ECRL Kelantan Expected To Be Completed Six Months Earlier
The East Coast Rail Link (ECRL) in Kelantan is expected to be completed six months ahead of schedule in January 2027.
Nik Soh Yaacoub, deputy director of the Kelantan Public Works Department, told Bernama that the project has reached 61.97 percent completion with a total workforce of 1,500. He stated that the project's current status included bridge construction, land reclamation, and piling, as well as the start of construction on the state's first ECRL station.
Nik Soh is confident that the project will be completed six months ahead of schedule due to the progress of the work being done by China Communications Construction Company Ltd (CCCC) and Malaysia Rail Link (MRL).
"The seriousness demonstrated by CCCC and MRL, as well as the technological sophistication used in implementing this project, is one of the contributors to the project's rapid implementation," he said.
Furthermore, Nik Soh stated that the technology brought by CCCC not only saves time in completing projects but also saves manpower.
"In terms of the iron fabrication process, new technology is used, which saves time and manpower." Furthermore, it is possible to maintain cleanliness while reducing waste production.
"With the initial expectation that construction of the project will be completed, this facility can also be used indirectly by the community, especially when Kelantan hosts the Malaysian Games (SUKMA) in 2026," he said.
Source: Bernama
Gallery
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPY4570
SELANGOR
BSK132
JOHOR
JYK7403
PULAU PINANG
PRV5269
PERAK
APC3966
PAHANG
CFE842
KEDAH
KGC9082
NEGERI SEMBILAN
NEH5632
KOTA KINABALU
SJN5895
KUCHING
QAB4928M
Last updated 09 Nov, 2025
Fuel Price
Petrol
RON 95
RM 2.60
RON 97
RM 3.20
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.02
+0.07
EURO 5 B7
RM 3.22
+0.07
Last updated 06 Nov, 2025
Related News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%
ECRL project's Kuantan Tunnel will be completed by the end of April.
08-03-2023
Latest News
New Leapmotor 3S Showroom Opens In Ipoh, Perak
Perak state capital of Ipoh gains new Leapmotor brand 3S showroom and service outlet operated by dealers CST Auto.
07-11-2025
KLIMS 2026 – ‘Beyond Mobility’ Theme Retained, Key Brands Announced
KLIMS 2026 set to retain ‘Beyond Mobility’ theme, over 20 key participating brands confirmed too.
07-11-2025
Govt Moves To Tighten FRU Vehicle Safety After Teluk Intan Crash
The Cabinet is reviewing new safety measures for FRU vehicles following the tragic Teluk Intan crash.
07-11-2025
JPJ Targets Firms Hiring Unlicensed Foreign Drivers
JPJ will launch operations nationwide to take action against companies employing foreigners without valid driving licences.
07-11-2025
MOT Steps Up Public Transport, Road Safety Upgrades
MOT rolls out new buses, terminals, and safety rules to improve travel and reduce road risks.
07-11-2025
CKD Excise Duty Revision: Govt Studying Measures to Ease Impact
Govt exploring ways to cushion a potential 10-30% car price hike once CKD excise duty exemption expires.
07-11-2025
Loke Urges Malaysians To Clear 5.5 Million Unpaid JPJ Summonses By Year-End
Transport Minister Anthony Loke says over 5.5 million JPJ summonses remain unpaid, urges motorists to settle them before year-end too.
07-11-2025
GWM Malaysia 3rd Anniversary Sees RM150,000 In Rewards Up For Grabs
RM150,000 in rewards, comprised of premium gadgets and more, are up for grabs from GWM Malaysia as it celebrates its third year anniversary.
07-11-2025
Show More
trending_flat