ECRL Kelantan Expected To Be Completed Six Months Earlier
The East Coast Rail Link (ECRL) in Kelantan is expected to be completed six months ahead of schedule in January 2027.
Nik Soh Yaacoub, deputy director of the Kelantan Public Works Department, told Bernama that the project has reached 61.97 percent completion with a total workforce of 1,500. He stated that the project's current status included bridge construction, land reclamation, and piling, as well as the start of construction on the state's first ECRL station.
Nik Soh is confident that the project will be completed six months ahead of schedule due to the progress of the work being done by China Communications Construction Company Ltd (CCCC) and Malaysia Rail Link (MRL).
"The seriousness demonstrated by CCCC and MRL, as well as the technological sophistication used in implementing this project, is one of the contributors to the project's rapid implementation," he said.
Furthermore, Nik Soh stated that the technology brought by CCCC not only saves time in completing projects but also saves manpower.
"In terms of the iron fabrication process, new technology is used, which saves time and manpower." Furthermore, it is possible to maintain cleanliness while reducing waste production.
"With the initial expectation that construction of the project will be completed, this facility can also be used indirectly by the community, especially when Kelantan hosts the Malaysian Games (SUKMA) in 2026," he said.
Source: Bernama
Gallery
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQF3625
SELANGOR
BSL2681
JOHOR
JYN6170
PULAU PINANG
PRX184
PERAK
APD6394
PAHANG
CFE5664
KEDAH
KGD5779
NEGERI SEMBILAN
NEJ1098
KOTA KINABALU
SJP4608
KUCHING
QAB8443M
Last updated 27 Dec, 2025
Fuel Price
Petrol
RON 95
RM 2.64
-0.02
RON 97
RM 3.27
-0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.06
-0.02
EURO 5 B7
RM 3.26
-0.02
Last updated 11 Dec, 2025
Related News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%
ECRL project's Kuantan Tunnel will be completed by the end of April.
08-03-2023
Latest News
Ops Lancar: Johor Police Issue Over 4,400 Summonses In Two Days
Johor police issued 4,433 traffic summonses in just the first two days of their Christmas and New Year road operations.
26-12-2025
MOF Extends OMV Relief: CKD Vehicle Prices Safe Until June 2026
MOF confirms that non-manufacturing costs under OMV remain fully excise-exempt for another six-months.
26-12-2025
iCaur V23 Earns 5-Star ASEAN NCAP Rating
Newly launched iCaur V23 EV SUV posts strong 91.02-point score in ASEAN NCAP 2021–2025 protocol crash-tests.
24-12-2025
Chery Tiggo 7 PHEV Earns 5-Star ASEAN NCAP Score
Chery Tiggo 7 PHEV C-SUV earns 5-star ASEAN NCAP rating, posting an impressive 94.68-point score.
24-12-2025
Updated Fuel Prices From 25 To 31 December
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 25 to 31 December, 2025, the rates are as such.
24-12-2025
Malaysian EV Market Buzzing Ahead Of Year-End Tax Changes
EV registrations jump as buyers rush to beat the fully imported tax exemption, with Tesla, BYD, and Proton leading the charge.
24-12-2025
DBKL Deploys Smart Traffic Light System Worth RM42 Million
DBKL deploys and maintains new ITMAX adaptive, data-driven smart traffic light systems across Kuala Lumpur.
24-12-2025
Penang Expects 2.2M Vehicles This Christmas, School Holidays
More than 2.2 million vehicles are expected to enter Penang during the Christmas season and school holidays.
24-12-2025
Show More
trending_flat