The East Coast Rail Link (ECRL) project is now 82.45% complete as of April 2025. The 665km railway is on track, with the Kota Bharu–Gombak stretch due by Dec 2026 and the Gombak–Port Klang section by Dec 2027.

Track installation from Maran to Kota Bharu, spanning 400 KM, finished ahead of schedule with work on the Maran–Bentong stretch beginning this month and is set to complete by June.

Electrification works started in May 2024, with over 9,000 OCS poles installed and around 2,700 left. Tunnel boring has reached 38 of 41 tunnels, with the 16.39km Genting Twin Tunnel expected to break through in Q3 this year.


GoqT8wbbMAAWTGk.jpeg


Station construction is progressing well and is set for completion by mid-2026. Testing and commissioning of the system will begin in June 2026.

Transport Minister YB Anthony Loke Siew Fook shared these updates during the launch of the ECRL’s Operations & Maintenance (O&M) workforce training under the PLKI-ECRL programme.

Once operational in January 2027, the ECRL will require around 1,800 workers, with 80% being Malaysians. The aim is to build a skilled local workforce for modern rail operations.

The PLKI-ECRL programme is now focused on training for the O&M phase. A total of 3,200 trainees will benefit, starting with 210 Malaysians this year.


GoqT9UCacAI3zXE.jpeg


Of that, 102 trainees will begin one-year training in Liuzhou, China, from 15 May. They’ll learn technical and operational skills for various ECRL roles.

Trainees are guaranteed jobs upon completion and the programme is supported by a RM12 million sponsorship from China Communications Construction Company Ltd (CCCC).


495463645_1267422871405944_6737999489992028850_n.jpg


ECRL will use 11 EMU train sets and 12 electric locomotives from CRRC Dalian. The first units are expected by year-end. These new trains will run up to 160 km/h, cutting travel time from Kota Bharu to Gombak to just four hours.

Loke also added that ECRL will help shift cargo from road to rail - an eco-friendly, cost-effective move in line with national transport goals.

He added that efforts are underway to ensure passenger fares remain affordable when operations begin.



Tagged:

East Coast Rail Link (ECRL)
China Communications Construction Company Ltd (CCCC)
Electric Multiple Unit (EMU)
ECRL Operations & Maintenance (O&M)
Minister of Transport YB Anthony Loke
Share This Article

Written By

Kumeran Sagathevan

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

Related News

Auto News

ECRL First EMU Trains, E-Locos Head To Malaysia For Testing

Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.

17-12-2025
Auto News

First ECRL Trains Depart China, Remaining Units Arriving Through 2026

First ECRL trains depart China, with remaining units scheduled to arrive through 2026.

28-11-2025
Auto News

ECRL Nears Completion with 89% Progress, Operations Set for 2027

ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.

Auto News

ECRL Trains Fully Assembled, Ready for Malaysia

The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.

21-11-2025
Auto News

ECRL Hits 88% Milestone As Key C1B Stretch Completed

The ECRL project has hit 88% completion with the C1B Segment now successfully completed.

05-11-2025
Auto News

ECRL Project On Track Despite RM2.9mil Theft Losses

MRL boosts security after 38 theft cases but says the ECRL project remains on schedule.

30-10-2025
Auto News

MOT Eyes Rail Expansion, Road Safety and Airport Improvements

Transport Minister YB Loke Siew Fook outlines major transport projects and safety reforms under the 2026 Budget.

Auto News

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025

Latest News

Auto News

UPSI Bus Crash: Brake Fade, Speed Cited as Key Factors

Mechanical faults, speeding, and poor oversight behind deadly Gerik bus crash, according to report.

23-01-2026
Auto News

Volvo Teases ES90 Launch With ‘SELAMAT’ Campaign

Volvo Malaysia briefly presented “SELAMAT” as a new brand before revealing it as a safety-themed teaser campaign ahead of the ES90 launch.

23-01-2026
Auto News

LEPAS Confirms 20-Outlets Ahead of 2026 Malaysia Launch

LEPAS signals serious intent ahead of its 2026 launch, confirming 20 sales and service outlets across Malaysia.

Auto News

JPJ Lifts Travel Proof Rule for Physical Driving Licence

JPJ lifts the travel proof rule, allowing motorists to apply for a physical licence without overseas travel justification.

Auto News

KL’s Lalaport Hub Nears Approval for Singapore Express Buses

KL’s Lalaport transport hub nears approval, set to streamline express bus travel to Singapore by February.

22-01-2026
Auto News

Overloaded Lorry Crackdown Reduces Road Deaths

Stricter JPJ checks on overloaded lorries are helping make Malaysian roads safer with fewer fatal accidents.

22-01-2026
Auto News

Bukit Chagar RTS Link Station Roof Completed, Final Facade Works Underway

Bukit Chagar station reaches a major milestone as the RTS Link roof is completed.

22-01-2026
Auto News

Puspakom - New Brake Inspection Rules for Heavy Vehicles

Puspakom’s new brake inspection rules for heavy vehicles target unsafe brake settings that increase accident risks.