Link Copiedcheck_circle
Auto News

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

Anis

Share via




The East Coast Rail Link (ECRL) project's Kuantan Tunnel, which broke ground in October last year, will be completed by the end of April. The 2.8km tunnel located in Jabor, near here, is the longest among the ECRL tunnels in Section B (Dungun-Mentakab), which also includes the 1.1km Paka Tunnel and 871m Dungun Tunnel, both in Terengganu. Wan Kamal Wan Embong, regional construction manager (Section 4 and 5) for Malaysian Rail Link (MRL), stated that the Kuantan Tunnel breakthrough occurred on October 17, last year, two months ahead of schedule.


"The tunnel's completion date is set for April 27. The Kuantan Tunnel runs through both Pahang and Terengganu, with 976 metres in Pahang and the remaining 1,890 metres in Terengganu "he told reporters yesterday during a media visit to the Kuantan Tunnel here. The New Austrian Tunnelling Method (NATM), the world's most widely used underground construction method, is being used in the drilling and blasting work for the Kuantan tunnel project, which began on October 7, 2019. The average height and width of the Kuantan Tunnel are 11.89m and 13.26m, respectively.



The project made use of a Swedish-made double-arm jumbo drilling machine, with tunnelling work beginning in both directions and meeting in the middle. Wan Kamal stated that MRL ensured that all workers strictly adhered to the safety aspects and conditions set by the Department of Occupational Safety and Health (DOSH). "Because tunnel construction required working in a confined space, we had to ensure proper ventilation and control gas emissions inside the tunnel that could endanger the workers. At the peak of the project, 177 workers were on the job "he said, adding that safety was given top priority during the blasting operations.


Closed-circuit television cameras were previously reported to have been installed at the construction site, including inside the tunnel, to monitor worker movement and ensure safety. In terms of the overall progress of the ECRL, Wan Kamal stated that the 665km rail project was 40% completed and was on track to be completed in December 2026. The 210km Dungun-Mentakab main line is also known as Section B, while the other sections are Kota Baru to Dungun (Section A) and Mentakab to Port Klang (Section B) (Section C).


The ECRL, which opened in 2017, will connect the east coast states of Kelantan, Terengganu, and Pahang with the Klang Valley.

Gallery

Tagged:

ECRL
East Coast Rail Link (ECRL)
ECRL project
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Project Progress Surpasses 56% - Loke

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News
ECRL Project In Terengganu Reaches 55% Progress

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News
ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

Selangor Forestry Department found that the alleged land clearing activities in the Selangor State Park are part of the ECRL project.

06-02-2023
Auto News
Kelantan And Terengganu ECRL Project Affected By Floods

Kelantan And Terengganu ECRL Project Affected By Floods

The floods last week impacted around 70% of the construction work at sections 1 and 2 of the East Coast Rail Line (ECRL), which spans 82 kilometres from Tunjong here to Setiu in Terengganu.

28-12-2022

Latest News

Auto News
Couple Killed In Ford Mustang Crash Near Segamat

Couple Killed In Ford Mustang Crash Near Segamat

A married couple died after their Ford Mustang crashed into an electric pole along Jalan Segamat-Kuantan.

05-08-2025
Auto News
Proton e.MAS 5 ‘MISI 5’ National Tour – Aug to Oct, Launching Soon?

Proton e.MAS 5 ‘MISI 5’ National Tour – Aug to Oct, Launching Soon?

The upcoming Proton e.MAS 5 is going on a ‘MISI 5’ national tour from August to October, 2025. Launch imminent?

05-08-2025
Auto News
Ferraris, Lambos Among 1,000 Untaxed Vehicles - JPJ

Ferraris, Lambos Among 1,000 Untaxed Vehicles - JPJ

JPJ flags over 1,000 luxury cars, including Ferraris and Lambos, for missing road tax and insurance.

05-08-2025
Auto News
MoF: Fuel Subsidy Rollout Under Testing, Launches End-Sept

MoF: Fuel Subsidy Rollout Under Testing, Launches End-Sept

MoF is finalising the targeted fuel subsidy system, with full rollout details expected by end-Sept.

Auto News
KLIA Apologises After Aerotrain Breaks Down Again

KLIA Apologises After Aerotrain Breaks Down Again

KLIA’s Aerotrain stalled for 15 minutes due to a door glitch, prompting an apology and public frustration.

05-08-2025
Auto News
Amir Hamzah: PADU at the Core of RON95 Subsidy Implementation

Amir Hamzah: PADU at the Core of RON95 Subsidy Implementation

With over 30 million individual profiles, PADU will guide MOF’s effort to roll out a more precise RON95 petrol subsidy.

Auto News
KPDN Probes SG Driver Sighted Pumping RON95 in Johor

KPDN Probes SG Driver Sighted Pumping RON95 in Johor

KPDN is probing a viral incident where a Singapore-registered car was seen pumping subsidised RON95 fuel.

Auto News
Traffic Diversion On Bukit Gambir-Tangkak From Aug 5

Traffic Diversion On Bukit Gambir-Tangkak From Aug 5

Traffic along the NSE near Tangkak will be diverted in both directions from Aug 5 for bridge construction.

04-08-2025