"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

Anis

Share via



According to Transport Minister Anthony Loke, the East Coast Rail Link (ECRL) is currently 42.06% complete. Loke stated today, while visiting the Genting ECRL Tunnel construction site, that the rail line's construction progress is on track to be completed by December 2026. However, Loke also stated that the ECRL project is currently facing a difficult challenge with the completion of the Genting ECRL tunnel, a twin tunnel spanning 16.39km in length that connects Bukit Tinggi, Pahang with Gombak, Selangor.


According to Loke, the tunnel will be built using a tunnel boring machine (TBM) rather than the drilling and explosives used in other ECRL tunnels. “I am confident with the management and workforce for the ECRL project to complete the project using two TBMs which were made in China. "When the construction crosses the Titiwangsa Range, these highly technological machines will be able to face engineering challenges and geological conditions," Loke said.



Construction on the first Genting tunnel has already begun, and approval to use the TBM for the second tunnel was obtained in November. “Boring works for the first Genting ECRL Tunnel have already reached a depth of 2.602km while the second reached 2.497km.




"For your information, the Genting ECRL Tunnel construction site spans 11.6ha in width and employs over 300 people."


"We hope that by January 2027, the ECRL will be fully operational, saving three hours of travel time from Kota Baru to Gombak," Loke added.

Gallery

Tagged:

ECRL
East Coast Rail Link (ECRL)
ECRL project
ECRL contruction progress
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023
Auto News

ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

Selangor Forestry Department found that the alleged land clearing activities in the Selangor State Park are part of the ECRL project.

06-02-2023
Auto News

Kelantan And Terengganu ECRL Project Affected By Floods

The floods last week impacted around 70% of the construction work at sections 1 and 2 of the East Coast Rail Line (ECRL), which spans 82 kilometres from Tunjong here to Setiu in Terengganu.

28-12-2022

Latest News

Auto News

Couple Killed In Ford Mustang Crash Near Segamat

A married couple died after their Ford Mustang crashed into an electric pole along Jalan Segamat-Kuantan.

05-08-2025
Auto News

Proton e.MAS 5 ‘MISI 5’ National Tour – Aug to Oct, Launching Soon?

The upcoming Proton e.MAS 5 is going on a ‘MISI 5’ national tour from August to October, 2025. Launch imminent?

05-08-2025
Auto News

Ferraris, Lambos Among 1,000 Untaxed Vehicles - JPJ

JPJ flags over 1,000 luxury cars, including Ferraris and Lambos, for missing road tax and insurance.

05-08-2025
Auto News

MoF: Fuel Subsidy Rollout Under Testing, Launches End-Sept

MoF is finalising the targeted fuel subsidy system, with full rollout details expected by end-Sept.

Auto News

KLIA Apologises After Aerotrain Breaks Down Again

KLIA’s Aerotrain stalled for 15 minutes due to a door glitch, prompting an apology and public frustration.

05-08-2025
Auto News

Amir Hamzah: PADU at the Core of RON95 Subsidy Implementation

With over 30 million individual profiles, PADU will guide MOF’s effort to roll out a more precise RON95 petrol subsidy.

Auto News

KPDN Probes SG Driver Sighted Pumping RON95 in Johor

KPDN is probing a viral incident where a Singapore-registered car was seen pumping subsidised RON95 fuel.

Auto News

Traffic Diversion On Bukit Gambir-Tangkak From Aug 5

Traffic along the NSE near Tangkak will be diverted in both directions from Aug 5 for bridge construction.

04-08-2025