ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

Anis

Share via




The East Coast Rail Link (ECRL) project's Kuantan Tunnel, which broke ground in October last year, will be completed by the end of April. The 2.8km tunnel located in Jabor, near here, is the longest among the ECRL tunnels in Section B (Dungun-Mentakab), which also includes the 1.1km Paka Tunnel and 871m Dungun Tunnel, both in Terengganu. Wan Kamal Wan Embong, regional construction manager (Section 4 and 5) for Malaysian Rail Link (MRL), stated that the Kuantan Tunnel breakthrough occurred on October 17, last year, two months ahead of schedule.


"The tunnel's completion date is set for April 27. The Kuantan Tunnel runs through both Pahang and Terengganu, with 976 metres in Pahang and the remaining 1,890 metres in Terengganu "he told reporters yesterday during a media visit to the Kuantan Tunnel here. The New Austrian Tunnelling Method (NATM), the world's most widely used underground construction method, is being used in the drilling and blasting work for the Kuantan tunnel project, which began on October 7, 2019. The average height and width of the Kuantan Tunnel are 11.89m and 13.26m, respectively.



The project made use of a Swedish-made double-arm jumbo drilling machine, with tunnelling work beginning in both directions and meeting in the middle. Wan Kamal stated that MRL ensured that all workers strictly adhered to the safety aspects and conditions set by the Department of Occupational Safety and Health (DOSH). "Because tunnel construction required working in a confined space, we had to ensure proper ventilation and control gas emissions inside the tunnel that could endanger the workers. At the peak of the project, 177 workers were on the job "he said, adding that safety was given top priority during the blasting operations.


Closed-circuit television cameras were previously reported to have been installed at the construction site, including inside the tunnel, to monitor worker movement and ensure safety. In terms of the overall progress of the ECRL, Wan Kamal stated that the 665km rail project was 40% completed and was on track to be completed in December 2026. The 210km Dungun-Mentakab main line is also known as Section B, while the other sections are Kota Baru to Dungun (Section A) and Mentakab to Port Klang (Section B) (Section C).


The ECRL, which opened in 2017, will connect the east coast states of Kelantan, Terengganu, and Pahang with the Klang Valley.

Gallery

Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VRC4952

SELANGOR

BSQ8024

JOHOR

JYY6253

PULAU PINANG

PSD745

PERAK

APJ2173

PAHANG

CFG7794

KEDAH

KGG5063

NEGERI SEMBILAN

NEK6503

KOTA KINABALU

SJS4148

KUCHING

QAB9856N

Last updated 18 Jun, 2026

Fuel Price

Petrol

RON 95

RM 3.97

+1.38

RON 97

RM 4.90

+1.75

RON 100

RM 7.20

+2.20

VPR

RM 8.23

+2.00

Diesel

EURO 5 B10

RM 5.12

+2.08

EURO 5 B7

RM 5.32

+2.08

Last updated 30 Apr, 2026

Related News

Auto News

16-06-2026
Auto News

Anwar: 13MP Pushes for Improved Connectivity – Better Buses, Trains and Roads

The 13th Malaysia Plan focuses on better connectivity through buses, trains, roads, and smarter planning.

31-07-2025

Latest News

Auto News

Good News For 5 Million Perodua Owners! Don't Go To Outside Workshops As Service Prices Just Dropped

Thinking of visiting an outside mechanic? Perodua is slashing overall service maintenance parts and labor costs by 10% nationwide starting 19 June.

18-06-2026
Auto News

It’s Happening! After Years Of Delays, The LRT3 Is Finally Ready To Start Operations

The long-awaited LRT3 Shah Alam Line is officially set to begin operations by the end of this month, as confirmed by Transport Minister Anthony Loke.

18-06-2026
Auto News

No More Just 'Screwing Parts Together', Malaysia Wants Local Talents To Design The Next Big ASEAN Car Tech

At KLIMS 2026, Deputy Transport Minister Datuk Hasbi Habibollah urged Malaysia's automotive industry to evolve from car assemblers into technology creators.

18-06-2026
Auto News

It Costs Up To RM300K To Protect One School Zone, And The Government Is Inviting Private Companies To Step Up

Why does a single Safe School Zone cost up to RM300K to build? Transport Minister Anthony Loke breaks down the new physical 30km/h traffic-calming blueprint and why private companies are being asked to step up.

17-06-2026
Auto News

Prime, Premium, Or Premium Plus? 4 Major Differences Between The 3 Proton e.Mas 7 Tiers

Prime, Premium, or Premium Plus? We break down the 4 massive differences in battery range, price, and luxury features across the new Proton eMas 7 EV tiers.

12-06-2026
Auto News

15 Drug Records But Still Driving?! Malaysians Are Furious Over The Viral Penang Highway Triton Rampage

Shocking details emerge on the viral Mitsubishi Triton highway crash in Penang. The drugged driver has 17 prior convictions, leaving 18 cars damaged.

10-06-2026
Auto News

Don't Buy A Car Full Price! Perodua Just Quietly Slashed Prices On 5 Models & The Discounts Vanish After June 30

Perodua just quietly slashed prices on 5 popular models for June 2026! Check out the exact cash rebates for the Myvi, Ativa, Aruz, Bezza, and Axia here.

09-06-2026
Auto News

Upgraded e.MAS 7 & A Spicy X50?! 5 Things To Check Out At Proton’s KLIMS 2026 Booth This June 12–21

Proton is bringing an upgraded long-range e.MAS 7, a humanoid robot, and new FutureMotion hybrid tech to KLIMS 2026 at MITEC. Here is what to look out for.

09-06-2026

Show More

trending_flat
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2026 CariCarz.com. All Rights Reserved.