ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

Anis

Share via




The East Coast Rail Link (ECRL) project's Kuantan Tunnel, which broke ground in October last year, will be completed by the end of April. The 2.8km tunnel located in Jabor, near here, is the longest among the ECRL tunnels in Section B (Dungun-Mentakab), which also includes the 1.1km Paka Tunnel and 871m Dungun Tunnel, both in Terengganu. Wan Kamal Wan Embong, regional construction manager (Section 4 and 5) for Malaysian Rail Link (MRL), stated that the Kuantan Tunnel breakthrough occurred on October 17, last year, two months ahead of schedule.


"The tunnel's completion date is set for April 27. The Kuantan Tunnel runs through both Pahang and Terengganu, with 976 metres in Pahang and the remaining 1,890 metres in Terengganu "he told reporters yesterday during a media visit to the Kuantan Tunnel here. The New Austrian Tunnelling Method (NATM), the world's most widely used underground construction method, is being used in the drilling and blasting work for the Kuantan tunnel project, which began on October 7, 2019. The average height and width of the Kuantan Tunnel are 11.89m and 13.26m, respectively.



The project made use of a Swedish-made double-arm jumbo drilling machine, with tunnelling work beginning in both directions and meeting in the middle. Wan Kamal stated that MRL ensured that all workers strictly adhered to the safety aspects and conditions set by the Department of Occupational Safety and Health (DOSH). "Because tunnel construction required working in a confined space, we had to ensure proper ventilation and control gas emissions inside the tunnel that could endanger the workers. At the peak of the project, 177 workers were on the job "he said, adding that safety was given top priority during the blasting operations.


Closed-circuit television cameras were previously reported to have been installed at the construction site, including inside the tunnel, to monitor worker movement and ensure safety. In terms of the overall progress of the ECRL, Wan Kamal stated that the 665km rail project was 40% completed and was on track to be completed in December 2026. The 210km Dungun-Mentakab main line is also known as Section B, while the other sections are Kota Baru to Dungun (Section A) and Mentakab to Port Klang (Section B) (Section C).


The ECRL, which opened in 2017, will connect the east coast states of Kelantan, Terengganu, and Pahang with the Klang Valley.

Gallery

Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VPY7918

SELANGOR

BSK1383

JOHOR

JYK9434

PULAU PINANG

PRV6170

PERAK

APC4637

PAHANG

CFE1418

KEDAH

KGC9560

NEGERI SEMBILAN

NEH5860

KOTA KINABALU

SJN6348

KUCHING

QAB5029M

Last updated 13 Nov, 2025

Fuel Price

Petrol

RON 95

RM 2.65

+0.05

RON 97

RM 3.25

+0.05

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 3.07

+0.05

EURO 5 B7

RM 3.27

+0.05

Last updated 13 Nov, 2025

Related News

Auto News

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023

Latest News

Auto News

Updated Fuel Prices From 13 To 19 November

The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 13 to 19 November, 2025, the rates are as such.

12-11-2025
Auto News

RM1.7b NPE2 Extension To Ease KL Congestion By 2029 - Nanta

The NPE2 will connect Pantai Dalam to Jalan Istana, cutting travel time by up to 25 minutes and improving traffic flow across KL.

12-11-2025
Auto News

BYD Shark PHEV Pick-Up Truck Teased by BYD Cars Malaysia – Coming Soon?

BYD Cars Malaysia has dropped a teaser for the BYD Shark PHEV pick-up truck. Coming to Malaysia soon?

12-11-2025
Auto News

Malaysia Scraps Rule of 78, Car Loan Savings Ahead - Analysts

Malaysia ends the Rule of 78, letting car loan borrowers save more with fairer interest.

12-11-2025
Auto News

Govt Not Forcing Aeroline To TBS, Corus KLCC Stop Unsuitable

Express bus operators aren’t forced to use TBS or TBG but must run from safe, licensed terminals.

12-11-2025
Auto News

Oct 2025 Vehicle Sales Up 30%, xEV Share at 8.7%

Malaysia’s car market surged in Oct 2025 with 81,413 new registrations, up 30% from Sept’s 62,598 units.

Auto News

LATAR Interchange Opens, Direct Access To Eco Grandeur

The Eco Grandeur Interchange and Toll Plaza has officially opened, offering direct access through Exit 2502 to Eco Grandeur.

11-11-2025
Auto News

Penang Sentral Set to Become Mainland’s Integrated Transport Hub

The Butterworth KTM station, Mutiara Line LRT, and airport expansions will turn Penang Sentral into key transport and logistics hub.

Show More

trending_flat
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.