RTS Link 65% Complete, First Train Arriving This Month
Malaysia’s long-awaited Rapid Transit System (RTS) Link connecting Johor Bahru and Singapore is officially 65% complete, with the first train set expected to arrive this month, Malay Mail has reported.
Transport Minister Anthony Loke said the project is moving steadily, with trial runs set to begin in Dec once the system’s technical checks are ready.
 “Today marks my first visit to the site since the completion of the main structure
“The first train set is expected at the Wadi Hana Depot by mid-November,” he said during a site visit in Johor Bahru.
 The minister further stated that the viaduct connecting both countries is now 91% complete, while Bukit Chagar Station and the Customs, Immigration, and Quarantine (CIQ) Complex are 73% and 77% done, respectively.
The trial phase, however, won’t be open to the public.
"This round of testing is crucial for system integration, safety inspections, and signalling trials to ensure everything runs smoothly before launch," Loke explained.

 RTS Operations (RTSO) CEO Dr Ahmad Marzuki Ariffin said one train will be delivered from Singapore first, followed by three more train sets from Batu Gajah by the end of the year.
Stretching roughly 4 kilometres, the RTS Link will connect Bukit Chagar in Johor Bahru directly to Woodlands North in Singapore, helping ease daily congestion at the Causeway.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPY1081
SELANGOR
BSJ9047
JOHOR
JYK5822
PULAU PINANG
PRV4467
PERAK
APC3190
PAHANG
CFD9715
KEDAH
KGC8518
NEGERI SEMBILAN
NEH5271
KOTA KINABALU
SJN5372
KUCHING
QAB4760M
Last updated 04 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.60
RON 97
RM 3.20
+0.06
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.95
+0.06
EURO 5 B7
RM 3.15
+0.06
Last updated 30 Oct, 2025
Related News
RTS2 Proposal Gains Support to Ease Tuas Congestion
Johor’s proposed second RTS Link between Tuas and Iskandar Puteri is gaining commuter support to ease travel woes, CNA reports.
11-08-2025
RTS Link On Track As Bukit Chagar Hub Completed
The Johor Bahru-Singapore RTS Link has completed its Bukit Chagar terminal and remains on track for launch by end-2026.
30-07-2025
Nightly Closure of Jalan Ismail Sultan for RTS Works Until July 16
Jalan Ismail Sultan (Stulang-bound) will be closed nightly from 10PM to 5AM for RTS Link construction until July 16.
04-07-2025
First RTS Link Train Set Delivered Ahead of 2026 Launch
The first train set for the Johor Bahru-Singapore RTS Link was unveiled today and will begin testing soon.
30-06-2025
KTM Shuttle Tebrau Ends 2027, Replaced By RTS Link
KTM Berhad’s Shuttle Tebrau service ends in 2027 and will be replaced by the RTS link.
25-06-2025
RTS Link: Key Road Closure in JB Until End of 2026
Jalan Johor Bahru–Endau closed for 18 months starting June 3 as RTS construction ramps up.
03-06-2025
Gov't Considering LRT Or Tram-Bus For RTS Link To Ease Congestion In JB
Putrajaya is considering either a LRT or a tram-bus system in JB to alleviate congestion once the RTS system is completed.
05-02-2025
JB Motorists Face Increased Congestion Due To RTS Link Construction
Johor Bahru mayor warns motorists of increased congestion as RTS Link construction ramps up.
31-01-2024
Latest News
BUDI95: Fuel Quota For E-Hailing Drivers Raised To 800 Litres
The govt has approved an 800-litre monthly RON95 quota for full-time e-hailing drivers under BUDI95.
04-11-2025
Zeekr X, MG MGS5 EV Earn 5-Star ASEAN NCAP Ratings
Zeekr X tops ASEAN NCAP with 94.64 points, while MG MGS5 EV trails closely at 92.39 points.
04-11-2025
New Audit Move To Keep Highway Concessionaires In Check
Works Ministry will introduce independent audits for highway concessionaires in early 2026.
04-11-2025
BAS.MY Pass Now At RM30 Monthly for Unlimited Bus Rides
BAS.MY services now cost just RM1 a day as the government reduces the 30-day Unlimited Travel Pass from RM50 to RM30.
04-11-2025
RTS Link 65% Complete, First Train Arriving This Month
RTS Link connecting JB and SG is officially 65% complete, with the first train set expected to arrive this month.
03-11-2025
Toyota Skill Contest 2025 Winners Announced
Winners for the Toyota Skill Contest 2025 organised by UMW Toyota Motor have been announced.
03-11-2025
Budi95: Only 0.6% Max Out Quota, Govt Flags Unusual Purchase Near Border
Only 0.6% hit the 300L limit under BUDI95 programme with most recipients using only about 98 litres in Oct.
03-11-2025
RM600 Million Super Magnet Plant Set to Power Malaysia’s EV Ambitions
RM600 million JS Link–Lynas investment drives Malaysia’s push in downstream REE processing for EV and clean energy sectors.
03-11-2025
Show More
trending_flat