ECRL Project Progress Surpasses 56% - Loke

Anis

Share via

ECRL-56-Completion-Minister-Loke.jpg

Transport Minister Anthony Loke Siew Fook announced that the East Coast Rail Link (ECRL) project has surpassed 56% of its progress as of November, marking a significant milestone.
This development is in line with the project's completion schedule, which calls for the Gombak Integrated Terminal to be completed by December 2026, and the location of Kota Bharu in Kelantan. By January 2027, operational readiness is expected to be achieved.

Minister Loke stressed the project's transition into a new construction phase, involving flyover beam installations, train station, and depot constructions, highlighting this year as the peak construction phase.

According to The Star, the minister also emphasizes that in order to facilitate passenger and cargo train operations, future stages will concentrate on electrification, signaling, and telecommunication system installations. 03-page-3-chung_2257706_20220325074846-(1).jpg

When it's completed, residents of Kuantan will only need to travel 1.5 hours to get to Kuala Lumpur instead of the three hours it takes now by road. Minister Loke highlighted that 23,000 laborers were involved in 1,900 construction sites, with drill and blast techniques being used to excavate 26 tunnels.

One of the major turning points will be the 16.39 km Genting twin tunnel, which is currently under construction and should be finished in the second quarter of 2025. More than 60km of flyover beams have been installed over the 145km ECRL flyover. The project's overall goal is to improve transportation infrastructure in Pahang, Terengganu, Kelantan, and Selangor by building 20 stations.




Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VPG4395

SELANGOR

BSF5104

JOHOR

JYA5140

PULAU PINANG

PRR5012

PERAK

ANW6841

PAHANG

CFC1460

KEDAH

KGA9457

NEGERI SEMBILAN

NEG2403

KOTA KINABALU

SJL3132

KUCHING

QAB5163L

Last updated 18 Jun, 2025

Fuel Price

Petrol

RON 95

RM 2.05

RON 97

RM 3.07

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.74

EURO 5 B7

RM 2.94

Last updated 12 Jun, 2025

Related News

Auto News

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023
Auto News

ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

Selangor Forestry Department found that the alleged land clearing activities in the Selangor State Park are part of the ECRL project.

06-02-2023
Auto News

Kelantan And Terengganu ECRL Project Affected By Floods

The floods last week impacted around 70% of the construction work at sections 1 and 2 of the East Coast Rail Line (ECRL), which spans 82 kilometres from Tunjong here to Setiu in Terengganu.

28-12-2022
Auto News

ECRL Will Continue - Loke Siew Fook

The federal government will continue the RM50 billion East Coast Rail Link (ECRL) project, according to Loke Siew Fook, the minister of transportation.

07-12-2022

Latest News

Auto News

Over 600 Commercial Vehicles Fail Tyre Checks Under New JPJ Rules

Since JPJ's stricter checks began this month, over 600 commercial vehicles have failed tyre tests, says Puspakom.

18-06-2025
Auto News

Special Mid-Year Deals from MG Motor Malaysia for MG5 & MG4

MG Motor Malaysia has announced special mid-year deals for both the MG5 fastback saloon and the MG4 EV hatch.

18-06-2025
Auto News

Repo Man Fined for Trespass – Know Your Rights

A 24-year-old repossession agent was fined RM2,800 for trespassing into a car owner's Bandar Amanjaya home last Saturday.

18-06-2025
Auto News

Report: New Mazda Models Could Rev Up BAuto’s Prospects

Despite analyst’s downgrades, Carz.com.my sees strong potential in BAuto's upcoming Mazda models.

18-06-2025
Auto News

Amir Hamzah: RON95 Subsidy Coming Reform Before 2026 Carbon Tax

RON95 petrol subsidies to be rationalised ahead of 2026 carbon tax rollout, comes as part of Malaysia’s energy transition.

17-06-2025
Auto News

Malaysian Single-Mom Truckers Make Local Headlines

In a male-dominated industry, 39-year-old Irzunika Idris and 40-year-old Marlia Ramli became truck drivers to support their kids.

17-06-2025
Auto News

Rapid KL On-Demand Adds 5 New Zones — Cyberjaya & Putrajaya Included

The Rapid KL On-Demand service has been expanded to five new zones, including Cyberjaya and Putrajaya.

17-06-2025
Auto News

PRO-NET Opens Three New Proton e.MAS & smart Dealerships

PRO-NET has expanded both its Proton e.MAS and smart dealer network by opening three new outlets in Malaysia.

17-06-2025

Show More

trending_flat
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.