ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%
Anis
8-3-2023
The East Coast Rail Link (ECRL) project's Kuantan Tunnel, which broke ground in October last year, will be completed by the end of April.
The 2.8km tunnel located in Jabor, near here, is the longest among the ECRL tunnels in Section B (Dungun-Mentakab), which also includes the 1.1km Paka Tunnel and 871m Dungun Tunnel, both in Terengganu.
Wan Kamal Wan Embong, regional construction manager (Section 4 and 5) for Malaysian Rail Link (MRL), stated that the Kuantan Tunnel breakthrough occurred on October 17, last year, two months ahead of schedule.
"The tunnel's completion date is set for April 27. The Kuantan Tunnel runs through both Pahang and Terengganu, with 976 metres in Pahang and the remaining 1,890 metres in Terengganu "he told reporters yesterday during a media visit to the Kuantan Tunnel here. The New Austrian Tunnelling Method (NATM), the world's most widely used underground construction method, is being used in the drilling and blasting work for the Kuantan tunnel project, which began on October 7, 2019. The average height and width of the Kuantan Tunnel are 11.89m and 13.26m, respectively.
The project made use of a Swedish-made double-arm jumbo drilling machine, with tunnelling work beginning in both directions and meeting in the middle. Wan Kamal stated that MRL ensured that all workers strictly adhered to the safety aspects and conditions set by the Department of Occupational Safety and Health (DOSH). "Because tunnel construction required working in a confined space, we had to ensure proper ventilation and control gas emissions inside the tunnel that could endanger the workers. At the peak of the project, 177 workers were on the job "he said, adding that safety was given top priority during the blasting operations.
Closed-circuit television cameras were previously reported to have been installed at the construction site, including inside the tunnel, to monitor worker movement and ensure safety. In terms of the overall progress of the ECRL, Wan Kamal stated that the 665km rail project was 40% completed and was on track to be completed in December 2026. The 210km Dungun-Mentakab main line is also known as Section B, while the other sections are Kota Baru to Dungun (Section A) and Mentakab to Port Klang (Section B) (Section C).
The ECRL, which opened in 2017, will connect the east coast states of Kelantan, Terengganu, and Pahang with the Klang Valley.
Gallery

Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPB6823
SELANGOR
BSE3819
JOHOR
JXW3362
PULAU PINANG
PRQ2639
PERAK
ANV2504
PAHANG
CFB6374
KEDAH
KGA3928
NEGERI SEMBILAN
NEF6675
KOTA KINABALU
SJK6701
KUCHING
QAB2775L
Last updated 30 Apr, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.18
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
EURO 5 B7
RM 3.08
Last updated 24 Apr, 2025
Related News
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide
Selangor Forestry Department found that the alleged land clearing activities in the Selangor State Park are part of the ECRL project.
06-02-2023
Kelantan And Terengganu ECRL Project Affected By Floods
The floods last week impacted around 70% of the construction work at sections 1 and 2 of the East Coast Rail Line (ECRL), which spans 82 kilometres from Tunjong here to Setiu in Terengganu.
28-12-2022
ECRL Will Continue - Loke Siew Fook
The federal government will continue the RM50 billion East Coast Rail Link (ECRL) project, according to Loke Siew Fook, the minister of transportation.
07-12-2022
Latest News
Counterfeit Engine Oil Syndicate Busted
Authorities raid three premises in Ara Damansara and Kepong, uncovering a syndicate that repackages and sells counterfeit engine oil.
30-04-2025
PIAM: Motor and EV Insurance Up 6.7% in 2024
Motor insurance surged in 2024, adding RM651.1 million in premiums, EV coverage sets the tone for 2025, touts PIAM.
30-04-2025
MOT Lowers School Zone Speed Limit To 30 KM/H
The government will soon gazette new 30 KM/H speed limit in school zones.
30-04-2025
JPJ Seizes Two Lorries After Drivers, Owner Obstruct Enforcement
JPJ seized two lorries after their drivers and owner obstructed enforcement by spilling sand, causing major disruption.
29-04-2025
Jaecoo Malaysia Teases Omoda C7 Ahead of MAS 2025 Debut
Jaecoo Malaysia teases sleek new Omoda C7 ahead of its official debut at upcoming Malaysian Autoshow 2025 (MAS 2025).
29-04-2025
New Mitsubishi 3S Centre Opens in Kajang, Selangor
MMM grows its dealership network again, welcomes new Mitsubishi 3S Centre in Kajang, Selangor into its network.
29-04-2025
Isuzu Malaysia Appoints Tomoyuki Yamaguchi as New CEO
Isuzu Malaysia has appointed Tomoyuki Yamaguchi as its new CEO, beginning from Apr 24, 2025, onwards.
29-04-2025
BMW Group Malaysia Appoints Performance Motors Malaysia as New Dealer Partner
BMW Group Malaysia’s new dealer partner, Performance Motors, is a joint venture between Sime Motors and Ingress.
29-04-2025
Show More
trending_flat