Five LRT3 Stations Set To Be Operational In 2027

Anis

Share via

2482248.jpg

According to Transport Minister Anthony Loke, the five Light Rail Transit Line 3 (LRT3) stations that were previously cancelled should be operational by 2027.

He stated that these new stations' construction cannot be finished or put into service by the following year because it is not feasible to finish it in a year because the stations have not been constructed. "These are optional stations to be reintroduced, with implementation expected to take two or three years." He added.

The government will resurrect the plan to construct the five previously cancelled LRT3 stations, Tropicana, Raja Muda, Temasya, Bukit Raja, and Bandar Botanik. The project is estimated to cost RM4.7 billion, according to Prime Minister Datuk Seri Anwar Ibrahim, who made the announcement during the presentation of the 2024 Budget. LRT3_R1-2.jpg

Beginning on March 1, 2025, work on the LRT3 construction project in Klang, Selangor, will move from Bandar Utama to Johan Setia. This massive transportation project, which is expected to benefit two million residents, is expected to cost about RM16 billion.

Regarding the LRT3 project's status, Loke stated that as of December 25 of last year, it had reached 91.68 percent completion. The LRT Shah Alam line's scheduled launch date is March 1 of the following year.

Furthermore, the Rapid Transit System (RTS) Link construction, which connects Johor Baru and Singapore, is progressing well. Over 33% of the system aspect and 65% of the infrastructure have been completed. The full completion target is set for December 31, 2026, Loke stated.

Four kilometers of rail connect Bukit Chagar, Johor Baru Station, and Woodlands in Singapore. Of the three hundred fifty daily commuters who use the Johor Causeway, thirty-five percent are expected to use the RTS Link.

Regarding the Bandaraya station's repair status, Loke stated that work has been finished and is presently going through a trial phase by the Land Public Transport Agency (APAD). By the end of February, operations are anticipated to resume.

Prasarana funded the RM30 million repair work, according to Loke, adding that the company plans to take the contractor or project owner to court to hold them liable for the station's damages.


LRT3-Launch-01-630x333.jpg

The Ampang LRT line experienced delays on January 27, 2018, as a result of a misaligned track near the Bandaraya LRT station. The viaduct's structural damage was ascribed to construction activities in the vicinity.

The route between Masjid Jamek and Bandaraya stations was temporarily closed by Rapid Rail as a result of this incident, forcing LRT passengers to choose buses or other alternate modes of transportation in order to get to their destinations. 

LRT3-(3)-full_normal.jpg





Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VPQ2970

SELANGOR

BSH3982

JOHOR

JYF6973

PULAU PINANG

PRT5370

PERAK

APA5839

PAHANG

CFD3176

KEDAH

KGB9731

NEGERI SEMBILAN

NEG8373

KOTA KINABALU

SJM3049

KUCHING

QAB263M

Last updated 27 Aug, 2025

Fuel Price

Petrol

RON 95

RM 2.05

RON 97

RM 3.13

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.85

-0.05

EURO 5 B7

RM 3.05

-0.05

Last updated 21 Aug, 2025

Related News

Auto News
LRT3 Hits 99% Completion - Loke

LRT3 Hits 99% Completion - Loke

LRT3, which will connect Bandar Utama to Johan Setia, is 99% complete and on track for launch, says Transport Minister.

30-07-2025
Auto News
LRT 3 Will Cost RM9.7 Billion Less Despite 5 Key Station Reinstatement

LRT 3 Will Cost RM9.7 Billion Less Despite 5 Key Station Reinstatement

LRT 3 will cost RM9.72 Billion less even with the reinstatement of five key stations compared to initial 2015 cost quoted.

Auto News
Federal Highway Lane Closure For LRT 3 Project Construction Works

Federal Highway Lane Closure For LRT 3 Project Construction Works

Federal Highway sees lane closures to facilitate the LRT 3 project works from July 26 to July 28.

Auto News
LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug

LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug

LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).

Auto News
LRT Service Will Resume At 6 Stations On May 12 , 6Am

LRT Service Will Resume At 6 Stations On May 12 , 6Am

Stesen Bandaraya, Sultan Ismail, PWTC, Titiwangsa, Sentul, and Sentul Timur LRT services will resume on May 12th at 6 a.m.

11-05-2023
Auto News
Ten LRT KJ Line Stations Set for Upgrade – Open From 9 AM on Weekends

Ten LRT KJ Line Stations Set for Upgrade – Open From 9 AM on Weekends

Ten LRT stations on the Kelana Jaya line will be upgraded, and their operation times will be affected on weekends.

28-07-2025
Auto News
Rapid KL On-Demand Adds 5 New Zones — Cyberjaya & Putrajaya Included

Rapid KL On-Demand Adds 5 New Zones — Cyberjaya & Putrajaya Included

The Rapid KL On-Demand service has been expanded to five new zones, including Cyberjaya and Putrajaya.

17-06-2025
Auto News
Rapid KL Boosts Peak Hours Operations Ahead of ASEAN Summit

Rapid KL Boosts Peak Hours Operations Ahead of ASEAN Summit

Rapid KL extends peak hours train frequency to support commuters during the ASEAN Summit.

Latest News

Auto News
New Law In February To Ease RTS Link Border Checks - Home Minister

New Law In February To Ease RTS Link Border Checks - Home Minister

Malaysia will table a Bill next February to enable co-located border checks for the Johor Bahru–Singapore RTS Link.

27-08-2025
Auto News
iCaur Malaysia Opens World’s First iCaur Dealership in Glenmarie

iCaur Malaysia Opens World’s First iCaur Dealership in Glenmarie

The newly opened iCaur Glenmarie by Absolute Motor is the brand’s first-ever dealership in the world.

27-08-2025
Auto News
West Coast Expressway On Track For 2027 Completion

West Coast Expressway On Track For 2027 Completion

The West Coast Expressway is on track for full completion by 2027, with eight of its 11 sections already open.

27-08-2025
Auto News
Jetour Malaysia Charts Over 2,000 Bookings, Expands Network to 20 Dealerships

Jetour Malaysia Charts Over 2,000 Bookings, Expands Network to 20 Dealerships

Jetour Malaysia has expanded its dealer network to 20 locations, while racking up over 2,000 bookings for their SUVs.

26-08-2025
Auto News
RON95 Subsidy Sees Quota System With Higher Allowance for P-Hailing, E-Hailing

RON95 Subsidy Sees Quota System With Higher Allowance for P-Hailing, E-Hailing

The government will introduce new quota-based RON95 subsidy with higher fuel allowances for p-hailing and e-hailing drivers.

Auto News
ETS 3 Final Phase to Johor Bahru Set for December Launch – MoT

ETS 3 Final Phase to Johor Bahru Set for December Launch – MoT

Transport Minister Anthony Loke said the final phase of the ETS 3 project to Johor Bahru will be launched this December.

26-08-2025
Auto News
Shah Alam LRT Delayed Again, December Now In Sight

Shah Alam LRT Delayed Again, December Now In Sight

The Shah Alam LRT may miss its September deadline, with Prasarana now aiming for a December launch pending crucial safety tests.

26-08-2025
Auto News
Malaysia’s Transport Push: RTS, Digital Upgrades and Rail Milestones

Malaysia’s Transport Push: RTS, Digital Upgrades and Rail Milestones

Transport Minister says Malaysia’s transport is hitting new milestones, bringing real changes for travellers.

26-08-2025

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.