Over 70 Percent Of ECRL Project Completed - Loke
According to Transport Minister Anthony Loke, the East Coast Rail Link (ECRL) project, which spans four states (Pahang, Kelantan, Terengganu, and Selangor), is currently 70.13 percent complete.
The government is optimistic that ECRL operations from Gombak to the East Coast, specifically Pahang, Terengganu, and Kelantan, will be able to start in early 2027 because the construction is proceeding without hiccups and in accordance with the planned timeline.

Photo: Bernama.
The minister stated that construction in Kelantan, Terengganu, and Pahang is well underway. In Selangor, it is in its early stages, with more than 30%. However, according to the schedule, ECRL operations will begin in January 2027, and the route from Kota Bharu to LRT Gombak will be completed by the end of 2026.
-full-full_normal.jpg)
“A year later, the track from Gombak to Port Klang will be completed. Indeed, the track connecting the port in Port Klang to the East Coast is quite important because it will reach our main port for cargo transportation,” he added.
He continued by saying that cargo transportation, along with the tracks and infrastructure, is a crucial part of the ECRL because it will benefit the East Coast's industrial sector greatly, particularly Pahang.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQG4940
SELANGOR
BSL4193
JOHOR
JYP1796
PULAU PINANG
PRX2991
PERAK
APD8059
PAHANG
CFE6424
KEDAH
KGD6679
NEGERI SEMBILAN
NEJ1822
KOTA KINABALU
SJP5865
KUCHING
QAB9481M
Last updated 01 Jan, 2026
Fuel Price
Petrol
RON 95
RM 2.56
RON 97
RM 3.16
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.94
EURO 5 B7
RM 3.14
Last updated 01 Jan, 2026
Related News
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Extension from Kota Bharu to Pasir Mas Under Review
Kelantan is pushing for the ECRL to extend to Rantau Panjang, eyeing cross-border rail links with Thailand.
23-07-2025
Kuantan-Bound KL-Karak Lanes Diverted For ECRL Work Until Aug 31
Kuantan-bound lanes (KM25.75–KM26.39) are being diverted for ECRL works until Aug 31.
10-07-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Finishes Excavation Of 30 Tunnels Ahead Of Schedule
The ECRL project made three tunnel breakthroughs in a single day in the Bentong district and finished excavating 30 tunnels along its rail alignment.
14-03-2024
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
Jalan Kuala Terengganu-Kuantan Closed For ECRL Works
The Dungun district police has announced a road closure on Jalan Kuala Terengganu-Kuantan for ECRL project.
03-04-2023
Latest News
Updated Fuel Prices From 1 To 7 January
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 1 to 7 January, 2026, the rates are as such.
31-12-2025
Selangor Police Collect RM19.5 Million During Summons Discount Period
More than 258,000 traffic summonses were settled in Selangor during the two-month 70% discount programme, collecting RM19.5 million.
31-12-2025
Traffic Summons Discount Ends, Tougher Penalties Ahead – Should Authorities Extend?
The traffic summons discount is over, millions of fines remain unpaid, and stricter penalties kick in next year
31-12-2025
LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing
All 33 technical problems identified on the Shah Alam Line have proposed fixes, but full testing is still underway.
31-12-2025
KLIA T1 Moves Customs Checks — Here’s What You Need To Know
Customs checks at KLIA T1 will move to the departure gates from Jan 1, promising smoother departures.
31-12-2025
China Set to Overtake Japan as World’s Top Auto Seller in 2025
China set to become world’s top auto seller in 2025, overtaking Japan as domestic and overseas sales growth surges.
30-12-2025
KTMB Southern Express Ends Service As ETS Takes Over
KTMB will end the Southern Express on the Gemas–JB Sentral route from Jan 1 to make way for eight daily ETS trips.
30-12-2025
Can Instalment-Based Payment Scheme Help Solve Unpaid Summonses?
Road safety expert suggests instalment-based payment scheme could help resolve unpaid summonses. Do you agree?
30-12-2025
Show More
trending_flat