ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

The East Coast Rail Link (ECRL) project's Kuantan Tunnel, which broke ground in October last year, will be completed by the end of April.
The 2.8km tunnel located in Jabor, near here, is the longest among the ECRL tunnels in Section B (Dungun-Mentakab), which also includes the 1.1km Paka Tunnel and 871m Dungun Tunnel, both in Terengganu.
Wan Kamal Wan Embong, regional construction manager (Section 4 and 5) for Malaysian Rail Link (MRL), stated that the Kuantan Tunnel breakthrough occurred on October 17, last year, two months ahead of schedule.
"The tunnel's completion date is set for April 27. The Kuantan Tunnel runs through both Pahang and Terengganu, with 976 metres in Pahang and the remaining 1,890 metres in Terengganu "he told reporters yesterday during a media visit to the Kuantan Tunnel here. The New Austrian Tunnelling Method (NATM), the world's most widely used underground construction method, is being used in the drilling and blasting work for the Kuantan tunnel project, which began on October 7, 2019. The average height and width of the Kuantan Tunnel are 11.89m and 13.26m, respectively.
The project made use of a Swedish-made double-arm jumbo drilling machine, with tunnelling work beginning in both directions and meeting in the middle. Wan Kamal stated that MRL ensured that all workers strictly adhered to the safety aspects and conditions set by the Department of Occupational Safety and Health (DOSH). "Because tunnel construction required working in a confined space, we had to ensure proper ventilation and control gas emissions inside the tunnel that could endanger the workers. At the peak of the project, 177 workers were on the job "he said, adding that safety was given top priority during the blasting operations.
Closed-circuit television cameras were previously reported to have been installed at the construction site, including inside the tunnel, to monitor worker movement and ensure safety. In terms of the overall progress of the ECRL, Wan Kamal stated that the 665km rail project was 40% completed and was on track to be completed in December 2026. The 210km Dungun-Mentakab main line is also known as Section B, while the other sections are Kota Baru to Dungun (Section A) and Mentakab to Port Klang (Section B) (Section C).
The ECRL, which opened in 2017, will connect the east coast states of Kelantan, Terengganu, and Pahang with the Klang Valley.
Gallery
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQK7609
SELANGOR
BSM2574
JOHOR
JYQ8520
PULAU PINANG
PRY3641
PERAK
APE8602
PAHANG
CFF1382
KEDAH
KGE1820
NEGERI SEMBILAN
NEJ4410
KOTA KINABALU
SJQ1542
KUCHING
QAB1858N
Last updated 31 Jan, 2026
Fuel Price
Petrol
RON 95
RM 2.54
+0.02
RON 97
RM 3.10
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.04
EURO 5 B7
RM 3.08
+0.04
Last updated 22 Jan, 2026
Related News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
Latest News
Chery Malaysia Outlines 2026 Plans, Four New SUVs Confirmed
Chery Malaysia outlines 2026 plans, with four new SUVs confirmed as the brand shifts focus toward premium and lifestyle models.
31-01-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
Summons Discounts for Foreign Vehicles Will Be Reviewed – MOT
The Transport Ministry will review traffic summons discounts offered to foreign vehicles, says minister Anthony Loke.
30-01-2026
Hyundai Expands Dealer Network and Insurance Partnerships
Hyundai Motor Malaysia partners with HZN and top insurers to enhance customer access and vehicle protection.
30-01-2026
JPJ Rolls Out Flexible Road Tax Renewal For E-Hailing Vehicles
E-hailing drivers can now renew their road tax from one to 12 months, making compliance easier and more cost-effective.
30-01-2026
Scrap Your Old Car, Get Up To RM4,000 For A New Proton
Scrap your old car and get up to RM4,000 towards a new Proton with trade-in incentives and a government grant.
30-01-2026
Traffic Diversions at 12 KL Intersections for 2026 Thaipusam
Traffic diversions at 12 KL intersections will be carried out in stages 2026 Thaipusam.
30-01-2026
Is GWM Seeking To Build Its Own Plant in Malaysia?
MITI raises prospects of a standalone GWM factory as newly launched Wey G9 begins production with 40% local content.
29-01-2026
Show More
trending_flat