ECRL Kelantan Expected To Be Completed Six Months Earlier
The East Coast Rail Link (ECRL) in Kelantan is expected to be completed six months ahead of schedule in January 2027.
Nik Soh Yaacoub, deputy director of the Kelantan Public Works Department, told Bernama that the project has reached 61.97 percent completion with a total workforce of 1,500. He stated that the project's current status included bridge construction, land reclamation, and piling, as well as the start of construction on the state's first ECRL station.
Nik Soh is confident that the project will be completed six months ahead of schedule due to the progress of the work being done by China Communications Construction Company Ltd (CCCC) and Malaysia Rail Link (MRL).
"The seriousness demonstrated by CCCC and MRL, as well as the technological sophistication used in implementing this project, is one of the contributors to the project's rapid implementation," he said.
Furthermore, Nik Soh stated that the technology brought by CCCC not only saves time in completing projects but also saves manpower.
"In terms of the iron fabrication process, new technology is used, which saves time and manpower." Furthermore, it is possible to maintain cleanliness while reducing waste production.
"With the initial expectation that construction of the project will be completed, this facility can also be used indirectly by the community, especially when Kelantan hosts the Malaysian Games (SUKMA) in 2026," he said.
Source: Bernama
Gallery
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPY5456
SELANGOR
BSK697
JOHOR
JYK7945
PULAU PINANG
PRV5504
PERAK
APC4203
PAHANG
CFE1146
KEDAH
KGC9254
NEGERI SEMBILAN
NEH5704
KOTA KINABALU
SJN6031
KUCHING
QAB4950M
Last updated 11 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.60
RON 97
RM 3.20
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.02
+0.07
EURO 5 B7
RM 3.22
+0.07
Last updated 06 Nov, 2025
Related News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%
ECRL project's Kuantan Tunnel will be completed by the end of April.
08-03-2023
Latest News
PLUS To Close Two Bangi Ramps Nightly Until Nov 28
PLUS will close two ramps near Bangi nightly from 10PM to 5AM starting today until Nov 28.
10-11-2025
KLIA Aerotrain Halts Daily Midnight To 5am For Maintenance
KLIA Aerotrain will stop running every night from midnight to 5am for routine checks and maintenance.
10-11-2025
4.4 Mil Old Vehicles Threaten Road Safety, Incentive Alone Insufficient
JPJ data shows over 4.4 million old vehicles are still on the road making up about 17% of the country’s 25.7m active vehicles.
10-11-2025
Proton Shifts 15,575 Units In Oct 2025, Outgoing Saga Still Leads
Proton closes Oct 2025 by shifting 15,575 units, outgoing Saga sales spikes to 12-year high ahead of successor’s debut.
10-11-2025
JPJ Warns Public Against Fake “Free Driving Licence” TikTok Scams
JPJ has warned the public about fake TikTok posts claiming people can get free driving licences without any tests.
10-11-2025
RM3b Juru–Sungai Dua Link Cuts Travel Time To Just 20 Minutes
RM3 billion traffic dispersal project aims to slash travel time between Juru and Sungai Dua from an hour to just 20 minutes.
10-11-2025
Nanta: Barrier-Free ANPR Toll System Still at RFP Stage
The Works Ministry is inviting proposals for an ANPR-based barrier-free MLFF toll system.
10-11-2025
New Leapmotor 3S Showroom Opens In Ipoh, Perak
Perak state capital of Ipoh gains new Leapmotor brand 3S showroom and service outlet operated by dealers CST Auto.
07-11-2025
Show More
trending_flat