ECRL Project Progress Surpasses 56% - Loke

Anis

Share via

ECRL-56-Completion-Minister-Loke.jpg

Transport Minister Anthony Loke Siew Fook announced that the East Coast Rail Link (ECRL) project has surpassed 56% of its progress as of November, marking a significant milestone.
This development is in line with the project's completion schedule, which calls for the Gombak Integrated Terminal to be completed by December 2026, and the location of Kota Bharu in Kelantan. By January 2027, operational readiness is expected to be achieved.

Minister Loke stressed the project's transition into a new construction phase, involving flyover beam installations, train station, and depot constructions, highlighting this year as the peak construction phase.

According to The Star, the minister also emphasizes that in order to facilitate passenger and cargo train operations, future stages will concentrate on electrification, signaling, and telecommunication system installations. 03-page-3-chung_2257706_20220325074846-(1).jpg

When it's completed, residents of Kuantan will only need to travel 1.5 hours to get to Kuala Lumpur instead of the three hours it takes now by road. Minister Loke highlighted that 23,000 laborers were involved in 1,900 construction sites, with drill and blast techniques being used to excavate 26 tunnels.

One of the major turning points will be the 16.39 km Genting twin tunnel, which is currently under construction and should be finished in the second quarter of 2025. More than 60km of flyover beams have been installed over the 145km ECRL flyover. The project's overall goal is to improve transportation infrastructure in Pahang, Terengganu, Kelantan, and Selangor by building 20 stations.




Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VPS6031

SELANGOR

BSH8371

JOHOR

JYG8397

PULAU PINANG

PRU1525

PERAK

APB2738

PAHANG

CFD4995

KEDAH

KGC3086

NEGERI SEMBILAN

NEH1445

KOTA KINABALU

SJM6409

KUCHING

QAB1806M

Last updated 20 Sep, 2025

Fuel Price

Petrol

RON 95

RM 2.05

RON 97

RM 3.21

+0.03

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.93

+0.03

EURO 5 B7

RM 3.13

+0.03

Last updated 18 Sep, 2025

Related News

Auto News

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023
Auto News

ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

Selangor Forestry Department found that the alleged land clearing activities in the Selangor State Park are part of the ECRL project.

06-02-2023
Auto News

Kelantan And Terengganu ECRL Project Affected By Floods

The floods last week impacted around 70% of the construction work at sections 1 and 2 of the East Coast Rail Line (ECRL), which spans 82 kilometres from Tunjong here to Setiu in Terengganu.

28-12-2022

Latest News

Auto News

TQ Wuling Bingo EV CKD Production Set to Begin in Dec 2025

The new SGMW-Tan Chong joint venture EV plant will start its local assembly efforts this Dec with the TQ Wuling Bingo.

19-09-2025
Auto News

MyKad Checks Urged Ahead of Fuel Price Drop

Home minister urges Malaysians to fix faulty MyKad chips early to enjoy the upcoming targeted fuel subsidy.

19-09-2025
Auto News

GAC Emkoo Awarded 5-star ASEAN NCAP Rating

Upcoming GAC Emkoo C-SUV earns coveted 5-star rating form ASEAN NCAP crash-testing regime.

19-09-2025
Auto News

KLCC Roads Closed Saturday For Sarong Music Run

Expect road closures and traffic delays around KLCC tomorrow for the Malaysia Sarong Music Run 2025.

19-09-2025
Auto News

Sand, Log Trucks Dominate Kelantan Roads - JPJ

Sand and log trucks make up most heavy vehicle traffic in Kelantan, with fewer overloaded cases.

19-09-2025
Auto News

Customs Seizes 32 Imported Cars Worth RM8.45 Million

Ops Purple uncovered vehicles stored beyond the legal limit, with unpaid duties and taxes totalling RM5.38 million.

19-09-2025
Auto News

MAA: Aug 2025 Sales Up 4.2%, YoY Growth Modest at 0.6%

Latest MAA Aug 2025 sales figures see PVs contribute 67,302 units, with CVs taking the remaining 5,739.

Auto News

PLUS Kulai–Senai Smart Lane Closed Starting Sept 22

PLUS closes Kulai–Senai Smart Lane on Sept 22 for road widening. Separately, it also continues RM37m restroom refurbishments across its highway network.

Show More

trending_flat
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.