ECRL Project, Aims to Operate by 2027

Jesica Sendai

Share via

Recently, Prime Minister Datuk Seri Ismail Sabri Yaakob has officiated a ceremony to mark the start of Genting Tunnel excavation under the East Coast Rail Link (ECRL) first tunnel boring machine (TBM1) project.

The project costs more than 50 million and could enhance connectivity between Selangor and the east coast states including transport cargo from Port Klang to Port Kuantan. 

Apart from that, it benefitted young people especially 5,000 youths from east coast as it has the potential to produce more highly skilled locals through ECRL Industrial Skills Training Programme (PLKI-ECRL).


Tunnel Boring Machine (TBM1) is predicted to complete approximately 2 and a half years to three years to break through 16.39km Genting Tunnel which costs an average excavation amount of between 400m and 600m per month. 

Once the tunnel project is accomplished, it will become the longest rail tunnel in the South-east Asia region which expected to operate in January 2027 having 665 kilometres distance across Kelantan, Terengganu, Pahang, and Selangor.

More uniquely, this tunnel excavation is the only among 59 tunnels drilling to use the TBM method, compared to the drilling and blasting methods for previous tunnels.


With a speed of 160kph, the journey is more convenient and safer for passengers to travel to the east coast. 

Total of 20 stations, consisting of 10 passenger stations and a mix of passenger and cargo stations, the ECRL is also connected to the LRT Kelana Jaya Line at ITT Gombak, thus reducing travel time to Kelantan to 4 hours compared to 7 to 12 hours of journey during festive season. 

TBM1 is a state-of-the-art machine built made for this project and is the largest rail construction machine in South-east Asia to convey through Titiwangsa Range along the Bukit Tinggi area which link Bentong with Gombak, Selangor.

THE East Coast Rail Link (ECRL) is under the partnership project between Malaysia Rail Link Sdn Bhd (MRL) and China Communications Construction Co Ltd (CCCC). 


Tagged:

ECRL
Share This Article

Written By

Jesica Sendai

from 9 to 5 grinder to 'racing' her way in the automotive industry through editorial work.

Share via

Related News

Auto News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News
ECRL Project Hits 87% Completion by August 2025 – MoT

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Project Progress Surpasses 56% - Loke

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News
ECRL Project In Terengganu Reaches 55% Progress

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023

Latest News

Auto News
The RM5,000 Raya Flex: Why Malaysians are Risking a Monthly Salary to Rent an Alphard

The RM5,000 Raya Flex: Why Malaysians are Risking a Monthly Salary to Rent an Alphard

Is renting an Alphard for RM5,000 a waste or a genius move? We break down the 'Raya Flex' cost, from RM10k insurance premiums to the 'Executive Lounge' comfort that saves your back on an 18-hour East Coast jam.

27-03-2026
Auto News
Safe Passage at Hormuz: Why Malaysia’s Special Deal with Iran Won't Lower Your Petrol Price

Safe Passage at Hormuz: Why Malaysia’s Special Deal with Iran Won't Lower Your Petrol Price

PM Anwar secured safe passage for Malaysian ships, so why is RON95 hitting RM3.87/L? We decode the 400% insurance surge and the new 200L BUDI95 quota.

27-03-2026
Auto News
Fuel Subsidy Update: Your 300L Monthly Quota Could Drop to 200L This April

Fuel Subsidy Update: Your 300L Monthly Quota Could Drop to 200L This April

If you rely on subsidised RON95 petrol to get to work, take note: a major change is coming to your monthly fuel budget.

26-03-2026
Auto News
Fuel Price Shock: Diesel Spikes to RM5.52, Unsubsidised RON95 Jumps 60 Sen

Fuel Price Shock: Diesel Spikes to RM5.52, Unsubsidised RON95 Jumps 60 Sen

Massive 80-sen spike for Diesel (RM5.52) and 60-sen jump for unsubsidised RON95 (RM3.87). Learn how the Budi Madani RM300 aid and BUDI95 quota protect Malaysian drivers this week.

26-03-2026
Auto News
Strait of Hormuz to Malaysia: Why We’re Paying for a War 6,000km Away

Strait of Hormuz to Malaysia: Why We’re Paying for a War 6,000km Away

Why is RON97 at RM4.55/L? We decode the Strait of Hormuz conflict, the May 2026 subsidy deadline, and why Malaysia imports oil despite being a producer.

19-03-2026
Auto News
From 82 Minutes to 8: How the Mutiara Line is Giving Penangites Their Time Back

From 82 Minutes to 8: How the Mutiara Line is Giving Penangites Their Time Back

Is the 80-minute Penang Bridge crawl finally ending? The Mutiara Line LRT links Butterworth to Komtar in just 8 minutes. Get the latest 2026 project updates, station lists, and more.

17-03-2026
Auto News
The 2026 Proton X90 Buyer’s Warning: 5 Critical Safety Features You Are No Longer Getting

The 2026 Proton X90 Buyer’s Warning: 5 Critical Safety Features You Are No Longer Getting

ASEAN NCAP revokes Proton X90’s 5-star rating. The 2026 facelift is downgraded to 1-star after stripping critical ADAS features. Is your family safe? Get the full safety specs here.

16-03-2026
Auto News
9,000+ Drivers Chose Toyota Hybrids This Year: Proof That Toyota’s Multi-Pathway Strategy Works

9,000+ Drivers Chose Toyota Hybrids This Year: Proof That Toyota’s Multi-Pathway Strategy Works

Toyota Malaysia hits 9,556 sales in early 2026, proving the "Multi-Pathway" strategy works. From Vios Hybrid to Vellfire HEV, see why hybrids are winning the sales war.

12-03-2026