Link Copiedcheck_circle
Auto News

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

Anis

Share via




The East Coast Rail Link (ECRL) project's Kuantan Tunnel, which broke ground in October last year, will be completed by the end of April. The 2.8km tunnel located in Jabor, near here, is the longest among the ECRL tunnels in Section B (Dungun-Mentakab), which also includes the 1.1km Paka Tunnel and 871m Dungun Tunnel, both in Terengganu. Wan Kamal Wan Embong, regional construction manager (Section 4 and 5) for Malaysian Rail Link (MRL), stated that the Kuantan Tunnel breakthrough occurred on October 17, last year, two months ahead of schedule.


"The tunnel's completion date is set for April 27. The Kuantan Tunnel runs through both Pahang and Terengganu, with 976 metres in Pahang and the remaining 1,890 metres in Terengganu "he told reporters yesterday during a media visit to the Kuantan Tunnel here. The New Austrian Tunnelling Method (NATM), the world's most widely used underground construction method, is being used in the drilling and blasting work for the Kuantan tunnel project, which began on October 7, 2019. The average height and width of the Kuantan Tunnel are 11.89m and 13.26m, respectively.



The project made use of a Swedish-made double-arm jumbo drilling machine, with tunnelling work beginning in both directions and meeting in the middle. Wan Kamal stated that MRL ensured that all workers strictly adhered to the safety aspects and conditions set by the Department of Occupational Safety and Health (DOSH). "Because tunnel construction required working in a confined space, we had to ensure proper ventilation and control gas emissions inside the tunnel that could endanger the workers. At the peak of the project, 177 workers were on the job "he said, adding that safety was given top priority during the blasting operations.


Closed-circuit television cameras were previously reported to have been installed at the construction site, including inside the tunnel, to monitor worker movement and ensure safety. In terms of the overall progress of the ECRL, Wan Kamal stated that the 665km rail project was 40% completed and was on track to be completed in December 2026. The 210km Dungun-Mentakab main line is also known as Section B, while the other sections are Kota Baru to Dungun (Section A) and Mentakab to Port Klang (Section B) (Section C).


The ECRL, which opened in 2017, will connect the east coast states of Kelantan, Terengganu, and Pahang with the Klang Valley.

Gallery

Tagged:

ECRL
East Coast Rail Link (ECRL)
ECRL project
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News

ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

Selangor Forestry Department found that the alleged land clearing activities in the Selangor State Park are part of the ECRL project.

06-02-2023

Latest News

Auto News

New RM22.7M JPJ Kajang Office Set for 2027

The new RM22.7M JPJ Kajang office will feature modern facilities and improved services for the public by 2027.

23-09-2025
Auto News

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News

Amir Hamzah: No Back-to-Back Pumping of RM1.99 RON95 A Day

Amir Hamzah: Govt. won't allow multiple subsidised refuels in a day as BUDI95 takes effect Sept 30.

Auto News

Petron Lubricants Gains SIRIM Certification & Label

Petron Malaysia acquires SIRIM genuine product licence certification and label for engine lubricant product line-up.

23-09-2025
Auto News

Govt Will Allow Commercial RV Rentals from 2026 - Loke

Starting January 2026, RVs can be licensed for commercial use, making self-drive RV holidays safer and regulated.

23-09-2025
Auto News

BUDI95: RON95 Ban on Foreign Cars Still On, RM1.99 for Malaysians

BUDI95 keeps foreign-registered cars out of subsidised RON95, only Malaysians with local vehicles can pump at RM1.99 per litre.

Auto News

Rapid Rail Set To Launch Real-Time Crowd Tracking & AI Security

Rapid Rail will introduce a live tracker showing coach crowd levels so commuters can board with less stress.

23-09-2025
Auto News

Rafizi: Budi95 Quota Won’t Deliver Savings or Fairness; T20 Gains the Most

Rafizi Ramli says Budi95 quota will keep subsidies at RM10–15 billion a year, but wealthier households enjoy biggest share.