ENZHMS
Link Copiedcheck_circle
Auto News

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

Anis

Share via




The East Coast Rail Link (ECRL) project's Kuantan Tunnel, which broke ground in October last year, will be completed by the end of April. The 2.8km tunnel located in Jabor, near here, is the longest among the ECRL tunnels in Section B (Dungun-Mentakab), which also includes the 1.1km Paka Tunnel and 871m Dungun Tunnel, both in Terengganu. Wan Kamal Wan Embong, regional construction manager (Section 4 and 5) for Malaysian Rail Link (MRL), stated that the Kuantan Tunnel breakthrough occurred on October 17, last year, two months ahead of schedule.


"The tunnel's completion date is set for April 27. The Kuantan Tunnel runs through both Pahang and Terengganu, with 976 metres in Pahang and the remaining 1,890 metres in Terengganu "he told reporters yesterday during a media visit to the Kuantan Tunnel here. The New Austrian Tunnelling Method (NATM), the world's most widely used underground construction method, is being used in the drilling and blasting work for the Kuantan tunnel project, which began on October 7, 2019. The average height and width of the Kuantan Tunnel are 11.89m and 13.26m, respectively.



The project made use of a Swedish-made double-arm jumbo drilling machine, with tunnelling work beginning in both directions and meeting in the middle. Wan Kamal stated that MRL ensured that all workers strictly adhered to the safety aspects and conditions set by the Department of Occupational Safety and Health (DOSH). "Because tunnel construction required working in a confined space, we had to ensure proper ventilation and control gas emissions inside the tunnel that could endanger the workers. At the peak of the project, 177 workers were on the job "he said, adding that safety was given top priority during the blasting operations.


Closed-circuit television cameras were previously reported to have been installed at the construction site, including inside the tunnel, to monitor worker movement and ensure safety. In terms of the overall progress of the ECRL, Wan Kamal stated that the 665km rail project was 40% completed and was on track to be completed in December 2026. The 210km Dungun-Mentakab main line is also known as Section B, while the other sections are Kota Baru to Dungun (Section A) and Mentakab to Port Klang (Section B) (Section C).


The ECRL, which opened in 2017, will connect the east coast states of Kelantan, Terengganu, and Pahang with the Klang Valley.

Gallery

Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VPS4837

SELANGOR

BSH7994

JOHOR

JYG7734

PULAU PINANG

PRU1304

PERAK

APB2529

PAHANG

CFD4893

KEDAH

KGC3042

NEGERI SEMBILAN

NEH1367

KOTA KINABALU

SJM6247

KUCHING

QAB1740M

Last updated 19 Sep, 2025

Fuel Price

Petrol

RON 95

RM 2.05

RON 97

RM 3.21

+0.03

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.93

+0.03

EURO 5 B7

RM 3.13

+0.03

Last updated 18 Sep, 2025

Related News

Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Project Progress Surpasses 56% - Loke

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News
ECRL Project In Terengganu Reaches 55% Progress

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News
ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

Selangor Forestry Department found that the alleged land clearing activities in the Selangor State Park are part of the ECRL project.

06-02-2023
Auto News
Kelantan And Terengganu ECRL Project Affected By Floods

Kelantan And Terengganu ECRL Project Affected By Floods

The floods last week impacted around 70% of the construction work at sections 1 and 2 of the East Coast Rail Line (ECRL), which spans 82 kilometres from Tunjong here to Setiu in Terengganu.

28-12-2022

Latest News

Auto News
KLCC Roads Closed Saturday For Sarong Music Run

KLCC Roads Closed Saturday For Sarong Music Run

Expect road closures and traffic delays around KLCC tomorrow for the Malaysia Sarong Music Run 2025.

19-09-2025
Auto News
Sand, Log Trucks Dominate Kelantan Roads - JPJ

Sand, Log Trucks Dominate Kelantan Roads - JPJ

Sand and log trucks make up most heavy vehicle traffic in Kelantan, with fewer overloaded cases.

19-09-2025
Auto News
Customs Seizes 32 Imported Cars Worth RM8.45 Million

Customs Seizes 32 Imported Cars Worth RM8.45 Million

Ops Purple uncovered vehicles stored beyond the legal limit, with unpaid duties and taxes totalling RM5.38 million.

19-09-2025
Auto News
MAA: Aug 2025 Sales Up 4.2%, YoY Growth Modest at 0.6%

MAA: Aug 2025 Sales Up 4.2%, YoY Growth Modest at 0.6%

Latest MAA Aug 2025 sales figures see PVs contribute 67,302 units, with CVs taking the remaining 5,739.

Auto News
PLUS Kulai–Senai Smart Lane Closed Starting Sept 22

PLUS Kulai–Senai Smart Lane Closed Starting Sept 22

PLUS closes Kulai–Senai Smart Lane on Sept 22 for road widening. Separately, it also continues RM37m restroom refurbishments across its highway network.

Auto News
JPJ Steps Up Crackdown On Thai Roktu Vans In Kelantan

JPJ Steps Up Crackdown On Thai Roktu Vans In Kelantan

Kelantan JPJ is intensifying checks on Thai private vans misusing permits to ferry passengers.

18-09-2025
Auto News
BUDI95 App Shows How Revised RON95 Subsidy Will Work

BUDI95 App Shows How Revised RON95 Subsidy Will Work

Viral Facebook video reveals how MyKad-linked BUDI95 app, designed to control RON95 quotas for Malaysians, will work.

Auto News
Proton e.MAS 7 Remains Malaysia’s Top-Selling EV, CKD Starts Soon

Proton e.MAS 7 Remains Malaysia’s Top-Selling EV, CKD Starts Soon

Proton e.MAS 7 retains No. 1 spot as Malaysia’s best-selling EV with over 5,800 units delivered as of Aug 2025.

18-09-2025

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.