"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

Anis

12-4-2023

Share via



According to Transport Minister Anthony Loke, the East Coast Rail Link (ECRL) is currently 42.06% complete. Loke stated today, while visiting the Genting ECRL Tunnel construction site, that the rail line's construction progress is on track to be completed by December 2026. However, Loke also stated that the ECRL project is currently facing a difficult challenge with the completion of the Genting ECRL tunnel, a twin tunnel spanning 16.39km in length that connects Bukit Tinggi, Pahang with Gombak, Selangor.


According to Loke, the tunnel will be built using a tunnel boring machine (TBM) rather than the drilling and explosives used in other ECRL tunnels. “I am confident with the management and workforce for the ECRL project to complete the project using two TBMs which were made in China. "When the construction crosses the Titiwangsa Range, these highly technological machines will be able to face engineering challenges and geological conditions," Loke said.



Construction on the first Genting tunnel has already begun, and approval to use the TBM for the second tunnel was obtained in November. “Boring works for the first Genting ECRL Tunnel have already reached a depth of 2.602km while the second reached 2.497km.




"For your information, the Genting ECRL Tunnel construction site spans 11.6ha in width and employs over 300 people."


"We hope that by January 2027, the ECRL will be fully operational, saving three hours of travel time from Kota Baru to Gombak," Loke added.

Gallery

Tagged:

ECRL
East Coast Rail Link (ECRL)
ECRL project
ECRL contruction progress
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023
Auto News

ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

Selangor Forestry Department found that the alleged land clearing activities in the Selangor State Park are part of the ECRL project.

06-02-2023
Auto News

Kelantan And Terengganu ECRL Project Affected By Floods

The floods last week impacted around 70% of the construction work at sections 1 and 2 of the East Coast Rail Line (ECRL), which spans 82 kilometres from Tunjong here to Setiu in Terengganu.

28-12-2022
Auto News

ECRL Will Continue - Loke Siew Fook

The federal government will continue the RM50 billion East Coast Rail Link (ECRL) project, according to Loke Siew Fook, the minister of transportation.

07-12-2022

Latest News

Auto News

New Professional Affiliates Programme By Jaecoo Malaysia Targets Professionals And Corporations

Jaecoo Malaysia launches new Professional Affiliates Programme, targets both corporations and professionals through which.

06-05-2025
Auto News

Govt Urged To Delay Targeted RON95 Subsidy Due To US Tariffs

Lawmakers are urging the government to postpone its proposed RON95 subsidy rationalization due to US tariffs.

06-05-2025
Auto News

Toyota GR86 Cup Car On Sale In Malaysia – 30 Units Only, RM208,315 Each

Toyota GR86 Cup Car now in sale locally through Haro Sports and Entertainment Sdn Bhd, just 30 units available at RM208,315 each.

06-05-2025
Auto News

Ekovest Gets Green Light for LIKE and KBL Expressway Projects

Ekovest has received government approval to proceed with the LIKE and KBL expressway projects under its highway expansion plan.

06-05-2025
Auto News

Bukit Kayu Hitam ICQS-Sadao CIQ Project On Track For Completion This Year

Bukit Kayu Hitam ICQS-Sadao CIQ project is 47% finished and expected to be completed by Sept.

06-05-2025
Auto News

Myvi, Yamaha 135LC Most Involved In Accidents, Toyota Hilux Most Stolen

In 2024, the Perodua Myvi and Yamaha 135LC were most frequently involved in accidents, while the Toyota Hilux was the most stolen vehicle.

06-05-2025
Auto News

Sisma Auto Opens New BYD Outlet At IPC

Sisma Auto opens a new BYD showroom outlet located in IPC Shopping Centre, Mutiara Damansara.

05-05-2025
Auto News

Petronas Kimanis Station Trialling RON97 Supply For Bruneians

KPDN and PDB are trialing the sale of RON97 fuel to Bruneian motorists at the Kimanis Petronas Station.

05-05-2025