-09-2026
Too Modified For Malaysian Roads? JPJ Takes Action Against 97, Seizes 37
JPJ seized 37 modified cars during Ops Ekstrem in KL, with 485 notices issued. Some owners reportedly spent up to RM150,000 on exhaust modifications.
09-09-2026
Should Malaysia Follow Singapore And Ban Holding Phones While Driving?
Malaysia is being urged to consider stricter rules on holding phones while driving, similar to Singapore's proposed approach. Here's what the law says.
08-09-2026
Show More
trending_flat
