ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

The East Coast Rail Link (ECRL) project's Kuantan Tunnel, which broke ground in October last year, will be completed by the end of April. The 2.8km tunnel located in Jabor, near here, is the longest among the ECRL tunnels in Section B (Dungun-Mentakab), which also includes the 1.1km Paka Tunnel and 871m Dungun Tunnel, both in Terengganu. Wan Kamal Wan Embong, regional construction manager (Section 4 and 5) for Malaysian Rail Link (MRL), stated that the Kuantan Tunnel breakthrough occurred on October 17, last year, two months ahead of schedule.
"The tunnel's completion date is set for April 27. The Kuantan Tunnel runs through both Pahang and Terengganu, with 976 metres in Pahang and the remaining 1,890 metres in Terengganu "he told reporters yesterday during a media visit to the Kuantan Tunnel here. The New Austrian Tunnelling Method (NATM), the world's most widely used underground construction method, is being used in the drilling and blasting work for the Kuantan tunnel project, which began on October 7, 2019. The average height and width of the Kuantan Tunnel are 11.89m and 13.26m, respectively.
The project made use of a Swedish-made double-arm jumbo drilling machine, with tunnelling work beginning in both directions and meeting in the middle. Wan Kamal stated that MRL ensured that all workers strictly adhered to the safety aspects and conditions set by the Department of Occupational Safety and Health (DOSH). "Because tunnel construction required working in a confined space, we had to ensure proper ventilation and control gas emissions inside the tunnel that could endanger the workers. At the peak of the project, 177 workers were on the job "he said, adding that safety was given top priority during the blasting operations.
Closed-circuit television cameras were previously reported to have been installed at the construction site, including inside the tunnel, to monitor worker movement and ensure safety. In terms of the overall progress of the ECRL, Wan Kamal stated that the 665km rail project was 40% completed and was on track to be completed in December 2026. The 210km Dungun-Mentakab main line is also known as Section B, while the other sections are Kota Baru to Dungun (Section A) and Mentakab to Port Klang (Section B) (Section C).
The ECRL, which opened in 2017, will connect the east coast states of Kelantan, Terengganu, and Pahang with the Klang Valley.
Gallery
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRY6294
SELANGOR
BSV1572
JOHOR
JH4833J
PULAU PINANG
PSH4357
PERAK
APN304
PAHANG
CFJ4206
KEDAH
KGJ8452
NEGERI SEMBILAN
NEM6053
KOTA KINABALU
SJV2073
KUCHING
QAB328Q
Last updated 17 Nov, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
ECRL Vs Express Bus: Is Saving Hours Worth Paying More?
ECRL to Kota Bharu starts at RM125, but express buses cost less. Compare fares, travel times and the 30% launch discount before choosing.
26-10-2026
ECRL Vs Driving To Kota Bharu: Petrol, EV Or Train, Which Costs Less?
ECRL fares to Kota Bharu start at RM125. We compare train tickets with petrol and EV energy costs to see which option makes more sense.
19-10-2026
Why Extending The ECRL To Rantau Panjang Could Be A Much Bigger Deal Than It Sounds
The proposed ECRL extension to Rantau Panjang could link Malaysia with Thailand and a wider Asian rail and port network. Here's why it matters.
29-09-2026
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
Latest News
GWM Malaysia 2026 Year-End Deals: Prices, Warranties And Financing Offers
GWM Malaysia's 2026 year-end deals include the ORA Good Cat from RM94,000, Haval H6 HEV privileges, WEY G9 financing and Tank SUV warranties.
16-11-2026
Honda Sumber Auto Edaran PJ Closes After 25 Years Of Operations
Honda Sumber Auto Edaran PJ has closed after 25 years, with over 27,000 cars sold. Here's what existing Honda customers should know.
16-11-2026
All-New Nissan X-Trail e-POWER x e-4ORCE Makes First Public Appearance In Malaysia
The new Nissan X-Trail e-POWER x e-4ORCE makes its first public road appearance in KL ahead of its Q4 2026 Malaysia launch. Here's what we know.
16-11-2026
Proton Sales 2026: Geely-Based Models Overtake Homegrown Cars
Geely-based Protons lead homegrown models in 2026 registrations. But the e.MAS lineup and Saga sales reveal a more interesting story.
13-11-2026
Johor Highway Upgrades: PLUS And Senai-Desaru May Open Early
Two Johor highway stretches on PLUS and Senai-Desaru may open early in 2027. Here's where they are, proposed dates and what drivers should know.
13-11-2026
Loke Says Some Welcomed His Resignation, Urges JPJ To Maintain Enforcement
Anthony Loke says some cheered his resignation, expecting JPJ's overloaded lorry crackdown to ease. Will enforcement continue without him?
12-11-2026
Volvo Secret Sale Malaysia 2026: Rebates Up To RM70K, Models And Dates
Volvo Secret Sale Malaysia runs 14–15 Nov 2026 with rebates up to RM70K, extra discounts and an EX30 Cross Country offer from RM185K.
12-11-2026
Mercedes-Benz KL Service Centre To Get AI Scanner In 2027
Mercedes-Benz's new RM3 million KL Northeast service centre plans to introduce an AI-powered vehicle scanner in Q1 2027. Here's what owners should know.
11-11-2026
Show More
trending_flat
Malaysia First Used Car and EV Consignment Platform
This is the best place to sell your car at true market value. Instead of accepting low dealer trade-ins, we handle everything and connect your car directly to genuine buyers for the highest price.

Understanding CariCarzAutomall Consignment Plan


Approved 200-Check Points Inspection

7 Day Money Back Guarantee

One Year Extended Warranty

No Hidden Charge