LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays

Photo: NST. The long-delayed LRT3 Shah Alam Line is now expected to begin operations by June 2026, with final testing currently underway, Transport Minister Anthony Loke confirmed in the Dewan Negara.
The 37.8km rail line, connecting Bandar Utama in Petaling Jaya to Johan Setia in Klang, will feature 25 stations and key interchange points at Bandar Utama (MRT Kajang Line) and Glenmarie (LRT Kelana Jaya Line).
"Once operational, it is projected to serve around 67,000 commuters daily, improving connectivity across Petaling Jaya, Shah Alam and Klang," Loke said.
However, before trains can start carrying passengers, several technical hurdles must be cleared. The delay, Loke stressed, is not due to cost-cutting measures but unresolved signalling and system stability issues discovered during fault-free run (FFR) testing and commissioning.
"So far, 14 out of 22 train sets have completed trials, with the remainder still undergoing testing. After all trains pass the FFR stage, the Land Public Transport Agency (APAD) will conduct final inspections before approval for operations," he added.
The project’s timeline has shifted multiple times. It was initially slated to open in September 2024, then pushed to December 2025, and now June 2026 following software and system-related issues identified during testing.
Beyond delays, LRT3 has also faced scrutiny over its rising cost. Launched in 2016 with an initial price tag of RM9 billion, the figure later ballooned to RM31.7 billion after previously excluded costs including consultancy fees, operational expenses and interest during construction.
In 2018, the government revised the scope, shelving five stations and cancelling one, which brought the cost down to RM16.63 billion.
Subsequently, five stations which consist of Tropicana, Raja Muda, Temasya, Bukit Raja and Bandar Botanik were reinstated, adding RM5.3 billion to the project and bringing the total cost to RM21.93 billion.

As for accountability, the project carries liquidated ascertained damages (LAD) of RM2.73 million per day for delays, equivalent to 0.024% of the total contract value.
The main contractor, Setia Utama LRT3, a unit of Malaysian Resources Corporation Berhad (MRCB) will be responsible for the compensation, although the final amount will only be determined once the project is fully completed.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQM4793
SELANGOR
BSM6007
JOHOR
JYR7105
PULAU PINANG
PRY8190
PERAK
APF3829
PAHANG
CFF3916
KEDAH
KGE4268
NEGERI SEMBILAN
NEJ5629
KOTA KINABALU
SJQ3644
KUCHING
QAB2664N
Last updated 24 Feb, 2026
Fuel Price
Petrol
RON 95
RM 2.54
RON 97
RM 3.10
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.99
EURO 5 B7
RM 3.19
Last updated 19 Feb, 2026
Related News
LRT3 Shah Alam Line Expected To Open In June
After years of delays, the LRT3 Shah Alam Line could finally begin operations in June, pending final safety tests.
05-02-2026
Prasarana Ridership Jumps 11% in 2025
Prasarana ridership jumps 11% in 2025 hitting 1.31 million users.
07-01-2026
Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.
15-12-2025
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.
12-12-2025
LRT3 Might Be Delayed Again As Testing Encounters Issues - Report
The LRT3, expected to open early next year, may face further delays due to ongoing signalling system issues.
07-12-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
LRT3 Will Begin Operations On Sept 30 - Loke
LRT3 will begin operating on September 30 this year, Transport Minister Anthony Loke announced.
27-02-2025
Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete
The LRT3 project is currently 95.6% complete and is scheduled to start ferrying passengers by Q3 2025.
29-07-2024
Latest News
LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays
The Shah Alam LRT3 line is targeted to begin operations by June 2026, with contractors liable for RM2.73 million per day in delay penalties.
24-02-2026
Johor–Singapore RTS Link Fare Expected at RM15 to RM22 Per Trip
Transport Minister Anthony Loke says the RTS Link could cost between RM15 and RM22 per journey, with fares to be announced in 2H2026.
23-02-2026
Public Review Opens for Revised Penang Mutiara LRT with Cross-Sea Link at Core
MRT Corp opens a three-month public review for the Penang Mutiara LRT, featuring a proposed six-kilometre cross-sea link to Penang Sentral.
23-02-2026
Ops Luxury: JPJ Seizes Sambung Bayar Camry, Owner in Legal Trouble
A Toyota Camry Hybrid was recently confiscated by JPJ in Kedah for being part of a sambung bayar scheme with no valid road tax or insurance.
20-02-2026
Fix Public Transport Reliability Before Limiting Car Ownership - Experts
Experts say improving speed, reliability and first-mile connectivity must come before any move to limit car ownership or introduce congestion charges.
19-02-2026
Updated Fuel Prices From 19 To 25 February
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 12 to 18 February, 2026, the rates are as such.
19-02-2026
JPJ Removes Daily Limit Quota for Queue Numbers at All Offices
The Road Transport Department has announced the removal of the daily limit quota for queue numbers at all its offices.
19-02-2026
Top 5 Best Car Tint in Malaysia
We’ve rounded up the 5 best car tints to keep your cabin comfy, protect your skin, and maintain privacy.
16-02-2026
Show More
trending_flat