ECRL Project Progress Surpasses 56% - Loke

Anis

Share via

ECRL-56-Completion-Minister-Loke.jpg

Transport Minister Anthony Loke Siew Fook announced that the East Coast Rail Link (ECRL) project has surpassed 56% of its progress as of November, marking a significant milestone.
This development is in line with the project's completion schedule, which calls for the Gombak Integrated Terminal to be completed by December 2026, and the location of Kota Bharu in Kelantan. By January 2027, operational readiness is expected to be achieved.

Minister Loke stressed the project's transition into a new construction phase, involving flyover beam installations, train station, and depot constructions, highlighting this year as the peak construction phase.

According to The Star, the minister also emphasizes that in order to facilitate passenger and cargo train operations, future stages will concentrate on electrification, signaling, and telecommunication system installations. 03-page-3-chung_2257706_20220325074846-(1).jpg

When it's completed, residents of Kuantan will only need to travel 1.5 hours to get to Kuala Lumpur instead of the three hours it takes now by road. Minister Loke highlighted that 23,000 laborers were involved in 1,900 construction sites, with drill and blast techniques being used to excavate 26 tunnels.

One of the major turning points will be the 16.39 km Genting twin tunnel, which is currently under construction and should be finished in the second quarter of 2025. More than 60km of flyover beams have been installed over the 145km ECRL flyover. The project's overall goal is to improve transportation infrastructure in Pahang, Terengganu, Kelantan, and Selangor by building 20 stations.




Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VQF3625

SELANGOR

BSL2681

JOHOR

JYN6170

PULAU PINANG

PRX184

PERAK

APD6394

PAHANG

CFE5664

KEDAH

KGD5779

NEGERI SEMBILAN

NEJ1098

KOTA KINABALU

SJP4608

KUCHING

QAB8443M

Last updated 27 Dec, 2025

Fuel Price

Petrol

RON 95

RM 2.64

-0.02

RON 97

RM 3.27

-0.02

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 3.06

-0.02

EURO 5 B7

RM 3.26

-0.02

Last updated 11 Dec, 2025

Related News

Auto News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News
ECRL Project Hits 87% Completion by August 2025 – MoT

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News
ECRL Project In Terengganu Reaches 55% Progress

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023

Latest News

Auto News
Ops Lancar: Johor Police Issue Over 4,400 Summonses In Two Days

Ops Lancar: Johor Police Issue Over 4,400 Summonses In Two Days

Johor police issued 4,433 traffic summonses in just the first two days of their Christmas and New Year road operations.

26-12-2025
Auto News
MOF Extends OMV Relief: CKD Vehicle Prices Safe Until June 2026

MOF Extends OMV Relief: CKD Vehicle Prices Safe Until June 2026

MOF confirms that non-manufacturing costs under OMV remain fully excise-exempt for another six-months.

Auto News
iCaur V23 Earns 5-Star ASEAN NCAP Rating

iCaur V23 Earns 5-Star ASEAN NCAP Rating

Newly launched iCaur V23 EV SUV posts strong 91.02-point score in ASEAN NCAP 2021–2025 protocol crash-tests.

Auto News
Chery Tiggo 7 PHEV Earns 5-Star ASEAN NCAP Score

Chery Tiggo 7 PHEV Earns 5-Star ASEAN NCAP Score

Chery Tiggo 7 PHEV C-SUV earns 5-star ASEAN NCAP rating, posting an impressive 94.68-point score.

Auto News
Updated Fuel Prices From 25 To 31 December

Updated Fuel Prices From 25 To 31 December

The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 25 to 31 December, 2025, the rates are as such.

Auto News
Malaysian EV Market Buzzing Ahead Of Year-End Tax Changes

Malaysian EV Market Buzzing Ahead Of Year-End Tax Changes

EV registrations jump as buyers rush to beat the fully imported tax exemption, with Tesla, BYD, and Proton leading the charge.

24-12-2025
Auto News
DBKL Deploys Smart Traffic Light System Worth RM42 Million

DBKL Deploys Smart Traffic Light System Worth RM42 Million

DBKL deploys and maintains new ITMAX adaptive, data-driven smart traffic light systems across Kuala Lumpur.

Auto News
Penang Expects 2.2M Vehicles This Christmas, School Holidays

Penang Expects 2.2M Vehicles This Christmas, School Holidays

More than 2.2 million vehicles are expected to enter Penang during the Christmas season and school holidays.

24-12-2025

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.