Over 70 Percent Of ECRL Project Completed - Loke

Anis

Share via

ECRL-56-Completion-Minister-Loke-full.jpg According to Transport Minister Anthony Loke, the East Coast Rail Link (ECRL) project, which spans four states (Pahang, Kelantan, Terengganu, and Selangor), is currently 70.13 percent complete. The government is optimistic that ECRL operations from Gombak to the East Coast, specifically Pahang, Terengganu, and Kelantan, will be able to start in early 2027 because the construction is proceeding without hiccups and in accordance with the planned timeline. FW1295812_KB02_25032023_ECRL-scaled-e1680489263316.jpg
Photo: Bernama.

The minister stated that construction in Kelantan, Terengganu, and Pahang is well underway. In Selangor, it is in its early stages, with more than 30%. However, according to the schedule, ECRL operations will begin in January 2027, and the route from Kota Bharu to LRT Gombak will be completed by the end of 2026. 03-page-3-chung_2257706_20220325074846-(1)-full.jpg

“A year later, the track from Gombak to Port Klang will be completed. Indeed, the track connecting the port in Port Klang to the East Coast is quite important because it will reach our main port for cargo transportation,” he added.
He continued by saying that cargo transportation, along with the tracks and infrastructure, is a crucial part of the ECRL because it will benefit the East Coast's industrial sector greatly, particularly Pahang.

Tagged:

ECRL project
East Coast Rail Link (ECRL)
ECRL contruction progress
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News

ECRL Extension from Kota Bharu to Pasir Mas Under Review

Kelantan is pushing for the ECRL to extend to Rantau Panjang, eyeing cross-border rail links with Thailand.

23-07-2025
Auto News

Kuantan-Bound KL-Karak Lanes Diverted For ECRL Work Until Aug 31

Kuantan-bound lanes (KM25.75–KM26.39) are being diverted for ECRL works until Aug 31.

10-07-2025
Auto News

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News

ECRL Finishes Excavation Of 30 Tunnels Ahead Of Schedule

The ECRL project made three tunnel breakthroughs in a single day in the Bentong district and finished excavating 30 tunnels along its rail alignment.

14-03-2024
Auto News

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News

Jalan Kuala Terengganu-Kuantan Closed For ECRL Works

The Dungun district police has announced a road closure on Jalan Kuala Terengganu-Kuantan for ECRL project.

03-04-2023

Latest News

Auto News

Ferrari’s 16-Year Marketing Chief Stepped Down—But Was It Really His Choice?

Ferrari’s 16-year marketing lead has stepped down following the controversial Luce EV launch. Was this a planned exit or a high-profile design disaster casualty?

26-06-2026
Auto News

Foreigners Are Using Local MyKads to Buy Vehicles—And Leaving Locals With a Legal Nightmare

Think renting your car to a foreigner is easy money? Think again. JPJ's Ops PeWA is seizing vehicles and hauling local owners to court. Learn the risks.

26-06-2026
Auto News

From 80 Sen To RM4.30: A Simple Breakdown Of The New LRT3 Fares

Planning to ride the new LRT3? Get a simple breakdown of the Shah Alam Line fares.

25-06-2026
Auto News

BUDI Diesel Explained: 200L Quota, No Deadlines, And The New 'Approved Person' Rule You Need To Know

Confused by the new RM2.10 diesel subsidy? Our ultimate guide covers quotas, how to claim your extra 100L, and the latest 'Approved Person' rules.

25-06-2026
Auto News

RM500 Saman & Jail For Racing? 5 Massive Traffic Law Changes Coming To Malaysia

Transport Minister Anthony Loke tables the Road Transport (Amendment) Bill 2026. Here are 5 massive proposed traffic law changes coming to Malaysia.

24-06-2026
Auto News

Government Pouring RM25.2 Million To Light Up 32 Dangerous Stretches So We Don't Have To Drive Blind At Night

The Ministry of Works approved RM25.24 mil to install 3,000 solar LED streetlights at 32 hazardous highway blackspots by November 2026. Is your route on the list?

24-06-2026
Auto News

"Not Our Priority" — Minister Reveals The 4 Major Road Crimes JPJ Is Hunting Instead Of Sunshades

Transport Minister Anthony Loke clarifies that JPJ will not target motorists using removable car window sunshades, choosing instead to focus enforcement priorities on illegal racing, mat rempit, drunk driving, and reckless driving.

22-06-2026
Auto News

M'sia Is Moving Toward Barrier-Free Tolls, But Gov Just Dropped One Non-Negotiable Rule

Works Minister Datuk Seri Alexander Nanta Linggi reveals that while Malaysia's barrier-free MLFF toll system negotiations are advanced, the government has set a strict, non-negotiable condition: road users must not pay higher toll fares.

22-06-2026