WCE: 29.5 KM Tanjong Karang-Assam Jawa Section is 71% Complete.

Kumeran Sagathevan

Share via

WCE-Sec-7-(3).jpg


According to Works Minister Datuk Seri Alexander Nanta Linggi, the Tanjong Karang-Assam Java section of the West Coast Expressway (WCE) has reached 71% completion and is scheduled to be completed by March 2026.

This stretch runs 29.5 KM and is separated into two sections: Section 7A and Section 7B.


WCE-Sec-7-(6).jpg


"Section 7A covers the stretch from Assam Java Interchange to Sungai Terap Farm, totaling 19.5 KM, while Section 7B extends from Sungai Terap Farm to Tanjong Karang Interchange, covering 10 KM," said Nanta. "As of April, Section 7A is 91% complete, and Section 7B is at 44%."

Speaking to reporters after inspecting the project's progress, Nanta stated that the new route will reduce traffic congestion, especially on weekends and during the holiday season.


WCE-Sec-7-(5).jpgWCE-Sec-7-(2).jpg


Once completed, this segment is expected to save up to an hour of travel time compared to the present federal road. It’s also tipped to reduce traffic density on the North-South Highway by offering an alternate route.

Nanta also acknowledged the difficulties in constructing these sections due to the soft soil structure, which necessitated tiered reclamation operations. However, he expressed optimism that the project will be finished on time.



Source: BERNAMA



Share This Article

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

JPJ Running Numbers

KUALA LUMPUR

VPS6031

SELANGOR

BSH8371

JOHOR

JYG8397

PULAU PINANG

PRU1525

PERAK

APB2738

PAHANG

CFD4995

KEDAH

KGC3086

NEGERI SEMBILAN

NEH1445

KOTA KINABALU

SJM6409

KUCHING

QAB1806M

Last updated 20 Sep, 2025

Fuel Price

Petrol

RON 95

RM 2.05

RON 97

RM 3.21

+0.03

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.93

+0.03

EURO 5 B7

RM 3.13

+0.03

Last updated 18 Sep, 2025

Related News

Auto News
West Coast Expressway On Track For 2027 Completion

West Coast Expressway On Track For 2027 Completion

The West Coast Expressway is on track for full completion by 2027, with eight of its 11 sections already open.

27-08-2025
Auto News
Hauliers Demand Swift WCE Land Fix

Hauliers Demand Swift WCE Land Fix

Association of Malaysian Hauliers urges swift resolution of land disputes delaying completion of the WCE Section 3.

11-08-2025
Auto News
230km Southern WCE Feasibility Study To Conclude By Dec

230km Southern WCE Feasibility Study To Conclude By Dec

Study underway on 230km WCE from Banting to Gelang Patah to ease North-South Expressway jams.

08-08-2025
Auto News
WCE Sec 2 Toll Enabled; Responds to Klang Eviction Claims

WCE Sec 2 Toll Enabled; Responds to Klang Eviction Claims

WCE starts toll operations in Seksyen 2 and clarifies illegal evictions claims.

Auto News
Hari Raya 2025: Over 140K Vehicles Expected Daily on WCE

Hari Raya 2025: Over 140K Vehicles Expected Daily on WCE

Over 140,000 vehicles are expected to use the WCE daily during this upcoming Hari Raya Aidilfitri festive season.

24-03-2025
EV
WCE Section 2 Opens with 240 kW DC Handal Charging Station

WCE Section 2 Opens with 240 kW DC Handal Charging Station

WCE Section 2 opens today toll free till 22 Feb, features 240 kW DCFC station by DC Handal.

Auto News
ECRL Kelantan LIne 87.8% Complete, On Track for 2026 Completion

ECRL Kelantan LIne 87.8% Complete, On Track for 2026 Completion

ECRL project makes swift progress to reach 87.8% completion, and it appears on track for planned 2027 launch.

Auto News
WCE Sees 83% Increment In Traffic & 128% Increment In Toll Collection

WCE Sees 83% Increment In Traffic & 128% Increment In Toll Collection

WCE sees increased average daily traffic volume by 83% supported by a boost in toll income by 128%.

Latest News

Auto News
TQ Wuling Bingo EV CKD Production Set to Begin in Dec 2025

TQ Wuling Bingo EV CKD Production Set to Begin in Dec 2025

The new SGMW-Tan Chong joint venture EV plant will start its local assembly efforts this Dec with the TQ Wuling Bingo.

19-09-2025
Auto News
MyKad Checks Urged Ahead of Fuel Price Drop

MyKad Checks Urged Ahead of Fuel Price Drop

Home minister urges Malaysians to fix faulty MyKad chips early to enjoy the upcoming targeted fuel subsidy.

19-09-2025
Auto News
GAC Emkoo Awarded 5-star ASEAN NCAP Rating

GAC Emkoo Awarded 5-star ASEAN NCAP Rating

Upcoming GAC Emkoo C-SUV earns coveted 5-star rating form ASEAN NCAP crash-testing regime.

19-09-2025
Auto News
KLCC Roads Closed Saturday For Sarong Music Run

KLCC Roads Closed Saturday For Sarong Music Run

Expect road closures and traffic delays around KLCC tomorrow for the Malaysia Sarong Music Run 2025.

19-09-2025
Auto News
Sand, Log Trucks Dominate Kelantan Roads - JPJ

Sand, Log Trucks Dominate Kelantan Roads - JPJ

Sand and log trucks make up most heavy vehicle traffic in Kelantan, with fewer overloaded cases.

19-09-2025
Auto News
Customs Seizes 32 Imported Cars Worth RM8.45 Million

Customs Seizes 32 Imported Cars Worth RM8.45 Million

Ops Purple uncovered vehicles stored beyond the legal limit, with unpaid duties and taxes totalling RM5.38 million.

19-09-2025
Auto News
MAA: Aug 2025 Sales Up 4.2%, YoY Growth Modest at 0.6%

MAA: Aug 2025 Sales Up 4.2%, YoY Growth Modest at 0.6%

Latest MAA Aug 2025 sales figures see PVs contribute 67,302 units, with CVs taking the remaining 5,739.

Auto News
PLUS Kulai–Senai Smart Lane Closed Starting Sept 22

PLUS Kulai–Senai Smart Lane Closed Starting Sept 22

PLUS closes Kulai–Senai Smart Lane on Sept 22 for road widening. Separately, it also continues RM37m restroom refurbishments across its highway network.

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.