ETS to JB Sentral ‘On Track’, But Not Quite There Yet

Train commuters hoping to ride the Electric Train Service (ETS) all the way to Johor Bahru will need to hold on a little longer. Despite earlier hopes for an August launch, the southern stretch of the line particularly from Kluang to JB Sentral still has significant work left to complete.
A recent inspection by The Star along the 180km alignment between Segamat and JB Sentral revealed that key electrification and signalling infrastructure are still unfinished. The 100KM stretch between Kluang and Johor Bahru, in particular, remains a major bottleneck.
In some areas near JB Sentral, only basic pole structures have been erected. The critical catenary system, which includes contact wires and other components of the overhead line equipment (OHLE) is still missing in several sections.

Experts say installing, testing, and commissioning this OHLE system is a time-consuming process that includes multiple steps such as tensioning, energisation, and safety checks.
While the full 192KM stretch from Gemas to JB was initially touted to be ready this year, progress appears slower than expected. ETS services from Gemas to Segamat began operations back in March, but no tickets beyond Segamat have been offered since.
In response to growing public concern, KTMB has issued a statement reaffirming its commitment to completing the southern ETS expansion. The rail operator stressed that the rollout is being done in phases and is still on track, pending technical and regulatory milestones.

KTMB said trial runs are currently underway on the next stretch between Segamat and Kluang. If all goes well, this segment could be opened next, possibly using existing ETS train sets, provided regulatory approvals come through.
In the background, KTMB is also testing new ETS train sets from China. The first of these, known as the “golden train,” must log at least 8,000 fault-free kilometres before it can enter commercial service, a standard requirement to ensure system integrity.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VRN6411
SELANGOR
BST4150
JOHOR
JD5175J
PULAU PINANG
PSF2841
PERAK
APL2093
PAHANG
CFH6084
KEDAH
KGH8376
NEGERI SEMBILAN
NEL6713
KOTA KINABALU
SJT8664
KUCHING
QAB5054P
Last updated 01 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Govt Plans to Add 50 New Train Sets for KTM ETS & Komuter Services
The government is planning to add 50 new train sets to meet growing demand for KTM ETS & Komuter services.
25-08-2025
Sultan Ibrahim Test-Drives ETS Train KL-Rawang
His Majesty Sultan Ibrahim took the controls of KTMB’s ETS for a test run from Kuala Lumpur to Rawang.
20-08-2025
Two Of 10 New ETS Train Sets Delivered To KTMB
Two of 10 new ETS sets, valued at RM400 million, have already been delivered to KTMB.
06-06-2025
KTM ETS Train Service To Segamat Starts March 15th
ETS train service extends to Segamat from March 15th due to partial completion of the Gemas-Johor Bahru rail project.
13-03-2025
MoT Set to Add 10 New KTM ETS Train Sets in Q1 2025
The Ministry of Transport has procured 10 new KTM ETS train sets, set to be operational later in Q1 2025.
19-12-2024
KTM Double-Track Klang Line Set For March Completion
KTM’s Klang Valley double-track upgrade between Subang Jaya and Klang is expected to be completed by March.
21-01-2026
Fallen Tree Disrupts KTMB Services Again, Safety Concerns Grow
Another track obstruction has caused major delays on KTM routes, renewing concerns over tree management and rail safety.
08-01-2026
KTMB Targets 1.2 Million ETS3 Passengers in 2026, MySawasdee Service Resumes
KTMB targets 1.2 million passengers for its new ETS3 this year, while the MySawasdee train service to Hatyai now resumes.
05-01-2026
Latest News
"Traffic Was Slow Before The Tanker Struck": Horrific 11-Vehicle LPT1 Crash Claims 4 Lives Near Temerloh
Four people, including Kuantan’s Secangkir Cafe founders and their 4-year-old son, were killed after an out-of-control cement tanker triggered an 11-vehicle crash on LPT1 near Temerloh. Read the latest police updates.
01-09-2026
Perodua's Supplier Just Dropped A Huge RM54Mil Clue About A Secret New Model Launching In 2027
Perodua supplier MCE Holdings drops an RM54M clue about a secret 2027 model. Read about the upcoming next-gen Myvi, Bezza facelift, and local ADAS tech.
27-08-2026
Proton Almost Built A RM150,000 Mid-Engined Sports Car Using Lotus Tech & Wira Parts
Did you know Proton almost built a RM150k mid-engined sports car? Discover how 'Project Sepang' combined Lotus engineering, Wira parts, and Petronas tech.
26-08-2026
RM1,000 Trade-In Subsidy For Old Motorcycles: Transport Ministry Considers New Scheme
Got an old motor? MOT is considering a RM1,000 trade-in subsidy to help Malaysian riders upgrade to new CKD bikes. Here is how the proposed scheme works.
26-08-2026
Do You REALLY Have To Give Way To Every Siren? What Experts Say About VIP Convoys vs. Emergencies
Do you legally have to give way to VIP convoys in Malaysia? Here is what traffic laws and safety experts say about sirens, outriders, and RM10k fines.
26-08-2026
"Can I Pass My Diesel Quota To My Family?" — 3 Big Changes Coming To Malaysia’s Diesel Subsidy System
KPDN & MOF to launch 3 diesel subsidy updates in less than a month, covering family quota transfers, sambung bayar eligibility, and easier applications.
24-08-2026
Hannah Yeoh & Amirudin Shari Unveil 5 Emergency Steps To Fix Klang Valley Floods Before Budget 2027
Hannah Yeoh & Amirudin Shari unveil a 5-step Klang Valley flood mitigation plan covering dam reviews, retention ponds, and river desilting before Budget 2027.
24-08-2026
Mat Rempit Shut Down Linkedua Highway Near JPO So They Could Race — Grown Men Aged Up To 45 Arrested
PDRM arrests 8 men aged 26 to 45 after a viral video over the weekend showed street racers shutting down the Linkedua Highway near JPO in Johor for a race.
24-08-2026
Show More
trending_flat