Ampang/Sri Petaling LRT Line Repair Completion Delayed Till February 2024

KS

29-9-2023

Share via

AmpangSri-Petaling-LRT-Line-Caricarz-(2).jpg

Rapid Rail Sdn Bhd (Rapid Rail), the operator of the Ampang/Sri Petaling LRT Line, announced that the comprehensive repair work (Phase 2) on the viaduct structure and tracks near the Bandaraya LRT Station is delayed and is expected to be completed, and normal operations resume on 29 February 2024.

The original plan for completing the repair work and restoring normal operations on this route was in mid-October 2023. However, the additional time is necessary because, in addition to the initial damage to viaduct 163, several other damages have been identified on nearby viaduct structures, namely viaducts 164 and 165, which require thorough repairs.

AmpangSri-Petaling-LRT-Line-Caricarz-(1).jpeg

After consulting with engineering experts, additional work is required on these viaduct structures to ensure they are safe, meet specifications, and can fulfil the criteria for normal safe operations.

These repair works also involve consultation, assessment, and approval from the Department of Irrigation and Drainage (JPS) of the Federal Territories, as support structures need to be installed along the Klang River adjacent to the affected LRT viaducts.

AmpangSri-Petaling-LRT-Line-Caricarz-(1).jpg

Safety considerations are a top priority for all parties involved in carrying out these high-risk tasks and this additional work has extended the timeline for the restoration work by 3 months.

Rapid Rail is extending its apologies for the inconvenience experienced by commuters. The decision to extend the timeline for the restoration work is to ensure that all damages are identified and repaired to guarantee the safety of public transportation operations and users.


Tagged:

Ampang/Sri Petaling LRT
LRT Ampang line
Bandaraya LRT Station
apid Rail Sdn Bhd (Rapid Rail)
Share This Article

Written By

KS

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well! https://www.linkedin.com/in/kumeran-sagathevan/

Share via

Related News

Auto News

Sri Petaling LRT Line Will Resume Operations On 29 February

Repairs to specific stations along the Sri Petaling LRT line will be completed by the end of February 2024, says Rapid KL.

07-01-2024
Auto News

Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months

Ampang/Sri Petaling LRT repair work would take up to seven months to complete.

22-02-2023
Auto News

LRT Ampang, Sri Petaling Line Will Get Women’s Coach From Dec 31

RapidKL has announced the implementation of women-only coaches on the LRT Ampang/Sri Petaling line, which will begin on December 31, 2024.

24-12-2024
Auto News

Direct Service From Ampang, Putra Heights LRT Stations To Masjid Jamek Resumes

LRT passengers from the Ampang and Putra Heights lines can continue their journey to Masjid Jamek effective today.

01-02-2024
Auto News

Park N Ride Facilities At Ampang & Gombak LRT Station Now Uses ‘Pay & Go App’ Parking Payment

RapidKL announced Park & Ride facilities at Ampang and Gombak LRT Station will now utilise an automatic number plate recognition (ANPR) system.

04-04-2023
Auto News

Bandaraya-Masjid Jamek LRT Line Closed For Two Weeks - Loke

Ampang LRT line will be closed between the Bandaraya and Masjid Jamek stations for about two weeks.

02-02-2023
Auto News

Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months

Ampang/Sri Petaling LRT repair work would take up to seven months to complete.

22-02-2023

Latest News

Auto News

Motorcyclists Make Up 70% Of Yearly Fatal Accidents - VTAREC

Motorcyclists make up 70% of the roughly 6,000 yearly road fatalities, yet they are responsible for only about 13% of accidents.

07-05-2025
Auto News

Proton Posts Strong April Sales, e.MAS 7 Leads EV Market

Proton recorded a 14.7% YOY sales growth in April 2025, buoyed by strong demand for e.MAS 7 EV.

06-05-2025
Auto News

Malaysia Autoshow 2025 Charges Up Ahead Of May 9 Opening Day

Malaysia Autoshow 2025 (MAS 202) gears up as May 9 opening day looms closer, tickets are still available online from RM20 onwards.

06-05-2025
Auto News

ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals

ECRL, Malaysia’s largest rail project is nearing completion, with passenger service set to begin by Jan 2027.

06-05-2025
Auto News

Man Warns About Car Battery Thefts Near Glenmarie LRT Station

A TikTok video by @bateriku.com_ttdi warns the public about increased car battery thefts near the Glenmarie LRT station.

06-05-2025
Auto News

New Professional Affiliates Programme By Jaecoo Malaysia Targets Professionals And Corporations

Jaecoo Malaysia launches new Professional Affiliates Programme, targets both corporations and professionals through which.

06-05-2025
Auto News

Govt Urged To Delay Targeted RON95 Subsidy Due To US Tariffs

Lawmakers are urging the government to postpone its proposed RON95 subsidy rationalization due to US tariffs.

06-05-2025
Auto News

Toyota GR86 Cup Car On Sale In Malaysia – 30 Units Only, RM208,315 Each

Toyota GR86 Cup Car now in sale locally through Haro Sports and Entertainment Sdn Bhd, just 30 units available at RM208,315 each.

06-05-2025