ECRL Will Continue - Loke Siew Fook

Anis

Share via




The federal government will continue the RM50 billion East Coast Rail Link (ECRL) project, according to Loke Siew Fook, the minister of transportation.

Loke reportedly told Bernama that despite the recent general election and the change in government, continuing transportation projects like the ECRL will proceed.

The anticipated cost of the 59 tunnels and 665km of rail is RM50.27 billion. It will pass through Kelantan, Terengganu, Pahang, and Selangor, four states.


Photo credit: NST

After reporting for work earlier on his first day as transport minister, Loke added that he will be concentrating on a number of issues relating to public transportation, including digitising its service.

From May 2018 to February 2020, Loke served as the Pakatan Harapan government's transport minister. Dr. Mahathir Mohamad led the coalition.

When it came to power in 2018, the PH government had temporarily put an end to the ECRL project, which had started in August 2017. Work began again in 2019.

Loke had vowed that if PH took power, the project wouldn't be shelved during the most recent election campaign.

In May, Amanah leader Faiz Fadzil expressed scepticism about the anticipated number of customers and asserted that the ECRL was unlikely to be financially successful in the long run and might require government bailout.

Gallery

Tagged:

ECRL
Ministry of Transport
transportation
GE15
Public Transportation
East Coast Rail Link (ECRL)
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Project Progress Surpasses 56% - Loke

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News
ECRL Project In Terengganu Reaches 55% Progress

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023
Auto News
ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

Selangor Forestry Department found that the alleged land clearing activities in the Selangor State Park are part of the ECRL project.

06-02-2023

Latest News

Auto News
KPDN Probes SG Driver Sighted Pumping RON95 in Johor

KPDN Probes SG Driver Sighted Pumping RON95 in Johor

KPDN is probing a viral incident where a Singapore-registered car was seen pumping subsidised RON95 fuel.

Auto News
Traffic Diversion On Bukit Gambir-Tangkak From Aug 5

Traffic Diversion On Bukit Gambir-Tangkak From Aug 5

Traffic along the NSE near Tangkak will be diverted in both directions from Aug 5 for bridge construction.

04-08-2025
Auto News
1,489 Summonses Issued in VEP Enforcement Operation – JPJ

1,489 Summonses Issued in VEP Enforcement Operation – JPJ

JPJ has issued a total of 1,489 summonses during an enforcement operation on VEP at the JB-Singapore land border.

04-08-2025
Auto News
No Green Light Yet For Cross-Border Ride-Hailing Between SG, JB.

No Green Light Yet For Cross-Border Ride-Hailing Between SG, JB.

Singapore holds off on cross-border ride-hailing plans, opting instead to improve its existing taxi scheme with Malaysia.

04-08-2025
Auto News
RM110 Million Collected from Special Plate Sales Since 2023 – MoT

RM110 Million Collected from Special Plate Sales Since 2023 – MoT

A total of RM110 million has been collected from sales of special number plates since 2023, the Transport Ministry says.

04-08-2025
Auto News
Nanta: 80% of Accidents Driver-Linked, Road Budget 70% Short

Nanta: 80% of Accidents Driver-Linked, Road Budget 70% Short

With 80% of accidents linked to drivers, the Works Ministry still grapples with limited funds to fix and rebuild roads.

Auto News
LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report

LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report

The LRT3 Shah Alam line opening could be delayed until Oct 31 instead of the planned launch date of Sept 30.

04-08-2025
Auto News
ETS to JB Sentral ‘On Track’, But Not Quite There Yet

ETS to JB Sentral ‘On Track’, But Not Quite There Yet

KTMB says electrification works between Kluang to JB Sentral are ongoing and the extension will proceed once conditions are met.