ENZHMS
Link Copiedcheck_circle
Auto News

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

Anis

Share via




The East Coast Rail Link (ECRL) project's Kuantan Tunnel, which broke ground in October last year, will be completed by the end of April. The 2.8km tunnel located in Jabor, near here, is the longest among the ECRL tunnels in Section B (Dungun-Mentakab), which also includes the 1.1km Paka Tunnel and 871m Dungun Tunnel, both in Terengganu. Wan Kamal Wan Embong, regional construction manager (Section 4 and 5) for Malaysian Rail Link (MRL), stated that the Kuantan Tunnel breakthrough occurred on October 17, last year, two months ahead of schedule.


"The tunnel's completion date is set for April 27. The Kuantan Tunnel runs through both Pahang and Terengganu, with 976 metres in Pahang and the remaining 1,890 metres in Terengganu "he told reporters yesterday during a media visit to the Kuantan Tunnel here. The New Austrian Tunnelling Method (NATM), the world's most widely used underground construction method, is being used in the drilling and blasting work for the Kuantan tunnel project, which began on October 7, 2019. The average height and width of the Kuantan Tunnel are 11.89m and 13.26m, respectively.



The project made use of a Swedish-made double-arm jumbo drilling machine, with tunnelling work beginning in both directions and meeting in the middle. Wan Kamal stated that MRL ensured that all workers strictly adhered to the safety aspects and conditions set by the Department of Occupational Safety and Health (DOSH). "Because tunnel construction required working in a confined space, we had to ensure proper ventilation and control gas emissions inside the tunnel that could endanger the workers. At the peak of the project, 177 workers were on the job "he said, adding that safety was given top priority during the blasting operations.


Closed-circuit television cameras were previously reported to have been installed at the construction site, including inside the tunnel, to monitor worker movement and ensure safety. In terms of the overall progress of the ECRL, Wan Kamal stated that the 665km rail project was 40% completed and was on track to be completed in December 2026. The 210km Dungun-Mentakab main line is also known as Section B, while the other sections are Kota Baru to Dungun (Section A) and Mentakab to Port Klang (Section B) (Section C).


The ECRL, which opened in 2017, will connect the east coast states of Kelantan, Terengganu, and Pahang with the Klang Valley.

Gallery

Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VQE481

SELANGOR

BSK9346

JOHOR

JYN524

PULAU PINANG

PRW6382

PERAK

APD4292

PAHANG

CFE4766

KEDAH

KGD4663

NEGERI SEMBILAN

NEH9347

KOTA KINABALU

SJP3243

KUCHING

QAB7536M

Last updated 18 Dec, 2025

Fuel Price

Petrol

RON 95

RM 2.64

-0.02

RON 97

RM 3.27

-0.02

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 3.06

-0.02

EURO 5 B7

RM 3.26

-0.02

Last updated 11 Dec, 2025

Related News

Auto News

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023

Latest News

Auto News

Updated Fuel Prices From 18 To 24 December

The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 18 to 24 December, 2025, the rates are as such.

Auto News

Perodua Traz Secures 5-Star ASEAN NCAP Crash Test Score

The newly-launched Perodua Traz has secured a full five-star rating for the ASEAN NCAP crash test.

17-12-2025
Auto News

ECRL First EMU Trains, E-Locos Head To Malaysia For Testing

Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.

17-12-2025
Auto News

Test Drive Any Chery PHEVs and Stand a Chance to Win Up to RM200K in Prizes

Test drive any of Chery’s new PHEVs from now until Jan 6 and stand a chance to win prizes worth up to RM200,000.

17-12-2025
Auto News

Rapid KL Travel Pass Prices Increase from Jan 1, 2026

Rapid KL travel pass prices to rise in 2026; My50 and concession passes unchanged

Auto News

KTMB Expands ETS, East Coast Rail Services From Jan 1

KTMB expands train services nationwide with new ETS and East Coast routes starting Jan 1.

17-12-2025
Auto News

KLIA Aerotrain Begins Trial Runs, Nightly Shutdown Remains

Malaysia Airports will start trial operations for the KLIA Aerotrain as part of a month-long plan to fix reliability issues.

17-12-2025
Auto News

No More Heavy Vehicles On Kuala Terengganu Drawbridge From Jan 1

Heavy vehicles will no longer be allowed to use the Kuala Terengganu drawbridge from Jan 1.

16-12-2025

Show More

trending_flat
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.