LRT3 Shah Alam Line Expected To Open In June
After years of delays and uncertainty, the long-awaited LRT3 Shah Alam Line is finally nearing the finish line, with operations expected to begin by June at the latest and possibly as early as April.
Transport Minister Anthony Loke said the June timeline set by asset owner Prasarana Malaysia Bhd is a conservative one, expressing confidence that the new rail line could be ready sooner if all final tests go smoothly.
He shared the update during a radio interview on Feb 5, offering reassurance to commuters who have been waiting for the project since construction began almost a decade ago.

The LRT3 line was originally slated to start running in October last year, but Loke said the delay was unavoidable as safety checks and technical testing had to be prioritised.
According to him, the most crucial phase in the entire process is the Fault-Free Run (FFR), a stringent test that requires each train to operate for at least 4,000km without encountering a single technical fault.
“Unfortunately, during testing in November and December, we ran into software and signalling issues
"What makes the process especially challenging is that any fault, no matter how minor, forces the test to restart from zero, even if the train had already clocked thousands of kilometres," Loke said.
The good news, however, is that progress has picked up. Loke said the first batch of more than 20 trains designated for the LRT3 line has already successfully passed the Fault-Free Run.
The remaining trains are currently undergoing the same testing process, and once all trial runs are completed, the ministry will give the green light for operations to begin.

Stretching 37.8km, the LRT3 Shah Alam Line connects Bandar Utama in Petaling Jaya to Johan Setia in Klang, running through key areas in the western corridor of the Klang Valley.
Once operational, it is expected to benefit around two million residents, providing a long-needed public transport alternative in areas that have traditionally relied heavily on private vehicles.
The LRT3 project has had a long and bumpy journey. Construction began in 2016, but progress was slowed by major restructuring of work packages, followed by disruptions caused by the Covid-19 pandemic.

Photo: BH.
Over the years, multiple launch deadlines were missed, with the opening pushed back from 2020 to March 2025, and later to October 2025, before being delayed again due to technical challenges.
Once in service, the line is expected to ease traffic congestion, improve connectivity between Petaling Jaya, Shah Alam and Klang, and encourage more people to switch to public transport.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQL2483
SELANGOR
BSM3690
JOHOR
JYR1875
PULAU PINANG
PRY4761
PERAK
APF904
PAHANG
CFF2094
KEDAH
KGE2627
NEGERI SEMBILAN
NEJ4739
KOTA KINABALU
SJQ2097
KUCHING
QAB2095N
Last updated 07 Feb, 2026
Fuel Price
Petrol
RON 95
RM 2.54
+0.02
RON 97
RM 3.10
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.04
EURO 5 B7
RM 3.08
+0.04
Last updated 22 Jan, 2026
Related News
Prasarana Ridership Jumps 11% in 2025
Prasarana ridership jumps 11% in 2025 hitting 1.31 million users.
07-01-2026
Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.
15-12-2025
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.
12-12-2025
LRT3 Might Be Delayed Again As Testing Encounters Issues - Report
The LRT3, expected to open early next year, may face further delays due to ongoing signalling system issues.
07-12-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
LRT3 Will Begin Operations On Sept 30 - Loke
LRT3 will begin operating on September 30 this year, Transport Minister Anthony Loke announced.
27-02-2025
Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete
The LRT3 project is currently 95.6% complete and is scheduled to start ferrying passengers by Q3 2025.
29-07-2024
LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30
A series of intermittent road closures will take place on PLUS and SPRINT highways from July 2 to Sept 30 for LRT3 construction works.
27-06-2024
Latest News
Zeekr 7X 2026 Pricing Updated - From RM183k, Up 1.8%
Zeekr Malaysia updates 7X pricing for 2026 following the end of EV tax incentives, with a modest increase of RM3,000-RM4,000 across variants.
06-02-2026
Perodua CEO: Next-Gen Myvi In The Pipelines, Current Bezza Remains
In rare interview, Perodua CEO details plans for next-gen Myvi hatch, confirms current Bezza remains too.
06-02-2026
UMW Toyota Records Slower January Sales, Down 12% to 4,700 Units
UMW Toyota posts lower January sales as competition intensifies and electrification accelerates.
06-02-2026
Malaysia’s Climate Plans Stop Short of Targeting Cars
Private vehicles are unlikely to face direct climate targets as Malaysians remain heavily dependent on cars.
06-02-2026
My50 Pass: Commuters Save RM100 Monthly
Over 50% of Klang Valley commuters are going digital with the My50 pass, saving RM100 monthly.
06-02-2026
LRT3 Shah Alam Line Expected To Open In June
After years of delays, the LRT3 Shah Alam Line could finally begin operations in June, pending final safety tests.
05-02-2026
First Johor Bahru–Singapore RTS Train Hits Woodlands
The first Johor Bahru–Singapore RTS Link train has arrived in Singapore on Wednesday, as confirmed by LTA.
05-02-2026
MTSB Bill in the Works to Streamline Transport Safety
The MTSB Bill is being drafted to integrate agencies like MIROS and AAIB, ensuring efficient transport safety management.
05-02-2026
Show More
trending_flat