ECRL Project Progress Surpasses 56% - Loke

Anis

Share via

ECRL-56-Completion-Minister-Loke.jpg

Transport Minister Anthony Loke Siew Fook announced that the East Coast Rail Link (ECRL) project has surpassed 56% of its progress as of November, marking a significant milestone.
This development is in line with the project's completion schedule, which calls for the Gombak Integrated Terminal to be completed by December 2026, and the location of Kota Bharu in Kelantan. By January 2027, operational readiness is expected to be achieved.

Minister Loke stressed the project's transition into a new construction phase, involving flyover beam installations, train station, and depot constructions, highlighting this year as the peak construction phase.

According to The Star, the minister also emphasizes that in order to facilitate passenger and cargo train operations, future stages will concentrate on electrification, signaling, and telecommunication system installations. 03-page-3-chung_2257706_20220325074846-(1).jpg

When it's completed, residents of Kuantan will only need to travel 1.5 hours to get to Kuala Lumpur instead of the three hours it takes now by road. Minister Loke highlighted that 23,000 laborers were involved in 1,900 construction sites, with drill and blast techniques being used to excavate 26 tunnels.

One of the major turning points will be the 16.39 km Genting twin tunnel, which is currently under construction and should be finished in the second quarter of 2025. More than 60km of flyover beams have been installed over the 145km ECRL flyover. The project's overall goal is to improve transportation infrastructure in Pahang, Terengganu, Kelantan, and Selangor by building 20 stations.




Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VQX3295

SELANGOR

BSP8730

JOHOR

JYW4033

PULAU PINANG

PSC1679

PERAK

APH3575

PAHANG

CFG4612

KEDAH

KGF8039

NEGERI SEMBILAN

NEK3670

KOTA KINABALU

SJR8269

KUCHING

QAB7403N

Last updated 14 May, 2026

Fuel Price

Petrol

RON 95

RM 3.97

+1.38

RON 97

RM 4.90

+1.75

RON 100

RM 7.20

+2.20

VPR

RM 8.23

+2.00

Diesel

EURO 5 B10

RM 5.12

+2.08

EURO 5 B7

RM 5.32

+2.08

Last updated 30 Apr, 2026

Related News

Auto News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News
ECRL Project Hits 87% Completion by August 2025 – MoT

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News
ECRL Project In Terengganu Reaches 55% Progress

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023

Latest News

Auto News
First 300L, Now 200L... Is 150L Inevitable? A Look At The Future Of Budi Madani

First 300L, Now 200L... Is 150L Inevitable? A Look At The Future Of Budi Madani

Is the 150L petrol quota coming? We break down the "taken out of context" Budi95 news and why Malaysia's RM7 billion subsidy bill makes a future cut a real possibility.

13-05-2026
Auto News
5 Shocking Numbers That Explain Why Proton Is Exiting Its Distribution Deal In South Africa

5 Shocking Numbers That Explain Why Proton Is Exiting Its Distribution Deal In South Africa

Proton's South African distributor, CMH Group, confirms the termination of its agreement. From selling only 7 cars in April to the rise of Geely, here are 5 numbers you need to see.

13-05-2026
Auto News
It’s Not Just About Income'—Economy Ministry Responds To Concerns That T20 Are Being 'Unfairly' Cut Off

It’s Not Just About Income'—Economy Ministry Responds To Concerns That T20 Are Being 'Unfairly' Cut Off

Is the T20 being unfairly cut off from RON95 subsidies? Economy Ministry clarifies how PADU will use household needs, not just income, for targeted fuel subsidies in Malaysia.

12-05-2026
Auto News
Bankrupt Or Safe? Take This Quiz To See Your New Motor Insurance Fate

Bankrupt Or Safe? Take This Quiz To See Your New Motor Insurance Fate

Will your driving habits save you money or break the bank? Take our quiz to see how Malaysia’s new 'risk-based' motor insurance rules from PIAM could affect your premiums.

12-05-2026
Auto News
Cheap Petrol For T20? Its Days Are Numbered. PM Anwar Drops New Update

Cheap Petrol For T20? Its Days Are Numbered. PM Anwar Drops New Update

PM Anwar confirms the T20 fuel subsidy cut is in its final stages. Find out how the T20, B40 and M40 groups are affected by the new RON95 rationalisation.

11-05-2026
Auto News
Why You Might Be Rejected (And Why You Won't): Decoding JPJ’s New License Conversion Categories

Why You Might Be Rejected (And Why You Won't): Decoding JPJ’s New License Conversion Categories

Returning to Malaysia? Starting June 1, 2026, you can convert your foreign driving license to a JPJ license without retaking the test. We decode the new SOPs, eligibility rules, and common reasons for rejection.

08-05-2026
Auto News
"Wait, Why Is It Taking So Long?" — 4 Things Slowing Down The Pan Borneo Highway In Sabah Right Now

"Wait, Why Is It Taking So Long?" — 4 Things Slowing Down The Pan Borneo Highway In Sabah Right Now

Why is the Pan Borneo Highway taking so long? Chief Minister Hajiji Noor reveals 4 main constraints slowing down Phase 1B from Sandakan to Lahad Datu.

07-05-2026
Auto News
No More Cheap Fuel For T20? Economists Suggest Cutting Them From BUDI95 To Save RM1.5B

No More Cheap Fuel For T20? Economists Suggest Cutting Them From BUDI95 To Save RM1.5B

Economists suggest excluding the T20 from the BUDI95 scheme to save Putrajaya RM1.5 billion monthly. Learn how targeted RON95 subsidies could change your petrol bill.

05-05-2026

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2026 CariCarz.com. All Rights Reserved.