Use The Kelana Jaya LRT? Here's Why Some Stations Won't Open Until 9.30AM

- Rapid KL is replacing tracks along the Kelana Jaya LRT Line in seven phases.
- The works begin on Sept 13, 2026 and are scheduled to continue until Sept 2027.
- On selected Sundays, affected stations will only begin operating at 9.30 AM instead of the usual 6 AM.
- Stations not involved in the works will operate as usual.
- Free shuttle buses will be provided to help passengers around the affected sections.
If you regularly take the Kelana Jaya LRT Line, especially on Sunday mornings, you might want to save these dates.
Rapid KL is starting a major track replacement programme along the line from Sept 13, 2026, with works being carried out in seven phases until September 2027.
And on certain Sundays, the stations involved won't begin operating until 9.30 AM, instead of the usual 6 AM.
Don't panic, though. This does not mean the entire Kelana Jaya Line will start late every Sunday for the next year.
Why Are Some Stations Opening Late?

Rapid KL says it is replacing existing tracks with new ones, together with related maintenance works, to maintain the safety and reliability of the Kelana Jaya Line.
Some sections have long curved stretches of track that require more time to replace. This means work on certain scheduled dates will continue into the morning, pushing the opening time of the affected stations to 9.30 AM.
Here's The Full Schedule
The replacement programme is split into seven phases, so check whether your usual station appears below.
| Phase | Dates | Affected Stations |
|---|---|---|
| 1 | Sept 13, 20 & 27, 2026 | Taman Melati, Gombak |
| 2 | Nov 15, 22 & 29, 2026 | Universiti, Kerinchi, Abdullah Hukum |
| 3 | Jan 10, 17 & 24, 2027 | Dato' Keramat, Jelatek, Setiawangsa |
| 4 | March 14, 21 & 28, 2027 | Universiti, Kerinchi, Abdullah Hukum |
| 5 | May 9, 16 & 23, 2027 | Masjid Jamek, Dang Wangi, Kampung Baru, KLCC, Ampang Park |
| 6 | July 11, 18 & 25, 2027 | Taman Jaya, Universiti, Kerinchi, Abdullah Hukum |
| 7 | Sept 12, 19 & 26, 2027 | Taman Melati, Gombak |
What If You Need The LRT Before 9.30 AM?
-full_normal.jpg)
Rapid KL says free shuttle buses will connect the affected stations during the track replacement works, allowing passengers to continue their journeys while waiting for normal train operations to resume.
Staff, auxiliary police and Prasarana Troopers will also be stationed at affected locations to help passengers get around.
So if your station appears on the schedule above, it would be wise to give yourself extra travelling time, especially if you have somewhere important to be early on a Sunday morning.
What About Tickets?
Ticket machines at the affected stations will be temporarily unavailable until 9.30 AM on the scheduled work days.
Passengers who need a ticket can still obtain one at the station counter, while users of Rapid KL products and Touch 'n Go can continue their journeys as usual.
First Up: Gombak And Taman Melati
The first phase begins this Sunday, Sept 13, affecting Gombak and Taman Melati.
The same two stations will also be affected on Sept 20 and Sept 27, before the programme moves to Universiti, Kerinchi and Abdullah Hukum in November.
With the entire track replacement programme stretching until September 2027, Kelana Jaya Line commuters should keep an eye on the schedule whenever one of these Sunday work periods approaches.
Is the entire Kelana Jaya LRT Line opening at 9.30 AM?
Will there be replacement buses?
When will the Kelana Jaya Line track replacement be completed?
Written By
Sofea Najmi
A Bachelor of English Language and Literature graduate with an obsession for the finer details. Sofea uses her background in translation to decode the technicalities of automotive innovation. She is dedicated to delivering impactful, meticulously researched articles that provide a narrative far beyond the spec sheet. LinkedIn: https://bit.ly/3C018vv
JPJ Running Numbers
KUALA LUMPUR
VRP4083
SELANGOR
BST5479
JOHOR
JD8469J
PULAU PINANG
PSF4223
PERAK
APL3492
PAHANG
CFH6721
KEDAH
KGH9583
NEGERI SEMBILAN
NEL7521
KOTA KINABALU
SJT9649
KUCHING
QAB5364P
Last updated 10 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Kelana Jaya LRT trains “out of service” but line running normally - RapidRail
Rapid Rail clarified that temporary train withdrawals on the Kelana Jaya LRT line are part of standard safety procedures.
27-02-2026
MOT Reviewing Platform Screen Doors For LRT Following Blind Passenger’s Death
MOT is considering platform gates at Kelana Jaya and Ampang LRT stations after a fatal accident involving a blind commuter.
10-09-2025
Loke Directs Prasarana To Meet On Klang Valley Train Disruptions
Prasarana has been directed by Loke to hold a special meeting to find the source of the technical issues affecting the MRT and LRT lines.
29-03-2023
Seven Day Free Travel, Kelana Jaya LRT Line - My50, Touch 'N Go and Token Users
As announced previously, free fares will be provided for every day of service disruption to Kelana Jaya Line LRT users. Even though the Kelana Jaya LRT line was only suspended for five (5) days, users will still be given free travel for seven (7) days.
14-11-2022
Automatic Train Control System Faulty, Kelana Jaya LRT’s Service Disruption
A fault in the Automatic Train Control (ATC) system has caused a disruption for the entire Kelana Jaya line LRT service schedule.
08-11-2022
Prasarana Moved 1.54 Million People on New Year’s Eve
Prasarana moved 1.54 million people on New Year’s Eve, marking its highest single-day ridership.
02-01-2026
Rapid KL New Year’s Eve Schedule - Here’s What You Need to Know
Rapid KL extends rail, bus and ROD services across key routes to support New Year’s EVE post-celebration travel.
29-12-2025
Kelana Jaya LRT Weekend Disruptions For Upgrades
Rapid KL will upgrade the Kelana Jaya Line signalling system on Nov 15–16 and 29–30.
14-11-2025
Latest News
Use The Kelana Jaya LRT? Here's Why Some Stations Won't Open Until 9.30AM
Kelana Jaya LRT track replacement works run from Sept 2026 to Sept 2027. Check the affected stations, Sunday dates and 9.30AM opening times.
10-09-2026
Your Car's Windscreen Isn't Just Glass, And This Crash Test Shows Why
Malaysia's first live windscreen crash test at MIROS shows why proper installation, adhesive and curing time matter for vehicle safety.
10-09-2026
Would You Trust Malaysia's MLFF System To Charge The Right Car, Every Time?
Malaysia's MLFF is moving forward, but how will barrier-free tolls identify and charge the right car? Here's how RFID, ANPR and the system could work.
09-09-2026
Is "Adjusting" Used-Car Mileage Really Normal In Malaysia?
A Bro Wong-SCRUT dispute has put used-car mileage adjustment back in focus. How common is odometer tampering in Malaysia, and are buyers protected?
09-09-2026
AI Is Now Monitoring 3 Malaysian Highways - Could Automated Summonses Be Next?
AI is now monitoring BESRAYA, NPE and LEKAS, detecting traffic offences and incidents in real time. Could automated summonses eventually follow?
09-09-2026
Too Modified For Malaysian Roads? JPJ Takes Action Against 97, Seizes 37
JPJ seized 37 modified cars during Ops Ekstrem in KL, with 485 notices issued. Some owners reportedly spent up to RM150,000 on exhaust modifications.
09-09-2026
Should Malaysia Follow Singapore And Ban Holding Phones While Driving?
Malaysia is being urged to consider stricter rules on holding phones while driving, similar to Singapore's proposed approach. Here's what the law says.
08-09-2026
Car Stuck At The Service Centre? KPDN Says Transport Costs May Be Claimable
Car stuck at the service centre for warranty repairs? KPDN says Malaysian owners may seek compensation for reasonable alternative transport costs.
08-09-2026
Show More
trending_flat