ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

The East Coast Rail Link (ECRL) project's Kuantan Tunnel, which broke ground in October last year, will be completed by the end of April.
The 2.8km tunnel located in Jabor, near here, is the longest among the ECRL tunnels in Section B (Dungun-Mentakab), which also includes the 1.1km Paka Tunnel and 871m Dungun Tunnel, both in Terengganu.
Wan Kamal Wan Embong, regional construction manager (Section 4 and 5) for Malaysian Rail Link (MRL), stated that the Kuantan Tunnel breakthrough occurred on October 17, last year, two months ahead of schedule.
"The tunnel's completion date is set for April 27. The Kuantan Tunnel runs through both Pahang and Terengganu, with 976 metres in Pahang and the remaining 1,890 metres in Terengganu "he told reporters yesterday during a media visit to the Kuantan Tunnel here. The New Austrian Tunnelling Method (NATM), the world's most widely used underground construction method, is being used in the drilling and blasting work for the Kuantan tunnel project, which began on October 7, 2019. The average height and width of the Kuantan Tunnel are 11.89m and 13.26m, respectively.
The project made use of a Swedish-made double-arm jumbo drilling machine, with tunnelling work beginning in both directions and meeting in the middle. Wan Kamal stated that MRL ensured that all workers strictly adhered to the safety aspects and conditions set by the Department of Occupational Safety and Health (DOSH). "Because tunnel construction required working in a confined space, we had to ensure proper ventilation and control gas emissions inside the tunnel that could endanger the workers. At the peak of the project, 177 workers were on the job "he said, adding that safety was given top priority during the blasting operations.
Closed-circuit television cameras were previously reported to have been installed at the construction site, including inside the tunnel, to monitor worker movement and ensure safety. In terms of the overall progress of the ECRL, Wan Kamal stated that the 665km rail project was 40% completed and was on track to be completed in December 2026. The 210km Dungun-Mentakab main line is also known as Section B, while the other sections are Kota Baru to Dungun (Section A) and Mentakab to Port Klang (Section B) (Section C).
The ECRL, which opened in 2017, will connect the east coast states of Kelantan, Terengganu, and Pahang with the Klang Valley.
Gallery
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQW3178
SELANGOR
BSP5914
JOHOR
JYV7839
PULAU PINANG
PSB8294
PERAK
APH1547
PAHANG
CFG3853
KEDAH
KGF6155
NEGERI SEMBILAN
NEK2839
KOTA KINABALU
SJR6742
KUCHING
QAB6923N
Last updated 02 May, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
Latest News
“Don't Even Try It” — KL Now Has 10,000 AI Cameras That Can Track Your Face & Call You Out If You Act Sus
KL is watching! DBKL’s 10,000 new AI CCTVs now feature facial recognition and audio blasting to catch lawbreakers in real-time. From traffic violations to "sus" behavior.
01-05-2026
Wait, Is That A Bronco? 5 Things To Know About KP31 That Might Be Chery Malaysia's First Truck
Is Chery bringing a Ford Bronco rival to Malaysia? Discover 5 key facts about the massive Chery KP31 pickup truck, including its "World’s First" hybrid tech, local assembly plans in Lembah Beringin, and its expected 2027 launch date. Read more for the full breakdown!
30-04-2026
You Might Be Paying More At The Pump Today (30 April – 6 May)
New fuel prices are live! As of 30 April 2026, RON97 and unsubsidised RON95 see a price hike in Malaysia. See the full breakdown and why prices are rising.
30-04-2026
900 Units In 21 Days?! The All-New Mitsubishi Xforce Is Officially The "It" Car Of April 2026
900 units in 21 days! The all-new Mitsubishi Xforce is officially April 2026’s "It" car. Discover why this compact SUV is stealing hearts and taking over Malaysian roads with its perfect blend of city style and "hidden gems" for local driving.
29-04-2026
Relax! 5 Simple Reasons You Don’t Need To Panic About The 200L Petrol Quota
Government is maintaining the BUDI95 cap and keeping the price at RM1.99 despite international pressure. See why the 200-litre limit is actually "safe" for 90% of Malaysian drivers.
29-04-2026
BYD Just Turned 1,200 Digital Pledges Into Real Trees, And Here’s Why Your "Likes" Actually Mattered
BYD Malaysia fulfills 1,200 digital pledges by planting 120 native trees at The Waterfront @ ParkCity. Discover how the Miyawaki method and the BYD Light the Change programme are cooling the Earth.
28-04-2026
Cheaper Road Tax For Diesel Owners? 5 Things You Need To Know About PM Anwar’s Newest Proposal
Tired of high diesel prices? The government is exploring a slash in diesel road tax rates to ease your burden. See the 5 things you need to know about the upcoming change.
27-04-2026
P1P To P9P: These 5 Malaysian Number Plates Cost More Than Most Luxury Supercars
The JPJ "P_P" series auction sets a new record, collecting RM21.6 million. From P1P at RM1.1 million to P9P at RM1 million, see the 5 Malaysian number plates that cost more than luxury supercars.
27-04-2026
Show More
trending_flat