230km Southern WCE Feasibility Study To Conclude By Dec
A new 230km stretch of the West Coast Expressway (WCE) from Banting, Selangor, to Gelang Patah, Johor, could be on the cards, with its feasibility study slated for completion by December 16.
Johor Works, Transport, Infrastructure and Communications Committee chairman Mohamad Fazli Mohamad Salleh said the highway would give motorists another option besides the North-South Expressway, which often grinds to a halt during festive seasons and weekends.
The route would snake through Selangor, Negeri Sembilan, Melaka and Johor, linking 11 districts and 14 local authorities. In Johor, it would pass Batu Pahat, Johor Bahru, Muar, Pontian and Tangkak.

“The study began in June and runs until December. We’re also holding three focus group sessions to get input from stakeholders. Once it’s done, we’ll have a full report and traffic model to decide the way forward,” Mohamad Fazli said.
He believes the project will be a game changer for southern connectivity, easing traffic, cutting travel times and boosting logistics and investment opportunities.

Photo: BH.
“By 2030, we expect about 26% of traffic to move to this new route. It’s a long-term fix for mobility issues in the southern region, and we’re hopeful the development goes smoothly,” Fazli added.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQG826
SELANGOR
BSL3635
JOHOR
JYN9330
PULAU PINANG
PRX2146
PERAK
APD7407
PAHANG
CFE6125
KEDAH
KGD6390
NEGERI SEMBILAN
NEJ1574
KOTA KINABALU
SJP5251
KUCHING
QAB9077M
Last updated 31 Dec, 2025
Fuel Price
Petrol
RON 95
RM 2.64
-0.02
RON 97
RM 3.27
-0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.06
-0.02
EURO 5 B7
RM 3.26
-0.02
Last updated 11 Dec, 2025
Related News
WCE: Six New Toll Plazas Planned Along Melaka’s 69 KM Stretch
WCE set to add six new tolls along Melaka’s 69 KM stretch to ease congestion and spread out traffic flow.
10-12-2025
WCE Reports 48% Jump In Toll Revenue, Eyes Full Completion By 2027
Toll collections on the WCE surged 48% in Q2 to RM44.1 million, with the firm aiming for full completion by March 2027.
27-11-2025
Court Upholds Land Takeover For WCE Despite Residents’ Complaint
Judge rules the acquisition for WCE valid even without direct notice, as Kampung Jawa landowners gear up for a crucial valuation hearing.
26-11-2025
WCE Road Closure on Nov 9 For Klang Royal City Marathon 2025
Parts of West Coast Expressway (WCE) will temporarily close for Klang Royal City Marathon on Sunday, Nov 9 2025.
06-11-2025
Selangor Govt Will Decide Fate Of 19 WCE-Affected Residents
The Selangor govt is set to decide soon on the fate of 19 Kampung Jawa residents affected by the West Coast Expressway project.
03-11-2025
Hauliers Warn WCE Delays Hurting Logistics and Economy
The Association of Malaysian Hauliers says delays in completing Section 3 of the WCE are disrupting cargo flow and driving up costs.
29-09-2025
West Coast Expressway On Track For 2027 Completion
The West Coast Expressway is on track for full completion by 2027, with eight of its 11 sections already open.
27-08-2025
Hauliers Demand Swift WCE Land Fix
Association of Malaysian Hauliers urges swift resolution of land disputes delaying completion of the WCE Section 3.
11-08-2025
Latest News
China Set to Overtake Japan as World’s Top Auto Seller in 2025
China set to become world’s top auto seller in 2025, overtaking Japan as domestic and overseas sales growth surges.
30-12-2025
KTMB Southern Express Ends Service As ETS Takes Over
KTMB will end the Southern Express on the Gemas–JB Sentral route from Jan 1 to make way for eight daily ETS trips.
30-12-2025
Can Instalment-Based Payment Scheme Help Solve Unpaid Summonses?
Road safety expert suggests instalment-based payment scheme could help resolve unpaid summonses. Do you agree?
30-12-2025
Kelantan Flags 29 Federal Roads For Urgent Repairs
The Kelantan JKR has identified 29 federal roads across nine districts that need urgent repairs.
30-12-2025
Johor-Singapore RTS Completes First Test Run from Wadi Hana To Border
The RTS Link completes its first train test run from Wadi Hana Depot through Bukit Chagar to the Malaysia-Singapore border.
30-12-2025
Higher CBU EV Taxes, Higher Prices: Auto TIV to Fall 2% in 2026
CIMB Securities predicts auto TIV will fall 2% in 2026, driven by higher CBU EV taxes and higher vehicle prices.
30-12-2025
UUM Tops Proton Business Case Study Challenge 2025
Proton Business Challenge 2025 challenged students to step into Proton’s shoes and navigate the EV - ICE balancing act.
30-12-2025
Bukit Bintang To Close Jan 1 & 3 For “I Lite U” Festival
Jalan Bukit Bintang will be fully closed from 6PM on Jan 1 and from 7.30PM to 10PM on Jan 3 for the “I Lite U” Festival.
29-12-2025
Show More
trending_flat