Weekly Prasarana Transport Services Report Now Available To The Public

Anis

Share via


The Transport Ministry now wants Prasarana to increase the capacity of the Kelana Jaya line MKBF to at least 1,000,000 passengers by the third quarter of 2026.
Prasarana Malaysia Bhd, the operator of the Klang Valley's commuter rail and bus network, is now sharing its performance indicators with the public in an effort to demonstrate its openness to change and excellence. Previously, Prasarana would only provide weekly updates to the Transport Ministry on key aspects of its rail and bus services. Commuters can now follow Prasarana's progress towards achieving a global indicator for rail service reliability known as Mean Kilometres Between Failures (MKBF), an established international benchmark for determining how well a rail network is run. Any incident that causes a five-minute or longer disruption will be recorded.



Due to the numerous disruptions over the past year, the MKBF of the country's most heavily used LRT line, the Kelana Jaya LRT, is a mere 150,000. The Transport Ministry now wants Prasarana to increase the capacity of the Kelana Jaya line MKBF to at least 1,000,000 passengers by the third quarter of 2026. According to Prasarana, an MKBF of 1,000,000 equates to five to six incidents per year.


"This initiative will immediately improve Prasarana's operational transparency." It will also improve its rail and bus services by identifying areas for improvement and implementing measures to address them in order to meet the company's MKBF target of 1,000,000 by Q3 2026. "The benefit will be passed on to the public in the form of constantly improving service reliability and consistency," said Transport Minister Anthony Loke. Loke agreed last month for Prasarana to make its MKBF report public every month. Prasarana's MKBF target of 1,000,000 currently applies to the Kelana Jaya LRT, Ampang LRT, and Kajang MRT. Because it is only a few kilometres long, the KL Monorail will be given a target of 150,000 passengers. Prasarana recorded an MKBF of between 151,000 and 178,000 for the three lines mentioned above in 2022, while the KL Monorail only achieved 84,000. This means that the Kelana Jaya LRT must be six times more reliable than it is now.

According to Prasarana president and group CEO Mohd Azharuddin Mat Sah, no MKBF target has been set for the Putrajaya MRT because the line is still new and data on its initial performance is still being gathered. Loke claims that the 1,000,000 MKBF target is comparable to that of every other reputable rail operator in the world, including Singapore's SMRT. The most recent MKBF data will be released on the 20th of each month, while updates on ridership, load factor, service reliability, service availability, and station facilities of its rail and bus services will be shared every 5pm Wednesday at myrapid.com.my/rapid-rail-performance.



Tagged:

Prasarana Malaysia Bhd
Prasarana
Prasarana weekly perfromance report
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News

Loke: No ETS For East Coast

Transport Minister Loke confirms ETS will not be extended to the east coast due to single-track, unelectrified rail lines.

Auto News

Prasarana Adds 310 Diesel Buses While Waiting for Electric Fleet

Prasarana updates its fleet with 310 new diesel buses to manage demand while awaiting the rollout of electric buses.

Auto News

New Rapid KL On-Demand New City Centre and University Zones

Rapid KL On-Demand adds new routes linking train stations to key urban and university campus locations.

Auto News

Prasarana Launches New MyRapid Pulse App

Prasarana announced a new, more exciting MyRapid Pulse app, replacing the previous version.

02-05-2025
Auto News

Rapid KL Ends Free Service For Putra Heights Fire Victims

Free van service for Putra Heights Inferno victims provided by Rapid KL has ended as the mosque relief centre closes.

14-04-2025
Auto News

Prasarana Adding 300 On-Demand Vans This Year

Prasarana has announced that it will add 300 new vans to its demand responsive transit (DRT) operations.

20-01-2025
Auto News

New Payment Options For My50 Pass Holders Next Year

My50 pass users will no longer be required to use their MyKad next year, as alternative payment options will be introduced.

11-11-2024
Auto News

LRT 3 Will Cost RM9.7 Billion Less Despite 5 Key Station Reinstatement

LRT 3 will cost RM9.72 Billion less even with the reinstatement of five key stations compared to initial 2015 cost quoted.

Latest News

Auto News

KPDN Probes SG Driver Sighted Pumping RON95 in Johor

KPDN is probing a viral incident where a Singapore-registered car was seen pumping subsidised RON95 fuel.

Auto News

Traffic Diversion On Bukit Gambir-Tangkak From Aug 5

Traffic along the NSE near Tangkak will be diverted in both directions from Aug 5 for bridge construction.

04-08-2025
Auto News

1,489 Summonses Issued in VEP Enforcement Operation – JPJ

JPJ has issued a total of 1,489 summonses during an enforcement operation on VEP at the JB-Singapore land border.

04-08-2025
Auto News

No Green Light Yet For Cross-Border Ride-Hailing Between SG, JB.

Singapore holds off on cross-border ride-hailing plans, opting instead to improve its existing taxi scheme with Malaysia.

04-08-2025
Auto News

RM110 Million Collected from Special Plate Sales Since 2023 – MoT

A total of RM110 million has been collected from sales of special number plates since 2023, the Transport Ministry says.

04-08-2025
Auto News

Nanta: 80% of Accidents Driver-Linked, Road Budget 70% Short

With 80% of accidents linked to drivers, the Works Ministry still grapples with limited funds to fix and rebuild roads.

Auto News

LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report

The LRT3 Shah Alam line opening could be delayed until Oct 31 instead of the planned launch date of Sept 30.

04-08-2025
Auto News

ETS to JB Sentral ‘On Track’, But Not Quite There Yet

KTMB says electrification works between Kluang to JB Sentral are ongoing and the extension will proceed once conditions are met.