Use The Kelana Jaya LRT? Here's Why Some Stations Won't Open Until 9.30AM

- Rapid KL is replacing tracks along the Kelana Jaya LRT Line in seven phases.
- The works begin on Sept 13, 2026 and are scheduled to continue until Sept 2027.
- On selected Sundays, affected stations will only begin operating at 9.30 AM instead of the usual 6 AM.
- Stations not involved in the works will operate as usual.
- Free shuttle buses will be provided to help passengers around the affected sections.
If you regularly take the Kelana Jaya LRT Line, especially on Sunday mornings, you might want to save these dates.
Rapid KL is starting a major track replacement programme along the line from Sept 13, 2026, with works being carried out in seven phases until September 2027.
And on certain Sundays, the stations involved won't begin operating until 9.30 AM, instead of the usual 6 AM.
Don't panic, though. This does not mean the entire Kelana Jaya Line will start late every Sunday for the next year.
Why Are Some Stations Opening Late?

Rapid KL says it is replacing existing tracks with new ones, together with related maintenance works, to maintain the safety and reliability of the Kelana Jaya Line.
Some sections have long curved stretches of track that require more time to replace. This means work on certain scheduled dates will continue into the morning, pushing the opening time of the affected stations to 9.30 AM.
Here's The Full Schedule
The replacement programme is split into seven phases, so check whether your usual station appears below.
| Phase | Dates | Affected Stations |
|---|---|---|
| 1 | Sept 13, 20 & 27, 2026 | Taman Melati, Gombak |
| 2 | Nov 15, 22 & 29, 2026 | Universiti, Kerinchi, Abdullah Hukum |
| 3 | Jan 10, 17 & 24, 2027 | Dato' Keramat, Jelatek, Setiawangsa |
| 4 | March 14, 21 & 28, 2027 | Universiti, Kerinchi, Abdullah Hukum |
| 5 | May 9, 16 & 23, 2027 | Masjid Jamek, Dang Wangi, Kampung Baru, KLCC, Ampang Park |
| 6 | July 11, 18 & 25, 2027 | Taman Jaya, Universiti, Kerinchi, Abdullah Hukum |
| 7 | Sept 12, 19 & 26, 2027 | Taman Melati, Gombak |
What If You Need The LRT Before 9.30 AM?
-full_normal.jpg)
Rapid KL says free shuttle buses will connect the affected stations during the track replacement works, allowing passengers to continue their journeys while waiting for normal train operations to resume.
Staff, auxiliary police and Prasarana Troopers will also be stationed at affected locations to help passengers get around.
So if your station appears on the schedule above, it would be wise to give yourself extra travelling time, especially if you have somewhere important to be early on a Sunday morning.
What About Tickets?
Ticket machines at the affected stations will be temporarily unavailable until 9.30 AM on the scheduled work days.
Passengers who need a ticket can still obtain one at the station counter, while users of Rapid KL products and Touch 'n Go can continue their journeys as usual.
First Up: Gombak And Taman Melati
The first phase begins this Sunday, Sept 13, affecting Gombak and Taman Melati.
The same two stations will also be affected on Sept 20 and Sept 27, before the programme moves to Universiti, Kerinchi and Abdullah Hukum in November.
With the entire track replacement programme stretching until September 2027, Kelana Jaya Line commuters should keep an eye on the schedule whenever one of these Sunday work periods approaches.
Is the entire Kelana Jaya LRT Line opening at 9.30 AM?
Will there be replacement buses?
When will the Kelana Jaya Line track replacement be completed?
Written By
Sofea Najmi
A Bachelor of English Language and Literature graduate with an obsession for the finer details. Sofea uses her background in translation to decode the technicalities of automotive innovation. She is dedicated to delivering impactful, meticulously researched articles that provide a narrative far beyond the spec sheet. LinkedIn: https://bit.ly/3C018vv
JPJ Running Numbers
KUALA LUMPUR
VRV8036
SELANGOR
BSU6256
JOHOR
JG4251J
PULAU PINANG
PSG8253
PERAK
APM5038
PAHANG
CFJ2446
KEDAH
KGJ6029
NEGERI SEMBILAN
NEM4045
KOTA KINABALU
SJU7284
KUCHING
QAB8396P
Last updated 27 Oct, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Prasarana's Broken Lifts: Why Anthony Loke Wants Weekly Updates
Anthony Loke wants Prasarana to continue weekly reports on faulty lifts and escalators. Here's why maintenance monitoring matters to commuters.
23-10-2026
Prasarana Moved 1.54 Million People on New Year’s Eve
Prasarana moved 1.54 million people on New Year’s Eve, marking its highest single-day ridership.
02-01-2026
New Year 2025: Rapid KL Extends Operations Till 3 AM
Rapid KL extends New Year’s Eve operation hours, trains till 3 AM, buses till 3:30 AM.
30-12-2024
Thaipusam 2024: Seven Road Closure Around Batu Caves Till 28 January
Selangor Police has announced seven (7) road closures around the Batu Caves area to alleviate congestion during the upcoming Thaipusam celebration.
23-01-2024
Rapid Bus Skip Stop Xpress From Ampang To KLCC Extended Till 14 Apr 2023
Rapid Bus Skip Stop Xpress bus service (DS01) from Ampang LRT to Kuala Lumpur City Center (KLCC) and Ampang Park direct extended till 14 April 2023.
21-01-2023
Latest News
OMODA | JAECOO Malaysia Sharpens Technician Skills For Better After-Sales Support
OMODA | JAECOO Malaysia's Technical Skills Competition 2026 assesses technician knowledge, diagnostics and repair skills to strengthen after-sales support.
27-10-2026
Malaysia F1 Return: Sepang's 50-50 Chances And What Happens Next
Malaysia's F1 return remains 50-50 as SIC prepares a November Cabinet proposal. Here's what Sepang must overcome before the Malaysian GP can return.
27-10-2026
DENZA Balakong 4S Centre Opens, Among 3 Largest in Malaysia
DENZA opens a 3,000-sqm Balakong 4S centre with servicing, body and paint facilities, plus BYD Flash Charging planned. See its location and opening hours.
26-10-2026
Why Is Waze A Security Concern In Malaysia? Here's What Your Data Reveals
Why has Malaysia restricted Waze for civil servants? Discover NACSA's security concerns, what GPS location data reveals and who is affected.
26-10-2026
ECRL Vs Express Bus: Is Saving Hours Worth Paying More?
ECRL to Kota Bharu starts at RM125, but express buses cost less. Compare fares, travel times and the 30% launch discount before choosing.
26-10-2026
Mercedes-AMG ONE Servicing Can Cost Six Figures. Malaysia Now Has A Dedicated Hub
Mercedes-AMG ONE servicing can cost six figures. Discover why Malaysia's new RM2.2 million service hub is a major milestone for the rare hypercar.
23-10-2026
Loke Says Transport Data Is Open. So Why Is Journey Planning Still A Headache?
Anthony Loke urges local developers to use Malaysia's open public transport data. But gaps in live bus and rail information remain.
23-10-2026
Prasarana's Broken Lifts: Why Anthony Loke Wants Weekly Updates
Anthony Loke wants Prasarana to continue weekly reports on faulty lifts and escalators. Here's why maintenance monitoring matters to commuters.
23-10-2026
Show More
trending_flat
Malaysia First Used Car and EV Consignment Platform
This is the best place to sell your car at true market value. Instead of accepting low dealer trade-ins, we handle everything and connect your car directly to genuine buyers for the highest price.

Understanding CariCarzAutomall Consignment Plan


Approved 200-Check Points Inspection

7 Day Money Back Guarantee

One Year Extended Warranty

No Hidden Charge