ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

The East Coast Rail Link (ECRL) project's Kuantan Tunnel, which broke ground in October last year, will be completed by the end of April.
The 2.8km tunnel located in Jabor, near here, is the longest among the ECRL tunnels in Section B (Dungun-Mentakab), which also includes the 1.1km Paka Tunnel and 871m Dungun Tunnel, both in Terengganu.
Wan Kamal Wan Embong, regional construction manager (Section 4 and 5) for Malaysian Rail Link (MRL), stated that the Kuantan Tunnel breakthrough occurred on October 17, last year, two months ahead of schedule.
"The tunnel's completion date is set for April 27. The Kuantan Tunnel runs through both Pahang and Terengganu, with 976 metres in Pahang and the remaining 1,890 metres in Terengganu "he told reporters yesterday during a media visit to the Kuantan Tunnel here. The New Austrian Tunnelling Method (NATM), the world's most widely used underground construction method, is being used in the drilling and blasting work for the Kuantan tunnel project, which began on October 7, 2019. The average height and width of the Kuantan Tunnel are 11.89m and 13.26m, respectively.
The project made use of a Swedish-made double-arm jumbo drilling machine, with tunnelling work beginning in both directions and meeting in the middle. Wan Kamal stated that MRL ensured that all workers strictly adhered to the safety aspects and conditions set by the Department of Occupational Safety and Health (DOSH). "Because tunnel construction required working in a confined space, we had to ensure proper ventilation and control gas emissions inside the tunnel that could endanger the workers. At the peak of the project, 177 workers were on the job "he said, adding that safety was given top priority during the blasting operations.
Closed-circuit television cameras were previously reported to have been installed at the construction site, including inside the tunnel, to monitor worker movement and ensure safety. In terms of the overall progress of the ECRL, Wan Kamal stated that the 665km rail project was 40% completed and was on track to be completed in December 2026. The 210km Dungun-Mentakab main line is also known as Section B, while the other sections are Kota Baru to Dungun (Section A) and Mentakab to Port Klang (Section B) (Section C).
The ECRL, which opened in 2017, will connect the east coast states of Kelantan, Terengganu, and Pahang with the Klang Valley.
Gallery
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRB2840
SELANGOR
BSQ5278
JOHOR
JYX7691
PULAU PINANG
PSC7047
PERAK
APH8940
PAHANG
CFG6758
KEDAH
KGG3495
NEGERI SEMBILAN
NEK5608
KOTA KINABALU
SJS2039
KUCHING
QAB9350N
Last updated 08 Jun, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
Latest News
Heartbreaking Dashcam Footage Reveals Final Moments Before Tragic Collision That Wiped Out 3 Generations Of A Family
A brand-new Proton X50 turned into a nightmare just hours after delivery, as a tragic head-on collision claimed the lives of 6 family members, including a baby.
08-06-2026
RM200k Rebates?! Test Drive 9 Brands At The Sime Motors MotorExpo 2026 This Weekend
Hit up the free-entry Sime Motors MotorExpo 2026 at XOX Arena this weekend for massive RM200,000 rebates and test drives from 9 major brands.
05-06-2026
Chery Just Dropped Prices Across Their Entire Lineup, Now Starting From RM80k!
Chery Malaysia launches its 3rd Anniversary Mega Rewards promo, slashing prices across its SUV lineup including the Tiggo Cross, O5, Tiggo 7 Pro, and Tiggo 8 PHEV starting from RM80,800.
04-06-2026
No Car On Campus? Perodua Launched A New App So Uni Students Can Rent Cars To Go To Class
Perodua launches UCar-e, an app-based campus car-rental service for students at UUM, UPM, and UTM, offering an affordable alternative to car ownership.
04-06-2026
Zeekr Turned First-Time Track Drivers Into "Confident Pros" At This Supervised Sepang Event
The inaugural Zeekr Dynamic event at Sepang International Circuit turned first-time track drivers into confident pros through supervised performance and safety exercises.
04-06-2026
Expect Higher Maintenance Costs? Suppliers Warn Of Upcoming Price Revisions For Tyres & Spare Parts
Malaysian vehicle owners should expect higher car servicing, tyre, and spare parts costs starting June due to global energy market volatility. Find out how to beat the price hike.
03-06-2026
Buying A Car Soon? 5 Big Changes That Took Effect On 1 June That You Need To Know
Buying a car in Malaysia? The Hire-Purchase Amendment Act 2026 took effect on 1 June. Here are 5 new rules on EIR and car loan interest you must know.
03-06-2026
No Extra Cost, But Check Your Filter? 4 Essential Things Every Diesel Driver Needs To Know About The B15 Rollout
Malaysia officially rolled out the B15 biodiesel blend on June 1. Find out if your Hilux, Ranger, Triton, or Mazda diesel engine is compatible based on latest manufacturer statements.
03-06-2026
Show More
trending_flat