ECRL Kelantan Expected To Be Completed Six Months Earlier
The East Coast Rail Link (ECRL) in Kelantan is expected to be completed six months ahead of schedule in January 2027.
Nik Soh Yaacoub, deputy director of the Kelantan Public Works Department, told Bernama that the project has reached 61.97 percent completion with a total workforce of 1,500. He stated that the project's current status included bridge construction, land reclamation, and piling, as well as the start of construction on the state's first ECRL station.
Nik Soh is confident that the project will be completed six months ahead of schedule due to the progress of the work being done by China Communications Construction Company Ltd (CCCC) and Malaysia Rail Link (MRL).
"The seriousness demonstrated by CCCC and MRL, as well as the technological sophistication used in implementing this project, is one of the contributors to the project's rapid implementation," he said.
Furthermore, Nik Soh stated that the technology brought by CCCC not only saves time in completing projects but also saves manpower.
"In terms of the iron fabrication process, new technology is used, which saves time and manpower." Furthermore, it is possible to maintain cleanliness while reducing waste production.
"With the initial expectation that construction of the project will be completed, this facility can also be used indirectly by the community, especially when Kelantan hosts the Malaysian Games (SUKMA) in 2026," he said.
Source: Bernama
Gallery



Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPM4921
SELANGOR
BSG7503
JOHOR
JYE4625
PULAU PINANG
PRT785
PERAK
ANY6891
PAHANG
CFD485
KEDAH
KGB6356
NEGERI SEMBILAN
NEG6323
KOTA KINABALU
SJL9999*
KUCHING
QAB8364L
Last updated 04 Aug, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.17
-0.04
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.91
EURO 5 B7
RM 3.11
Last updated 31 Jul, 2025
Related News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%
ECRL project's Kuantan Tunnel will be completed by the end of April.
08-03-2023
ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide
Selangor Forestry Department found that the alleged land clearing activities in the Selangor State Park are part of the ECRL project.
06-02-2023
Kelantan And Terengganu ECRL Project Affected By Floods
The floods last week impacted around 70% of the construction work at sections 1 and 2 of the East Coast Rail Line (ECRL), which spans 82 kilometres from Tunjong here to Setiu in Terengganu.
28-12-2022
Latest News
JPJ: RM3 Million Rolls-Royce Among 53 Vehicles Seized
JPJ Ops Luxury 2.0 sees 53 high-end vehicles, including a Rolls-Royce Cullinan and Lamborghini Huracan, seized over expired road tax and insurance.
02-08-2025
Malaysian-Bound Toyota Yaris Cross Receives 5-Star ASEAN NCAP Score
The DNGA-based Toyota Yaris Cross just received a five-star score for the ASEAN NCAP crash test. Coming to Malaysia soon?
02-08-2025
Chery’s Lepas Brand Entering Malaysia Soon? ‘Official’ IG Page Sighted
New ‘official’ IG page we sighted by chance indicates Chery’s new Lepas sub-brand is set to enter Malaysia very soon.
01-08-2025
Govt Looking To Revive MEX II Highway With New Completion Plan
The government is working with bondholders to restart the long-delayed MEX II Highway.
01-08-2025
2025 Proton X50 Facelift Sees 999 Units Shifted In 5 Days
2025 Proton X50 Facelift sees 999 units delivered in just five days, production hits 2,000 units mark as of end of July too.
01-08-2025
Bridgestone Turanza 6 Tyres Launched in Malaysia – 14 to 21 Inches, EV-Ready
Bridgestone Malaysia has introduced the new Turanza 6 tyres in Malaysia, with sizes ranging from 14 to 21 inches.
01-08-2025
Johor Proposes RTS2 Link Between Iskandar Puteri and Tuas
With Bukit Chagar terminal nearing completion, Johor eyes new RTS2 link to Tuas to further ease cross-border travel.
01-08-2025
PAC to KKR: Avoid Costly Missteps in Delayed MLFF Rollout
PAC wants KKR to ensure no hidden costs to government or road users in the upcoming MLFF toll system rollout.
01-08-2025
Show More
trending_flat