The East Coast Rail Link (ECRL) project's Kuantan Tunnel, which broke ground in October last year, will be completed by the end of April. The 2.8km tunnel located in Jabor, near here, is the longest among the ECRL tunnels in Section B (Dungun-Mentakab), which also includes the 1.1km Paka Tunnel and 871m Dungun Tunnel, both in Terengganu. Wan Kamal Wan Embong, regional construction manager (Section 4 and 5) for Malaysian Rail Link (MRL), stated that the Kuantan Tunnel breakthrough occurred on October 17, last year, two months ahead of schedule.


"The tunnel's completion date is set for April 27. The Kuantan Tunnel runs through both Pahang and Terengganu, with 976 metres in Pahang and the remaining 1,890 metres in Terengganu "he told reporters yesterday during a media visit to the Kuantan Tunnel here. The New Austrian Tunnelling Method (NATM), the world's most widely used underground construction method, is being used in the drilling and blasting work for the Kuantan tunnel project, which began on October 7, 2019. The average height and width of the Kuantan Tunnel are 11.89m and 13.26m, respectively.



The project made use of a Swedish-made double-arm jumbo drilling machine, with tunnelling work beginning in both directions and meeting in the middle. Wan Kamal stated that MRL ensured that all workers strictly adhered to the safety aspects and conditions set by the Department of Occupational Safety and Health (DOSH). "Because tunnel construction required working in a confined space, we had to ensure proper ventilation and control gas emissions inside the tunnel that could endanger the workers. At the peak of the project, 177 workers were on the job "he said, adding that safety was given top priority during the blasting operations.


Closed-circuit television cameras were previously reported to have been installed at the construction site, including inside the tunnel, to monitor worker movement and ensure safety. In terms of the overall progress of the ECRL, Wan Kamal stated that the 665km rail project was 40% completed and was on track to be completed in December 2026. The 210km Dungun-Mentakab main line is also known as Section B, while the other sections are Kota Baru to Dungun (Section A) and Mentakab to Port Klang (Section B) (Section C).


The ECRL, which opened in 2017, will connect the east coast states of Kelantan, Terengganu, and Pahang with the Klang Valley.

Gallery

Tagged:

ECRL
East Coast Rail Link (ECRL)
ECRL project
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News
ECRL Project Hits 87% Completion by August 2025 – MoT

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Project Progress Surpasses 56% - Loke

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News
ECRL Project In Terengganu Reaches 55% Progress

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023

Latest News

Auto News
New Leapmotor 3S Showroom Opens In Ipoh, Perak

New Leapmotor 3S Showroom Opens In Ipoh, Perak

Perak state capital of Ipoh gains new Leapmotor brand 3S showroom and service outlet operated by dealers CST Auto.

07-11-2025
Auto News
KLIMS 2026 – ‘Beyond Mobility’ Theme Retained, Key Brands Announced

KLIMS 2026 – ‘Beyond Mobility’ Theme Retained, Key Brands Announced

KLIMS 2026 set to retain ‘Beyond Mobility’ theme, over 20 key participating brands confirmed too.

07-11-2025
Auto News
Govt Moves To Tighten FRU Vehicle Safety After Teluk Intan Crash

Govt Moves To Tighten FRU Vehicle Safety After Teluk Intan Crash

The Cabinet is reviewing new safety measures for FRU vehicles following the tragic Teluk Intan crash.

07-11-2025
Auto News
JPJ Targets Firms Hiring Unlicensed Foreign Drivers

JPJ Targets Firms Hiring Unlicensed Foreign Drivers

JPJ will launch operations nationwide to take action against companies employing foreigners without valid driving licences.

07-11-2025
Auto News
MOT Steps Up Public Transport, Road Safety Upgrades

MOT Steps Up Public Transport, Road Safety Upgrades

MOT rolls out new buses, terminals, and safety rules to improve travel and reduce road risks.

07-11-2025
Auto News
CKD Excise Duty Revision: Govt Studying Measures to Ease Impact

CKD Excise Duty Revision: Govt Studying Measures to Ease Impact

Govt exploring ways to cushion a potential 10-30% car price hike once CKD excise duty exemption expires.

Auto News
Loke Urges Malaysians To Clear 5.5 Million Unpaid JPJ Summonses By Year-End

Loke Urges Malaysians To Clear 5.5 Million Unpaid JPJ Summonses By Year-End

Transport Minister Anthony Loke says over 5.5 million JPJ summonses remain unpaid, urges motorists to settle them before year-end too.

Auto News
GWM Malaysia 3rd Anniversary Sees RM150,000 In Rewards Up For Grabs

GWM Malaysia 3rd Anniversary Sees RM150,000 In Rewards Up For Grabs

RM150,000 in rewards, comprised of premium gadgets and more, are up for grabs from GWM Malaysia as it celebrates its third year anniversary.

07-11-2025