ECRL Kelantan Expected To Be Completed Six Months Earlier

Anis

Share via

image.png The East Coast Rail Link (ECRL) in Kelantan is expected to be completed six months ahead of schedule in January 2027.

Nik Soh Yaacoub, deputy director of the Kelantan Public Works Department, told Bernama that the project has reached 61.97 percent completion with a total workforce of 1,500. He stated that the project's current status included bridge construction, land reclamation, and piling, as well as the start of construction on the state's first ECRL station.

Nik Soh is confident that the project will be completed six months ahead of schedule due to the progress of the work being done by China Communications Construction Company Ltd (CCCC) and Malaysia Rail Link (MRL). image.png

"The seriousness demonstrated by CCCC and MRL, as well as the technological sophistication used in implementing this project, is one of the contributors to the project's rapid implementation," he said.

Furthermore, Nik Soh stated that the technology brought by CCCC not only saves time in completing projects but also saves manpower.

"In terms of the iron fabrication process, new technology is used, which saves time and manpower." Furthermore, it is possible to maintain cleanliness while reducing waste production.

image.png


"With the initial expectation that construction of the project will be completed, this facility can also be used indirectly by the community, especially when Kelantan hosts the Malaysian Games (SUKMA) in 2026," he said.

Source: Bernama

Gallery

Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VQD7825

SELANGOR

BSK8756

JOHOR

JYM8964

PULAU PINANG

PRW6011

PERAK

APD4031

PAHANG

CFE4685

KEDAH

KGD4501

NEGERI SEMBILAN

NEH9159

KOTA KINABALU

SJP3024

KUCHING

QAB7469M

Last updated 17 Dec, 2025

Fuel Price

Petrol

RON 95

RM 2.64

-0.02

RON 97

RM 3.27

-0.02

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 3.06

-0.02

EURO 5 B7

RM 3.26

-0.02

Last updated 11 Dec, 2025

Related News

Auto News

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023

Latest News

Auto News

No More Heavy Vehicles On Kuala Terengganu Drawbridge From Jan 1

Heavy vehicles will no longer be allowed to use the Kuala Terengganu drawbridge from Jan 1.

16-12-2025
Auto News

OMODA & JAECOO Wrap Up 2025 With Season of Rewards

OMODA & JAECOO 2025 Season of Rewards offers extended service packages and practical ownership benefits.

Auto News

Overloaded Trucks Crackdown Showing Results, Transport Rates Remain Stable

Strict enforcement against overloaded trucks is paying off, improving road safety and transport efficiency without hiking rates.

16-12-2025
Auto News

Gemas-JB ETS Needs Better Access To Curb City Traffic - Expert

Experts urge improved first-mile access, feeder buses, and park-and-ride options for the Gemas- JB ETS.

16-12-2025
Auto News

SCS Adopts Advanced European Testing Systems

SCS raises the bar for vehicle inspections with advanced European testing technology.

Auto News

Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash

Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.

15-12-2025
Auto News

Federal Highway Won’t Be Upgraded, Costs Deemed Too High

Despite worsening traffic conditions, the Federal Highway will not be upgraded, with the government citing high costs.

Auto News

Bollards Are There for Your Safety, Not Decoration - DBKL

DBKL is reminding the public that bollards play a crucial role in keeping pedestrians safe.

15-12-2025

Show More

trending_flat
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.