ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

Anis

Share via


According to state government staffer Jay Jay Denis, a Chinese construction company responsible for clearing land in Selangor's forest reserves for the East Coast Rail Link (ECRL) project was subject to enforcement action last year for failing to follow standard operating procedures. Despite having a permit to work on the ECRL, China Communications Construction Company (M) Sdn Bhd (CCCC) started construction on that part of the project in Selangor in December of last year before getting the go-ahead from the state Forestry Department.



"They (CCCC) believed they could start working right away because they had the permit, but they actually needed to apply to the department to let authorities know they would be beginning work. When contacted, he explained, "This is so that the department can send personnel to the site to ensure that the proper parts of the forests are being carved out."




The stop-work order and fine that were imposed on the company in December have since been lifted, according to the special officer to Selangor Menteri Besar Datuk Seri Amirudin Shari. "The company was informed in December that they will need to follow the proper administrative procedures in order to start working in the future.


The problem back then was simply that they failed to give a notice (to the department), he said. "If (CCCC) had no permit to operate then, there would definitely have been further legal action," he said. Denis' remarks follow yesterday's statement by state executive councillor Hee Loy Sian that a use permit had been issued by the department in July 2022 for the execution of the ECRL project in the permanent forest reserve area.


The head of the state's Environment, Green Technology, Tourism, and Orang Asli Affairs Committee also stated that on November 30, 2021, Malaysia Rail Link Sdn Bhd, the department of the Finance Ministry in charge of managing the ECRL project, received approval for the environmental impact assessment report for Section C2 (Gombak-Serendah-Port Klang). However, Amirudin had previously claimed that land clearing operations in the state's forest reserves had been carried out "without approval," noting that a police report had been filed against CCCC in December. Denis clarified that Amirudin was not referring to the lack of a permit to work on the project, but rather the lack of approval from the state Forestry Department to start clearing state land.



Amirudin and Hee were responding to a complaint made by the environmental watchdog Rimba Disclosure Project regarding the clearing of land. According to a CCCC spokesman, the organisation has all the necessary approvals and permits from the necessary authorities to move forward with the project. On December 21, Prime Minister Datuk Seri Anwar Ibrahim declared that the ECRL project would now cost RM74.96 billion to complete, down from the initial estimate of RM85.97 billion when the project was first announced in 2017.

He declared that the project to build the 665km-long rail system from Kota Baru in Kelantan to Port Klang in Selangor will move forward.


Tagged:

ECRL
East Coast Rail Link (ECRL)
ECRL project
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023

Latest News

Auto News

CNY 2026: 50% Toll Discount on Second Penang Bridge

50% Toll Discount on Second Penang Bridge, Feb 14–15.

Auto News

PDRM Suggests Making Dashcams Compulsory for All Road Users

PDRM’s Traffic Investigation and Enforcement Department suggests making dashcams compulsory for all road users.

12-02-2026
Auto News

Malaysia Tables RTS Link Bill 2026 to Enable Joint CIQ at JB–Singapore Stations

RTS Link Bill 2026 is set to enable joint customs, immigration, and security operations between Bukit Chagar Station and Woodlands North Station

12-02-2026
Auto News

Updated Fuel Prices From 12 To 18 February

The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 12 to 18 February, 2026, the rates are as such.

11-02-2026
Auto News

PLUS Expects 2.2 Million Vehicles Daily During CNY Peak Travel

PLUS is preparing for up to 2.2 million vehicles per day during the CNY, a 16% increase from normal traffic levels.

11-02-2026
Auto News

GWM Wey G9 Receives 800 Bookings Within First Week of Launch

The new GWM Wey G9 MPV has received over 800 bookings within the first week of its Malaysian debut.

11-02-2026
Auto News

Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations

The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.

11-02-2026
Auto News

Jan 2026 Auto Sales Down 30%, xEV Penetration Holds at 12.4%

New vehicle registrations fell to 67,995 units in Jan, a seasonal pullback from Dec’s delivery-driven surge.