ECRL Kelantan Expected To Be Completed Six Months Earlier

Anis

26-6-2023

Share via

image.png The East Coast Rail Link (ECRL) in Kelantan is expected to be completed six months ahead of schedule in January 2027.

Nik Soh Yaacoub, deputy director of the Kelantan Public Works Department, told Bernama that the project has reached 61.97 percent completion with a total workforce of 1,500. He stated that the project's current status included bridge construction, land reclamation, and piling, as well as the start of construction on the state's first ECRL station.

Nik Soh is confident that the project will be completed six months ahead of schedule due to the progress of the work being done by China Communications Construction Company Ltd (CCCC) and Malaysia Rail Link (MRL). image.png

"The seriousness demonstrated by CCCC and MRL, as well as the technological sophistication used in implementing this project, is one of the contributors to the project's rapid implementation," he said.

Furthermore, Nik Soh stated that the technology brought by CCCC not only saves time in completing projects but also saves manpower.

"In terms of the iron fabrication process, new technology is used, which saves time and manpower." Furthermore, it is possible to maintain cleanliness while reducing waste production.

image.png


"With the initial expectation that construction of the project will be completed, this facility can also be used indirectly by the community, especially when Kelantan hosts the Malaysian Games (SUKMA) in 2026," he said.

Source: Bernama

Gallery

Tagged:

ECRL
East Coast Rail Link (ECRL)
ECRL contruction progress
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023
Auto News

ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

Selangor Forestry Department found that the alleged land clearing activities in the Selangor State Park are part of the ECRL project.

06-02-2023
Auto News

Kelantan And Terengganu ECRL Project Affected By Floods

The floods last week impacted around 70% of the construction work at sections 1 and 2 of the East Coast Rail Line (ECRL), which spans 82 kilometres from Tunjong here to Setiu in Terengganu.

28-12-2022
Auto News

ECRL Will Continue - Loke Siew Fook

The federal government will continue the RM50 billion East Coast Rail Link (ECRL) project, according to Loke Siew Fook, the minister of transportation.

07-12-2022

Latest News

Auto News

Special Models & Prizes Await at BAuto’s MAS 2025 Showcase

Visitors to Bermaz Auto’s showcase at the upcoming Malaysia Autoshow 2025 can stand a chance to win exclusive merchandise.

07-05-2025
Auto News

Motorcyclists Make Up 70% Of Yearly Fatal Accidents - VTAREC

Motorcyclists make up 70% of the roughly 6,000 yearly road fatalities, yet they are responsible for only about 13% of accidents.

07-05-2025
Auto News

Proton Posts Strong April Sales, e.MAS 7 Leads EV Market

Proton recorded a 14.7% YOY sales growth in April 2025, buoyed by strong demand for e.MAS 7 EV.

06-05-2025
Auto News

Malaysia Autoshow 2025 Charges Up Ahead Of May 9 Opening Day

Malaysia Autoshow 2025 (MAS 202) gears up as May 9 opening day looms closer, tickets are still available online from RM20 onwards.

06-05-2025
Auto News

ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals

ECRL, Malaysia’s largest rail project is nearing completion, with passenger service set to begin by Jan 2027.

06-05-2025
Auto News

Man Warns About Car Battery Thefts Near Glenmarie LRT Station

A TikTok video by @bateriku.com_ttdi warns the public about increased car battery thefts near the Glenmarie LRT station.

06-05-2025
Auto News

New Professional Affiliates Programme By Jaecoo Malaysia Targets Professionals And Corporations

Jaecoo Malaysia launches new Professional Affiliates Programme, targets both corporations and professionals through which.

06-05-2025
Auto News

Toyota GR86 Cup Car On Sale In Malaysia – 30 Units Only, RM208,315 Each

Toyota GR86 Cup Car now in sale locally through Haro Sports and Entertainment Sdn Bhd, just 30 units available at RM208,315 each.

06-05-2025