Over 70 Percent Of ECRL Project Completed - Loke

Anis

Share via

ECRL-56-Completion-Minister-Loke-full.jpg According to Transport Minister Anthony Loke, the East Coast Rail Link (ECRL) project, which spans four states (Pahang, Kelantan, Terengganu, and Selangor), is currently 70.13 percent complete. The government is optimistic that ECRL operations from Gombak to the East Coast, specifically Pahang, Terengganu, and Kelantan, will be able to start in early 2027 because the construction is proceeding without hiccups and in accordance with the planned timeline. FW1295812_KB02_25032023_ECRL-scaled-e1680489263316.jpg
Photo: Bernama.

The minister stated that construction in Kelantan, Terengganu, and Pahang is well underway. In Selangor, it is in its early stages, with more than 30%. However, according to the schedule, ECRL operations will begin in January 2027, and the route from Kota Bharu to LRT Gombak will be completed by the end of 2026. 03-page-3-chung_2257706_20220325074846-(1)-full.jpg

“A year later, the track from Gombak to Port Klang will be completed. Indeed, the track connecting the port in Port Klang to the East Coast is quite important because it will reach our main port for cargo transportation,” he added.
He continued by saying that cargo transportation, along with the tracks and infrastructure, is a crucial part of the ECRL because it will benefit the East Coast's industrial sector greatly, particularly Pahang.

Tagged:

ECRL project
East Coast Rail Link (ECRL)
ECRL contruction progress
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News
ECRL Project Hits 87% Completion by August 2025 – MoT

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News
ECRL Extension from Kota Bharu to Pasir Mas Under Review

ECRL Extension from Kota Bharu to Pasir Mas Under Review

Kelantan is pushing for the ECRL to extend to Rantau Panjang, eyeing cross-border rail links with Thailand.

23-07-2025
Auto News
Kuantan-Bound KL-Karak Lanes Diverted For ECRL Work Until Aug 31

Kuantan-Bound KL-Karak Lanes Diverted For ECRL Work Until Aug 31

Kuantan-bound lanes (KM25.75–KM26.39) are being diverted for ECRL works until Aug 31.

10-07-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Finishes Excavation Of 30 Tunnels Ahead Of Schedule

ECRL Finishes Excavation Of 30 Tunnels Ahead Of Schedule

The ECRL project made three tunnel breakthroughs in a single day in the Bentong district and finished excavating 30 tunnels along its rail alignment.

14-03-2024
Auto News
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News
ECRL Project In Terengganu Reaches 55% Progress

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News
Jalan Kuala Terengganu-Kuantan Closed For ECRL Works

Jalan Kuala Terengganu-Kuantan Closed For ECRL Works

The Dungun district police has announced a road closure on Jalan Kuala Terengganu-Kuantan for ECRL project.

03-04-2023

Latest News

Auto News
Strait of Hormuz to Malaysia: Why We’re Paying for a War 6,000km Away

Strait of Hormuz to Malaysia: Why We’re Paying for a War 6,000km Away

Why is RON97 at RM4.55/L? We decode the Strait of Hormuz conflict, the May 2026 subsidy deadline, and why Malaysia imports oil despite being a producer.

19-03-2026
Auto News
From 82 Minutes to 8: How the Mutiara Line is Giving Penangites Their Time Back

From 82 Minutes to 8: How the Mutiara Line is Giving Penangites Their Time Back

Is the 80-minute Penang Bridge crawl finally ending? The Mutiara Line LRT links Butterworth to Komtar in just 8 minutes. Get the latest 2026 project updates, station lists, and more.

17-03-2026
Auto News
The 2026 Proton X90 Buyer’s Warning: 5 Critical Safety Features You Are No Longer Getting

The 2026 Proton X90 Buyer’s Warning: 5 Critical Safety Features You Are No Longer Getting

ASEAN NCAP revokes Proton X90’s 5-star rating. The 2026 facelift is downgraded to 1-star after stripping critical ADAS features. Is your family safe? Get the full safety specs here.

16-03-2026
Auto News
9,000+ Drivers Chose Toyota Hybrids This Year: Proof That Toyota’s Multi-Pathway Strategy Works

9,000+ Drivers Chose Toyota Hybrids This Year: Proof That Toyota’s Multi-Pathway Strategy Works

Toyota Malaysia hits 9,556 sales in early 2026, proving the "Multi-Pathway" strategy works. From Vios Hybrid to Vellfire HEV, see why hybrids are winning the sales war.

12-03-2026
Auto News
Chery Tiggo 7 is Now the Safest Chinese SUV on the Planet, This Is Why

Chery Tiggo 7 is Now the Safest Chinese SUV on the Planet, This Is Why

The Chery Tiggo 7 makes history as the only Chinese SUV to sweep 5-star ratings from Euro NCAP, ANCAP, and ASEAN NCAP. With a record 94.68 points, see why this is 2026’s safest family SUV.

11-03-2026
Auto News
Sepang Dates Confirmed: Catch Team Porsche Malaysia in Action on 21–23 August

Sepang Dates Confirmed: Catch Team Porsche Malaysia in Action on 21–23 August

While the 2026 Porsche Carrera Cup Asia (PCCA) season kicks off in Shanghai this weekend, Malaysian fans are already looking ahead to the highlight of the year: the homecoming.

10-03-2026
Auto News
Iran-US War Day 10: It’s Not Just Fuel — Malaysia’s Automotive Industry Faces New Risks

Iran-US War Day 10: It’s Not Just Fuel — Malaysia’s Automotive Industry Faces New Risks

While the BUDI95 subsidy program is already feeling the heat of oil prices flirting with US$120 a barrel, the true threat to our automotive sector lies beneath the surface.

09-03-2026
Auto News
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far

Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far

The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.

05-03-2026