RTS Link 65% Complete, First Train Arriving This Month

Anis

Share via

579c0a91-07f1-48b9-974d-38768479f5d1.JPEG


Malaysia’s long-awaited Rapid Transit System (RTS) Link connecting Johor Bahru and Singapore is officially 65% complete, with the first train set expected to arrive this month, Malay Mail has reported.

Transport Minister Anthony Loke said the project is moving steadily, with trial runs set to begin in Dec once the system’s technical checks are ready.

b54d4dca-f7b7-46a4-9edc-0a79c0a6b188-(1).JPEG
“Today marks my first visit to the site since the completion of the main structure

“The first train set is expected at the Wadi Hana Depot by mid-November,”  he said during a site visit in Johor Bahru. 

bfb20a1a-5108-460b-a20d-0fd098ac95d3.JPEG
The minister further stated that the viaduct connecting both countries is now 91% complete, while Bukit Chagar Station and the Customs, Immigration, and Quarantine (CIQ) Complex are 73% and 77% done, respectively.

The trial phase, however, won’t be open to the public. 

"This round of testing is crucial for system integration, safety inspections, and signalling trials to ensure everything runs smoothly before launch," Loke explained.

Untitled-design---2025-11-03T175623.099.png
RTS Operations (RTSO) CEO Dr Ahmad Marzuki Ariffin said one train will be delivered from Singapore first, followed by three more train sets from Batu Gajah by the end of the year.

Stretching roughly 4 kilometres, the RTS Link will connect Bukit Chagar in Johor Bahru directly to Woodlands North in Singapore, helping ease daily congestion at the Causeway.


Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VRQ2733

SELANGOR

BST7217

JOHOR

JE3179J

PULAU PINANG

PSF5744

PERAK

APL4862

PAHANG

CFH7429

KEDAH

KGJ1321

NEGERI SEMBILAN

NEL8542

KOTA KINABALU

SJU1383

KUCHING

QAB5687P

Last updated 18 Sep, 2026

Fuel Price

Petrol

RON 95

RM 3.97

+1.38

RON 97

RM 4.90

+1.75

RON 100

RM 7.20

+2.20

VPR

RM 8.23

+2.00

Diesel

EURO 5 B10

RM 5.12

+2.08

EURO 5 B7

RM 5.32

+2.08

Last updated 30 Apr, 2026

Related News

Auto News
Johor–Singapore RTS Link Fare Expected at RM15 to RM22 Per Trip

Johor–Singapore RTS Link Fare Expected at RM15 to RM22 Per Trip

Transport Minister Anthony Loke says the RTS Link could cost between RM15 and RM22 per journey, with fares to be announced in 2H2026.

23-02-2026
Auto News
Malaysia Tables RTS Link Bill 2026 to Enable Joint CIQ at JB–Singapore Stations

Malaysia Tables RTS Link Bill 2026 to Enable Joint CIQ at JB–Singapore Stations

RTS Link Bill 2026 is set to enable joint customs, immigration, and security operations between Bukit Chagar Station and Woodlands North Station

12-02-2026
Auto News
First Johor Bahru–Singapore RTS Train Hits Woodlands

First Johor Bahru–Singapore RTS Train Hits Woodlands

The first Johor Bahru–Singapore RTS Link train has arrived in Singapore on Wednesday, as confirmed by LTA.

05-02-2026
Auto News
RTS Link to Deploy 100 E-Gates at Bukit Chagar ICQ

RTS Link to Deploy 100 E-Gates at Bukit Chagar ICQ

RTS Link to deploy 100 e-gates at Bukit Chagar ICQ as part of a high-capacity, congestion-reducing clearance system.

Auto News
Bukit Chagar RTS Link Station Roof Completed, Final Facade Works Underway

Bukit Chagar RTS Link Station Roof Completed, Final Facade Works Underway

Bukit Chagar station reaches a major milestone as the RTS Link roof is completed.

22-01-2026
Auto News
Johor Bahru-Singapore RTS Nears Completion as Testing Begins

Johor Bahru-Singapore RTS Nears Completion as Testing Begins

The JB-SG RTS Link is on track for completion by Dec, with train testing underway and passenger services expected to begin in Jan 2027.

15-01-2026
Auto News
Johor-Singapore RTS Completes First Test Run from Wadi Hana To Border

Johor-Singapore RTS Completes First Test Run from Wadi Hana To Border

The RTS Link completes its first train test run from Wadi Hana Depot through Bukit Chagar to the Malaysia-Singapore border.

30-12-2025
Auto News
Johor Questions Delay as Penang LRT Gets Federal Nod

Johor Questions Delay as Penang LRT Gets Federal Nod

Johor is urging Putrajaya to expedite approval for its long-awaited rail system to avoid RTS congestion.

Latest News

Auto News
Perodua Ativa X Is Now RM53K - Would You Still Buy A Myvi?

Perodua Ativa X Is Now RM53K - Would You Still Buy A Myvi?

The Perodua Ativa X is now RM53,000 after a RM9,500 rebate, just RM1,900 below the Myvi 1.5 H. Here's what you get with each.

17-09-2026
Auto News
BUDI Diesel Can Now Be Transferred Beyond Family - Here's How It Works

BUDI Diesel Can Now Be Transferred Beyond Family - Here's How It Works

BUDI Diesel eligibility can now be transferred beyond immediate family to the actual vehicle user. Here's who qualifies, how to apply and the Sept 27 deadline.

17-09-2026
Auto News
Puspakom Has More Rivals Now. So Why Aren't Car Inspections Getting Cheaper?

Puspakom Has More Rivals Now. So Why Aren't Car Inspections Getting Cheaper?

Puspakom now has rivals for M.V.15 ownership transfer inspections, but fees won't get cheaper. Here's why JPJ is keeping rates standardised.

15-09-2026
Auto News
If You're In Penang And Eyeing A Suzuki, There's A New Showroom To Check Out

If You're In Penang And Eyeing A Suzuki, There's A New Showroom To Check Out

Suzuki has opened a new RM1 million dealership in Juru, Penang, expanding its Malaysian network to 14 sales outlets and 13 service centres.

14-09-2026
Auto News
Malaysia Has More Car Brands Than Ever. So Why Do We Still Choose Proton And Perodua?

Malaysia Has More Car Brands Than Ever. So Why Do We Still Choose Proton And Perodua?

Proton and Perodua account for nearly 63% of Malaysia's new car registrations in 2026. Here's why national brands still dominate despite growing competition.

14-09-2026
Auto News
40,595 Summonses, RM12.18 Million Unpaid. JPJ's Patience Is Running Out

40,595 Summonses, RM12.18 Million Unpaid. JPJ's Patience Is Running Out

JPJ has given 945 transport companies 14 days to settle 40,595 outstanding summonses worth RM12.18 million or face tougher enforcement.

11-09-2026
Auto News
Use The Kelana Jaya LRT? Here's Why Some Stations Won't Open Until 9.30AM

Use The Kelana Jaya LRT? Here's Why Some Stations Won't Open Until 9.30AM

Kelana Jaya LRT track replacement works run from Sept 2026 to Sept 2027. Check the affected stations, Sunday dates and 9.30AM opening times.

10-09-2026
Auto News
Your Car's Windscreen Isn't Just Glass, And This Crash Test Shows Why

Your Car's Windscreen Isn't Just Glass, And This Crash Test Shows Why

Malaysia's first live windscreen crash test at MIROS shows why proper installation, adhesive and curing time matter for vehicle safety.

10-09-2026

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2026 CariCarz.com. All Rights Reserved.