Kelana Jaya Line Signalling Works Delayed, Phase 2 Work Starts Sept 6
The planned upgrade works for Phases 2 and 3 of the Kelana Jaya Line signalling system, originally set to begin on Aug 9, have been postponed to Sept 6.
Prasarana Malaysia Berhad announced recently the delay is to allow more time for testing the newly installed Phase 1 signalling system. The additional tests are essential to evaluate the system's performance in real-world conditions and to reduce the chances of future disruptions.
For Phase 1, the upgrades were done during overnight maintenance hours as the works were confined to depot areas and did not impact the main train service. The entire project is part of a broader effort to strengthen the system following a major disruption in Nov 2022.
With the revised schedule, Phase 2 works will now take place on selected days in September and October, affecting the KLCC to Gombak stretch. Phase 3 will follow in November, covering stations from Lembah Subang to Ampang Park.
On those specific dates, trains at affected stations will begin operating later than usual, only opening to passengers from 9AM instead of the normal 6AM start. Services at all other stations will run as scheduled.
To ease passenger travel during these disruptions, free shuttle buses and vans will be available between the affected stations.
The new SelTrac Generation 8 system being installed offers real-time data capabilities, stronger cybersecurity, and more reliable communication. It is expected to extend the current system’s lifespan by as much as 20 years.
More information on affected stations and updates can be found at www.myrapid.com.my
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VPM8257
SELANGOR
BSG8453
JOHOR
JYE6362
PULAU PINANG
PRT1721
PERAK
ANY8521
PAHANG
CFD1278
KEDAH
KGB6823
NEGERI SEMBILAN
NEG6617
KOTA KINABALU
SJL9999*
KUCHING
QAB8707L
Last updated 07 Aug, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.17
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.94
+0.03
EURO 5 B7
RM 3.14
+0.03
Last updated 07 Aug, 2025
Related News
Loke Directs Prasarana To Meet On Klang Valley Train Disruptions
Prasarana has been directed by Loke to hold a special meeting to find the source of the technical issues affecting the MRT and LRT lines.
29-03-2023
Prasarana To Spend RM2.8b To Improve Train, Bus Services
A total of RM2.8 billion will be spent by Prasarana to upgrade the train and bus systems.
09-01-2023
Rapid Rail Extends Service At Bukit Jalil Stadium - AFF MITSUBISHI ELECTRIC CUP 2022
Rapid Rail extends operation till 12.30 am (8 Jan) for AFF MITSUBISHI ELECTRIC CUP 2022 at Bukit Jalil National Stadium.
06-01-2023
Kelana Jaya LRT Line Suffers Yet Another Malfunction
RapidKL issued a statement that the delays were caused by a switch malfunctions issue which causes all trains on the line to move slower and stop longer at the platform.
06-01-2023
Ten LRT KJ Line Stations Set for Upgrade – Open From 9 AM on Weekends
Ten LRT stations on the Kelana Jaya line will be upgraded, and their operation times will be affected on weekends.
28-07-2025
Loke: No Political Appointments in Public Transport
Anthony Loke highlights Prasarana’s success as proof that expert leadership delivers results.
05-06-2025
Prasarana Aims For 40% Public Transit Ridership By 2030
Prasarana plans to boost public transport usage to 40% by 2030 through ongoing service and facility improvements.
19-05-2025
Prasarana Implements Safety Measures Following Fatal LRT Incident
Prasarana enhances safety measures, including planned platform upgrades following fatal LRT incident.
01-04-2025
Latest News
Over 39,000 Road Issues Flagged On MyJalan App Since Launch
MyJalan app logs over 39,000 complaints, but most fall outside federal jurisdiction, says Deputy Works Minister.
07-08-2025
PLUS Eyes MLFF ANPR Toll Trials This Month - JustGo Digital App
PLUS will begin trials for automatic number plate recognition (ALPR) toll system with its JustGo Digital App, part of proposed MLFF system, across nine toll plazas this month.
07-08-2025
Kelana Jaya Line Signalling Works Delayed, Phase 2 Work Starts Sept 6
Kelana Jaya Line Phase 2 and 3 signalling works will now begin on Sept 6, with select stations opening later on affected dates.
07-08-2025
UMW Toyota Jul y2025 Sales Total At 8,877 Units
UMW Toyota sees its sales for July 2025 total at 8,877 units, YTD total now up to 53,163 units.
07-08-2025
RM25 Million Allocated to Light Up Dark Federal Roads – KKR
The Works Ministry has allocated RM25 million to light up dark federal roads to prevent future accidents.
07-08-2025
Ops Pengarah: 252 Fined, One With Road Tax Expired For 2 Years
JPJ’s Ops Pengarah nabs dozens driving without licence, including one with road tax expired for two years.
07-08-2025
Aerotrain Disruption A Minor Glitch, ETS3 Project On Track - Loke
KLIA’s Aerotrain glitch was a minor software bug, not a breakdown, while ETS3 to Johor Bahru is on track, says Transport Minister.
07-08-2025
Updated Fuel Prices From 07 To 13 August
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 07 to 13 August, 2025, the rates are as such.
06-08-2025
Show More
trending_flat