WCE: 29.5 KM Tanjong Karang-Assam Jawa Section is 71% Complete.
According to Works Minister Datuk Seri Alexander Nanta Linggi, the Tanjong Karang-Assam Java section of the West Coast Expressway (WCE) has reached 71% completion and is scheduled to be completed by March 2026.
This stretch runs 29.5 KM and is separated into two sections: Section 7A and Section 7B.
"Section 7A covers the stretch from Assam Java Interchange to Sungai Terap Farm, totaling 19.5 KM, while Section 7B extends from Sungai Terap Farm to Tanjong Karang Interchange, covering 10 KM," said Nanta. "As of April, Section 7A is 91% complete, and Section 7B is at 44%."
Speaking to reporters after inspecting the project's progress, Nanta stated that the new route will reduce traffic congestion, especially on weekends and during the holiday season.
Once completed, this segment is expected to save up to an hour of travel time compared to the present federal road. It’s also tipped to reduce traffic density on the North-South Highway by offering an alternate route.
Nanta also acknowledged the difficulties in constructing these sections due to the soft soil structure, which necessitated tiered reclamation operations. However, he expressed optimism that the project will be finished on time.
Source: BERNAMA
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VPS6031
SELANGOR
BSH8371
JOHOR
JYG8397
PULAU PINANG
PRU1525
PERAK
APB2738
PAHANG
CFD4995
KEDAH
KGC3086
NEGERI SEMBILAN
NEH1445
KOTA KINABALU
SJM6409
KUCHING
QAB1806M
Last updated 20 Sep, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.21
+0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.93
+0.03
EURO 5 B7
RM 3.13
+0.03
Last updated 18 Sep, 2025
Related News
West Coast Expressway On Track For 2027 Completion
The West Coast Expressway is on track for full completion by 2027, with eight of its 11 sections already open.
27-08-2025
Hauliers Demand Swift WCE Land Fix
Association of Malaysian Hauliers urges swift resolution of land disputes delaying completion of the WCE Section 3.
11-08-2025
230km Southern WCE Feasibility Study To Conclude By Dec
Study underway on 230km WCE from Banting to Gelang Patah to ease North-South Expressway jams.
08-08-2025
WCE Sec 2 Toll Enabled; Responds to Klang Eviction Claims
WCE starts toll operations in Seksyen 2 and clarifies illegal evictions claims.
13-06-2025
Hari Raya 2025: Over 140K Vehicles Expected Daily on WCE
Over 140,000 vehicles are expected to use the WCE daily during this upcoming Hari Raya Aidilfitri festive season.
24-03-2025
WCE Section 2 Opens with 240 kW DC Handal Charging Station
WCE Section 2 opens today toll free till 22 Feb, features 240 kW DCFC station by DC Handal.
22-01-2025
ECRL Kelantan LIne 87.8% Complete, On Track for 2026 Completion
ECRL project makes swift progress to reach 87.8% completion, and it appears on track for planned 2027 launch.
16-01-2025
WCE Sees 83% Increment In Traffic & 128% Increment In Toll Collection
WCE sees increased average daily traffic volume by 83% supported by a boost in toll income by 128%.
29-11-2024
Latest News
TQ Wuling Bingo EV CKD Production Set to Begin in Dec 2025
The new SGMW-Tan Chong joint venture EV plant will start its local assembly efforts this Dec with the TQ Wuling Bingo.
19-09-2025
MyKad Checks Urged Ahead of Fuel Price Drop
Home minister urges Malaysians to fix faulty MyKad chips early to enjoy the upcoming targeted fuel subsidy.
19-09-2025
GAC Emkoo Awarded 5-star ASEAN NCAP Rating
Upcoming GAC Emkoo C-SUV earns coveted 5-star rating form ASEAN NCAP crash-testing regime.
19-09-2025
KLCC Roads Closed Saturday For Sarong Music Run
Expect road closures and traffic delays around KLCC tomorrow for the Malaysia Sarong Music Run 2025.
19-09-2025
Sand, Log Trucks Dominate Kelantan Roads - JPJ
Sand and log trucks make up most heavy vehicle traffic in Kelantan, with fewer overloaded cases.
19-09-2025
Customs Seizes 32 Imported Cars Worth RM8.45 Million
Ops Purple uncovered vehicles stored beyond the legal limit, with unpaid duties and taxes totalling RM5.38 million.
19-09-2025
MAA: Aug 2025 Sales Up 4.2%, YoY Growth Modest at 0.6%
Latest MAA Aug 2025 sales figures see PVs contribute 67,302 units, with CVs taking the remaining 5,739.
19-09-2025
PLUS Kulai–Senai Smart Lane Closed Starting Sept 22
PLUS closes Kulai–Senai Smart Lane on Sept 22 for road widening. Separately, it also continues RM37m restroom refurbishments across its highway network.
19-09-2025
Show More
trending_flat