ECRL Project In Terengganu Reaches 55% Progress

Jesica Sendai

Share via




Malaysia Railway Link Sdn Bhd said in a statement the construction of East Coast Rail Link (ECRL) Project in Terengganu has reached a progress level of 55.21 percent.  


The route in Terengganu holds the longest line compared to the other three states namely Kelantan, Pahang and Selangor which is 275 KM long from a total of 665 KM and estimated to  cost a sum of RM 50.27 billion. 


So far, the construction work on the said project in Terengganu is set to be on track and scheduled to be fully completed by December 2026.





From there it includes the construction of six stations namely Jerteh, Bandar Permaisuri, Kuala Terengganu and Kemasik which function as passenger stations while Dungun and Chukai are for the purpose of passengers and cargo.


Separately, construction work for the entire 665 KM ECRL line project from Kota Bharu, Kelantan to Port Klang, Selangor has an overall progress level of 40.81 percent, according to Malaysia Rail Link (MRL) CEO Datuk Seri Darwis Abdul Razak. 


"Out of that amount, there are 21 km of tunnels in Selangor and there are approximately 31 km of bridges that will be built in the Selangor line," he added. 





Meanwhile, the East Coast Rail Link (ECRL) project involving the Selangor line is considered to be the most critical compared to the other three states, as reported by local news online.


He further stated that the construction of the C1B alignment in the northern part of the state is seen as complex because it involves various types of construction in addition to bridges and tunnels.


"I say it is critical because we started this ECRL project in 2017, stopped for a while in July 2018 and resumed in April 2019.


‘’We got approval from the state government for us to implement the ECRL project through the northern line starting December 2021 and we can only start construction work with good cooperation from all state and federal departments and agencies which give us approval in June 2022,’’ the exec said. 


The service is expected to be operational in January 2027 and can accommodate 5.6 million passengers a year aside from also can carry 440 passengers for a trip involving six carriages.



Tagged:

ECRL
East Coast Rail Link (ECRL)
ECRL project
Projek Laluan Rel Pantai Timur (ECRL)
Share This Article

Written By

Jesica Sendai

from 9 to 5 grinder to 'racing' her way in the automotive industry through editorial work.

Share via

Related News

Auto News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News
ECRL Project Hits 87% Completion by August 2025 – MoT

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Project Progress Surpasses 56% - Loke

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023

Latest News

Auto News
Updated Fuel Prices From 12 To 18 February

Updated Fuel Prices From 12 To 18 February

The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 12 to 18 February, 2026, the rates are as such.

11-02-2026
Auto News
PLUS Expects 2.2 Million Vehicles Daily During CNY Peak Travel

PLUS Expects 2.2 Million Vehicles Daily During CNY Peak Travel

PLUS is preparing for up to 2.2 million vehicles per day during the CNY, a 16% increase from normal traffic levels.

11-02-2026
Auto News
GWM Wey G9 Receives 800 Bookings Within First Week of Launch

GWM Wey G9 Receives 800 Bookings Within First Week of Launch

The new GWM Wey G9 MPV has received over 800 bookings within the first week of its Malaysian debut.

11-02-2026
Auto News
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations

Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations

The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.

11-02-2026
Auto News
Jan 2026 Auto Sales Down 30%, xEV Penetration Holds at 12.4%

Jan 2026 Auto Sales Down 30%, xEV Penetration Holds at 12.4%

New vehicle registrations fell to 67,995 units in Jan, a seasonal pullback from Dec’s delivery-driven surge.

Auto News
Honda Malaysia Eyes 60,000 Sales, Confirms Six New Models For 2026 Too

Honda Malaysia Eyes 60,000 Sales, Confirms Six New Models For 2026 Too

Honda Malaysia lays out target to shift up to 60,000 units, buoyed by the introduction of six new models too.

10-02-2026
Auto News
KPDN Plans Tighter Controls on RON95 Misuse

KPDN Plans Tighter Controls on RON95 Misuse

KPDN is reviewing legislative changes to prevent fraud and ensure subsidised RON95 benefits only eligible Malaysians.

Auto News
Putrajaya Pulls Plug on ART Plans Due to High Costs

Putrajaya Pulls Plug on ART Plans Due to High Costs

Putrajaya has dropped plans for a trackless ART tram after the RM212 million project was found to be too costly.