Kelantan And Terengganu ECRL Project Affected By Floods

The floods last week impacted around 70% of the construction work at sections 1 and 2 of the East Coast Rail Line (ECRL), which spans 82 kilometres from Tunjong here to Setiu in Terengganu.
Mohd Azemi Abdullah, construction manager of Malaysia Rail Link Sdn Bhd (MRL) (sections 1 and 2), stated that the impacted regions entailed preliminary operations such as forest removal and were in low-lying areas.
"The earthworks have been impacted by rainwater (flooding), and we are unable to work," he told reporters yesterday after presenting donations to flood victims at the Bukit Abal Penggawa office. Mohd Azemi, on the other hand, stated that the floods had no effect on the construction activity, including the bridge construction.
"We only have to stop operations if it rains, except for work at a height of more than 2m from the ground level," he explained.
According to reports, Kelantan suffered heavy rainfall last week, inundating numerous areas of the state.
On December 18, the state Drainage and Irrigation Department recorded 627mm of rainfall intensity in Kampung Wakaf Raja, Bukit Yong near Pasir Puteh, the highest since 1967.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQQ1659
SELANGOR
BSN3367
JOHOR
JYT1498
PULAU PINANG
PSA4874
PERAK
APF9094
PAHANG
CFF7343
KEDAH
KGE7324
NEGERI SEMBILAN
NEJ7530
KOTA KINABALU
SJQ7590
KUCHING
QAB4013N
Last updated 14 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
Latest News
9,000+ Drivers Chose Toyota Hybrids This Year: Proof That Toyota’s Multi-Pathway Strategy Works
Toyota Malaysia hits 9,556 sales in early 2026, proving the "Multi-Pathway" strategy works. From Vios Hybrid to Vellfire HEV, see why hybrids are winning the sales war.
12-03-2026
Chery Tiggo 7 is Now the Safest Chinese SUV on the Planet, This Is Why
The Chery Tiggo 7 makes history as the only Chinese SUV to sweep 5-star ratings from Euro NCAP, ANCAP, and ASEAN NCAP. With a record 94.68 points, see why this is 2026’s safest family SUV.
11-03-2026
Sepang Dates Confirmed: Catch Team Porsche Malaysia in Action on 21–23 August
While the 2026 Porsche Carrera Cup Asia (PCCA) season kicks off in Shanghai this weekend, Malaysian fans are already looking ahead to the highlight of the year: the homecoming.
10-03-2026
Iran-US War Day 10: It’s Not Just Fuel — Malaysia’s Automotive Industry Faces New Risks
While the BUDI95 subsidy program is already feeling the heat of oil prices flirting with US$120 a barrel, the true threat to our automotive sector lies beneath the surface.
09-03-2026
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far
The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.
05-03-2026
EV King is Here: How Proton e.MAS 5 Dethroned Popular Petrol Cars in 60 Days
PRO-NET has announced that the Proton e.MAS 5 has officially surpassed the 5,000-unit delivery milestone in just two months.
05-03-2026
Wolfgang Egger’s Masterpiece: Denza Z9 GT Confirmed for Malaysia Launch in Q2 2026
BYD Malaysia has officially confirmed that the Denza Z9 GT is set to launch in the local market in early 2026 (expected Q2). As the flagship luxury "shooting brake" for the brand, the Z9 GT is designed to offer a tech-forward alternative to the Porsche Panamera and BMW 5 Series Touring.
03-03-2026
Kelana Jaya LRT trains “out of service” but line running normally - RapidRail
Rapid Rail clarified that temporary train withdrawals on the Kelana Jaya LRT line are part of standard safety procedures.
27-02-2026
Show More
trending_flat