West Coast Expressway (WCE) Section 11 Beruas To Taiping Opens Before Raya
Section 11 of the West Coast Expressway (WCE), which runs from Beruas to Taiping (South), is expected to open in the first quarter of this year, and no later than April, Bernama reported.
Nadzrol Fadzilah Ahmad, Deputy Director-General (Development) of the Malaysian Highway Authority (LLM), stated that efforts are being made to commission the section before Chinese New Year, but he is confident that it will be operational before Hari Raya Aidilfitri.
“The aim is to help people avoid congestion, but it is still subjective because safety is our priority,” he said at a press conference here yesterday.
He also stated that the toll booths would be open for free use as usual for a limited time.

Meanwhile, West Coast Expressway (WCE) Holdings Bhd CEO Lyndon Alfred Felix stated that construction progress had reached 98% by December 31, last year.
“We are now entering the inspection, supervision and certification phase by LLM. We have to go through these phases before this section can be opened to all road users,” he added.
Saarani earlier stated that the WCE project was critical because it provided a strategic route for expanding the transportation network not only between cities and districts, but also connecting Perak to economic growth centers, beginning with Port Klang, Lumut Port, and Penang Port.
This route is also significant because it serves as a catalyst for Perak's plan to drive socioeconomic growth along the west coast and transform the state's tourism landscape by improving access to strategic destinations in accordance with the Visit Perak Year 2024 initiative. "When it opens later, road users will have alternative routes to the existing roads to areas on the west coast of Perak such as Teluk Intan, Manjung, Pulau Pangkor, Beruas, Trong, Changkat Jering and Taiping," the official said.
The 233-kilometer-long project, being carried out by West Coast Expressway Sdn Bhd as part of a privatisation initiative, connects Taiping and Banting in Selangor.
To date, five of the eleven sections of the WCE expressway routes have been opened to traffic: Sections 5 (Klang-Kapar) and 6 (Kapar-Assam Java) in Selangor, Sections 8 (Hutan Melintang-Teluk Intan), 9 (Kampung Lekir-Changkat Cermin), and 10 (Changkat Cermin-Beruas) in Perak. Section 11 (Beruas-South Taiping), which spans 35.5 kilometers, completes the WCE section in the state of Perak.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQR5571
SELANGOR
BSN5534
JOHOR
JYT6276
PULAU PINANG
PSA7970
PERAK
APG2359
PAHANG
CFF9175
KEDAH
KGE9043
NEGERI SEMBILAN
NEJ8524
KOTA KINABALU
SJR356
KUCHING
QAB4536N
Last updated 30 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
WCE: Six New Toll Plazas Planned Along Melaka’s 69 KM Stretch
WCE set to add six new tolls along Melaka’s 69 KM stretch to ease congestion and spread out traffic flow.
10-12-2025
WCE Reports 48% Jump In Toll Revenue, Eyes Full Completion By 2027
Toll collections on the WCE surged 48% in Q2 to RM44.1 million, with the firm aiming for full completion by March 2027.
27-11-2025
Court Upholds Land Takeover For WCE Despite Residents’ Complaint
Judge rules the acquisition for WCE valid even without direct notice, as Kampung Jawa landowners gear up for a crucial valuation hearing.
26-11-2025
WCE Road Closure on Nov 9 For Klang Royal City Marathon 2025
Parts of West Coast Expressway (WCE) will temporarily close for Klang Royal City Marathon on Sunday, Nov 9 2025.
06-11-2025
Selangor Govt Will Decide Fate Of 19 WCE-Affected Residents
The Selangor govt is set to decide soon on the fate of 19 Kampung Jawa residents affected by the West Coast Expressway project.
03-11-2025
Hauliers Warn WCE Delays Hurting Logistics and Economy
The Association of Malaysian Hauliers says delays in completing Section 3 of the WCE are disrupting cargo flow and driving up costs.
29-09-2025
West Coast Expressway On Track For 2027 Completion
The West Coast Expressway is on track for full completion by 2027, with eight of its 11 sections already open.
27-08-2025
Hauliers Demand Swift WCE Land Fix
Association of Malaysian Hauliers urges swift resolution of land disputes delaying completion of the WCE Section 3.
11-08-2025
Latest News
Motorcyclist Dies After Being Hit by Speeding Car in Klang
Tragic fatal crash in Klang: A motorcyclist was killed on the spot after a car allegedly speeding and overtaking on a double yellow line struck him on Jalan Bunga Raya Barat behind MBDK on 29 March 2026.
29-03-2026
The RM5,000 Raya Flex: Why Malaysians are Risking a Monthly Salary to Rent an Alphard
Is renting an Alphard for RM5,000 a waste or a genius move? We break down the 'Raya Flex' cost, from RM10k insurance premiums to the 'Executive Lounge' comfort that saves your back on an 18-hour East Coast jam.
27-03-2026
Safe Passage at Hormuz: Why Malaysia’s Special Deal with Iran Won't Lower Your Petrol Price
PM Anwar secured safe passage for Malaysian ships, so why is RON95 hitting RM3.87/L? We decode the 400% insurance surge and the new 200L BUDI95 quota.
27-03-2026
Fuel Subsidy Update: Your 300L Monthly Quota Could Drop to 200L This April
If you rely on subsidised RON95 petrol to get to work, take note: a major change is coming to your monthly fuel budget.
26-03-2026
Fuel Price Shock: Diesel Spikes to RM5.52, Unsubsidised RON95 Jumps 60 Sen
Massive 80-sen spike for Diesel (RM5.52) and 60-sen jump for unsubsidised RON95 (RM3.87). Learn how the Budi Madani RM300 aid and BUDI95 quota protect Malaysian drivers this week.
26-03-2026
Strait of Hormuz to Malaysia: Why We’re Paying for a War 6,000km Away
Why is RON97 at RM4.55/L? We decode the Strait of Hormuz conflict, the May 2026 subsidy deadline, and why Malaysia imports oil despite being a producer.
19-03-2026
From 82 Minutes to 8: How the Mutiara Line is Giving Penangites Their Time Back
Is the 80-minute Penang Bridge crawl finally ending? The Mutiara Line LRT links Butterworth to Komtar in just 8 minutes. Get the latest 2026 project updates, station lists, and more.
17-03-2026
The 2026 Proton X90 Buyer’s Warning: 5 Critical Safety Features You Are No Longer Getting
ASEAN NCAP revokes Proton X90’s 5-star rating. The 2026 facelift is downgraded to 1-star after stripping critical ADAS features. Is your family safe? Get the full safety specs here.
16-03-2026
Show More
trending_flat