ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

Anis

Share via




The East Coast Rail Link (ECRL) project's Kuantan Tunnel, which broke ground in October last year, will be completed by the end of April. The 2.8km tunnel located in Jabor, near here, is the longest among the ECRL tunnels in Section B (Dungun-Mentakab), which also includes the 1.1km Paka Tunnel and 871m Dungun Tunnel, both in Terengganu. Wan Kamal Wan Embong, regional construction manager (Section 4 and 5) for Malaysian Rail Link (MRL), stated that the Kuantan Tunnel breakthrough occurred on October 17, last year, two months ahead of schedule.


"The tunnel's completion date is set for April 27. The Kuantan Tunnel runs through both Pahang and Terengganu, with 976 metres in Pahang and the remaining 1,890 metres in Terengganu "he told reporters yesterday during a media visit to the Kuantan Tunnel here. The New Austrian Tunnelling Method (NATM), the world's most widely used underground construction method, is being used in the drilling and blasting work for the Kuantan tunnel project, which began on October 7, 2019. The average height and width of the Kuantan Tunnel are 11.89m and 13.26m, respectively.



The project made use of a Swedish-made double-arm jumbo drilling machine, with tunnelling work beginning in both directions and meeting in the middle. Wan Kamal stated that MRL ensured that all workers strictly adhered to the safety aspects and conditions set by the Department of Occupational Safety and Health (DOSH). "Because tunnel construction required working in a confined space, we had to ensure proper ventilation and control gas emissions inside the tunnel that could endanger the workers. At the peak of the project, 177 workers were on the job "he said, adding that safety was given top priority during the blasting operations.


Closed-circuit television cameras were previously reported to have been installed at the construction site, including inside the tunnel, to monitor worker movement and ensure safety. In terms of the overall progress of the ECRL, Wan Kamal stated that the 665km rail project was 40% completed and was on track to be completed in December 2026. The 210km Dungun-Mentakab main line is also known as Section B, while the other sections are Kota Baru to Dungun (Section A) and Mentakab to Port Klang (Section B) (Section C).


The ECRL, which opened in 2017, will connect the east coast states of Kelantan, Terengganu, and Pahang with the Klang Valley.

Gallery

Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VPY5456

SELANGOR

BSK697

JOHOR

JYK7945

PULAU PINANG

PRV5504

PERAK

APC4203

PAHANG

CFE1146

KEDAH

KGC9254

NEGERI SEMBILAN

NEH5704

KOTA KINABALU

SJN6031

KUCHING

QAB4950M

Last updated 11 Nov, 2025

Fuel Price

Petrol

RON 95

RM 2.60

RON 97

RM 3.20

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 3.02

+0.07

EURO 5 B7

RM 3.22

+0.07

Last updated 06 Nov, 2025

Related News

Auto News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News
ECRL Project Hits 87% Completion by August 2025 – MoT

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Project Progress Surpasses 56% - Loke

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News
ECRL Project In Terengganu Reaches 55% Progress

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023

Latest News

Auto News
PLUS To Close Two Bangi Ramps Nightly Until Nov 28

PLUS To Close Two Bangi Ramps Nightly Until Nov 28

PLUS will close two ramps near Bangi nightly from 10PM to 5AM starting today until Nov 28.

10-11-2025
Auto News
KLIA Aerotrain Halts Daily Midnight To 5am For Maintenance

KLIA Aerotrain Halts Daily Midnight To 5am For Maintenance

KLIA Aerotrain will stop running every night from midnight to 5am for routine checks and maintenance.

10-11-2025
Auto News
4.4 Mil Old Vehicles Threaten Road Safety, Incentive Alone Insufficient

4.4 Mil Old Vehicles Threaten Road Safety, Incentive Alone Insufficient

JPJ data shows over 4.4 million old vehicles are still on the road making up about 17% of the country’s 25.7m active vehicles.

10-11-2025
Auto News
Proton Shifts 15,575 Units In Oct 2025, Outgoing Saga Still Leads

Proton Shifts 15,575 Units In Oct 2025, Outgoing Saga Still Leads

Proton closes Oct 2025 by shifting 15,575 units, outgoing Saga sales spikes to 12-year high ahead of successor’s debut.

10-11-2025
Auto News
JPJ Warns Public Against Fake “Free Driving Licence” TikTok Scams

JPJ Warns Public Against Fake “Free Driving Licence” TikTok Scams

JPJ has warned the public about fake TikTok posts claiming people can get free driving licences without any tests.

10-11-2025
Auto News
RM3b Juru–Sungai Dua Link Cuts Travel Time To Just  20 Minutes

RM3b Juru–Sungai Dua Link Cuts Travel Time To Just 20 Minutes

RM3 billion traffic dispersal project aims to slash travel time between Juru and Sungai Dua from an hour to just 20 minutes.

Auto News
Nanta: Barrier-Free ANPR Toll System Still at RFP Stage

Nanta: Barrier-Free ANPR Toll System Still at RFP Stage

The Works Ministry is inviting proposals for an ANPR-based barrier-free MLFF toll system.

Auto News
New Leapmotor 3S Showroom Opens In Ipoh, Perak

New Leapmotor 3S Showroom Opens In Ipoh, Perak

Perak state capital of Ipoh gains new Leapmotor brand 3S showroom and service outlet operated by dealers CST Auto.

07-11-2025

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.