ECRL Project In Terengganu Reaches 55% Progress

Jesica Sendai

Share via




Malaysia Railway Link Sdn Bhd said in a statement the construction of East Coast Rail Link (ECRL) Project in Terengganu has reached a progress level of 55.21 percent.  


The route in Terengganu holds the longest line compared to the other three states namely Kelantan, Pahang and Selangor which is 275 KM long from a total of 665 KM and estimated to  cost a sum of RM 50.27 billion. 


So far, the construction work on the said project in Terengganu is set to be on track and scheduled to be fully completed by December 2026.





From there it includes the construction of six stations namely Jerteh, Bandar Permaisuri, Kuala Terengganu and Kemasik which function as passenger stations while Dungun and Chukai are for the purpose of passengers and cargo.


Separately, construction work for the entire 665 KM ECRL line project from Kota Bharu, Kelantan to Port Klang, Selangor has an overall progress level of 40.81 percent, according to Malaysia Rail Link (MRL) CEO Datuk Seri Darwis Abdul Razak. 


"Out of that amount, there are 21 km of tunnels in Selangor and there are approximately 31 km of bridges that will be built in the Selangor line," he added. 





Meanwhile, the East Coast Rail Link (ECRL) project involving the Selangor line is considered to be the most critical compared to the other three states, as reported by local news online.


He further stated that the construction of the C1B alignment in the northern part of the state is seen as complex because it involves various types of construction in addition to bridges and tunnels.


"I say it is critical because we started this ECRL project in 2017, stopped for a while in July 2018 and resumed in April 2019.


‘’We got approval from the state government for us to implement the ECRL project through the northern line starting December 2021 and we can only start construction work with good cooperation from all state and federal departments and agencies which give us approval in June 2022,’’ the exec said. 


The service is expected to be operational in January 2027 and can accommodate 5.6 million passengers a year aside from also can carry 440 passengers for a trip involving six carriages.



Tagged:

ECRL
East Coast Rail Link (ECRL)
ECRL project
Projek Laluan Rel Pantai Timur (ECRL)
Share This Article

Written By

Jesica Sendai

from 9 to 5 grinder to 'racing' her way in the automotive industry through editorial work.

Share via

Related News

Auto News

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023

Latest News

Auto News

MITI Breaks Silence: The Truth Behind the '80% Export' Ultimatum

MITI breaks its silence on the viral BYD "80% export" rumors. From the RM100k EV price floor to the truth behind the BYD Shark "ban," here is the official clarification on Malaysia's automotive future.

31-03-2026
Auto News

DUI Offenders Face Direct Compensation to Families Under New Law

Transport Minister Anthony Loke confirms new amendments to Act 333 for DUI offenders.

31-03-2026
Auto News

7 Years of Peace of Mind: Why the Saga MC3’s New Warranty is a "Must-Have" Add-On

Proton's new RM1,200 extended warranty for the Saga MC3 offers 7 years of cover. We decode the costs, the 1.5L i-GT engine risks, and the resale value hacks.

30-03-2026
Auto News

Reality Check: Decoding the Massive Gaps in Maslan’s Cycling & Biodiesel Proposals

We decode the RM643m funding gap in Ahmad Maslan's B20 biodiesel plan and the reality of cycling in Malaysia. Is the 7-point fuel fix a dream or a disaster?

30-03-2026
Auto News

Final 24 Hours: 3 Things You Must Do Before the BUDI95 Quota Drops to 200L Tomorrow

Midnight Deadline: The BUDI95 quota drops to 200L in less than 24 hours. See the 3 vital steps every driver must take today to avoid a massive price shock at the pump tomorrow.

30-03-2026
Auto News

Proton Wants to Forgive Your “Service Sins” from RM120

Lapsed your Proton service for 12 months? Get a fresh start with PROTON’s 2026 campaign. Packages from RM120 for Persona/Saga and RM216 for X-series SUVs.

30-03-2026
Auto News

Farewell to Budget High-Tech EV? MITI’s Terms Could Force BYD Out of Tanjung Malim

Why is the BYD Tanjung Malim plant stuck? We decode MITI’s 80% export rule and the RM200k price floor that’s keeping affordable EVs out of Malaysia.

30-03-2026
Auto News

Motorcyclist Dies After Being Hit by Speeding Car in Klang

Tragic fatal crash in Klang: A motorcyclist was killed on the spot after a car allegedly speeding and overtaking on a double yellow line struck him on Jalan Bunga Raya Barat behind MBDK on 29 March 2026.

29-03-2026