RTS Link 65% Complete, First Train Arriving This Month
Malaysia’s long-awaited Rapid Transit System (RTS) Link connecting Johor Bahru and Singapore is officially 65% complete, with the first train set expected to arrive this month, Malay Mail has reported.
Transport Minister Anthony Loke said the project is moving steadily, with trial runs set to begin in Dec once the system’s technical checks are ready.
“Today marks my first visit to the site since the completion of the main structure
“The first train set is expected at the Wadi Hana Depot by mid-November,” he said during a site visit in Johor Bahru.
The minister further stated that the viaduct connecting both countries is now 91% complete, while Bukit Chagar Station and the Customs, Immigration, and Quarantine (CIQ) Complex are 73% and 77% done, respectively.
The trial phase, however, won’t be open to the public.
"This round of testing is crucial for system integration, safety inspections, and signalling trials to ensure everything runs smoothly before launch," Loke explained.

RTS Operations (RTSO) CEO Dr Ahmad Marzuki Ariffin said one train will be delivered from Singapore first, followed by three more train sets from Batu Gajah by the end of the year.
Stretching roughly 4 kilometres, the RTS Link will connect Bukit Chagar in Johor Bahru directly to Woodlands North in Singapore, helping ease daily congestion at the Causeway.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQK8672
SELANGOR
BSM2839
JOHOR
JYQ9250
PULAU PINANG
PRY3972
PERAK
APE9125
PAHANG
CFF1565
KEDAH
KGE2153
NEGERI SEMBILAN
NEJ4523
KOTA KINABALU
SJQ1627
KUCHING
QAB1930N
Last updated 03 Feb, 2026
Fuel Price
Petrol
RON 95
RM 2.54
+0.02
RON 97
RM 3.10
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.04
EURO 5 B7
RM 3.08
+0.04
Last updated 22 Jan, 2026
Related News
Bukit Chagar RTS Link Station Roof Completed, Final Facade Works Underway
Bukit Chagar station reaches a major milestone as the RTS Link roof is completed.
22-01-2026
Johor Bahru-Singapore RTS Nears Completion as Testing Begins
The JB-SG RTS Link is on track for completion by Dec, with train testing underway and passenger services expected to begin in Jan 2027.
15-01-2026
Johor-Singapore RTS Completes First Test Run from Wadi Hana To Border
The RTS Link completes its first train test run from Wadi Hana Depot through Bukit Chagar to the Malaysia-Singapore border.
30-12-2025
Johor Questions Delay as Penang LRT Gets Federal Nod
Johor is urging Putrajaya to expedite approval for its long-awaited rail system to avoid RTS congestion.
21-11-2025
RTS Link: First Train Arrives In Johor, Testing Kicks Off At Wadi Hana Depot
Train Set 02 has arrived at Wadi Hana Depot, marking the start of critical testing and commissioning.
17-11-2025
RTS2 Proposal Gains Support to Ease Tuas Congestion
Johor’s proposed second RTS Link between Tuas and Iskandar Puteri is gaining commuter support to ease travel woes, CNA reports.
11-08-2025
RTS Link On Track As Bukit Chagar Hub Completed
The Johor Bahru-Singapore RTS Link has completed its Bukit Chagar terminal and remains on track for launch by end-2026.
30-07-2025
Nightly Closure of Jalan Ismail Sultan for RTS Works Until July 16
Jalan Ismail Sultan (Stulang-bound) will be closed nightly from 10PM to 5AM for RTS Link construction until July 16.
04-07-2025
Latest News
Isuzu Reels In ‘Strong’ 2025 Sales Figures Despite Downward Demands
Isuzu Malaysia says its 2025 sales remain strong despite downward demands for diesel vehicles in Malaysia.
02-02-2026
KLIA Aerotrain Performance Stabilising
Independent assessors say the KLIA Aurotrain system is operating as intended, with early service disruptions performance stabilising.
02-02-2026
WISE Highway Project May Get Six-Month Extension To Strengthen Financial
KKR may grant a six-month extension to the WISE Highway developer to secure funding and complete preparations.
02-02-2026
Ford, Xiaomi Denies EV Joint Venture Talks In US
Ford and Xiaomi dismiss reports of joint venture discussions for EV production in the US.
02-02-2026
Proton e.MAS Charts 3,276 Deliveries in January 2026
Proton e.MAS has delivered a total of 3,276 vehicles in Jan 2026 alone—more than 100 units every day.
02-02-2026
RM39,999 Neta V: Bargain or Red Flag?
RM39,999 Neta V - bargain or red flag? Rock-bottom pricing meets big questions over long-term support.
02-02-2026
Chery Malaysia Outlines 2026 Plans, Four New SUVs Confirmed
Chery Malaysia outlines 2026 plans, with four new SUVs confirmed as the brand shifts focus toward premium and lifestyle models.
31-01-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
Show More
trending_flat