Over 70 Percent Of ECRL Project Completed - Loke
According to Transport Minister Anthony Loke, the East Coast Rail Link (ECRL) project, which spans four states (Pahang, Kelantan, Terengganu, and Selangor), is currently 70.13 percent complete.
The government is optimistic that ECRL operations from Gombak to the East Coast, specifically Pahang, Terengganu, and Kelantan, will be able to start in early 2027 because the construction is proceeding without hiccups and in accordance with the planned timeline.
Photo: Bernama.
The minister stated that construction in Kelantan, Terengganu, and Pahang is well underway. In Selangor, it is in its early stages, with more than 30%. However, according to the schedule, ECRL operations will begin in January 2027, and the route from Kota Bharu to LRT Gombak will be completed by the end of 2026.
“A year later, the track from Gombak to Port Klang will be completed. Indeed, the track connecting the port in Port Klang to the East Coast is quite important because it will reach our main port for cargo transportation,” he added.
He continued by saying that cargo transportation, along with the tracks and infrastructure, is a crucial part of the ECRL because it will benefit the East Coast's industrial sector greatly, particularly Pahang.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPM5672
SELANGOR
BSG7762
JOHOR
JYE5047
PULAU PINANG
PRT1087
PERAK
ANY7255
PAHANG
CFD724
KEDAH
KGB6459
NEGERI SEMBILAN
NEG6404
KOTA KINABALU
SJL9999*
KUCHING
QAB8491L
Last updated 05 Aug, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.17
-0.04
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.91
EURO 5 B7
RM 3.11
Last updated 31 Jul, 2025
Related News
ECRL Extension from Kota Bharu to Pasir Mas Under Review
Kelantan is pushing for the ECRL to extend to Rantau Panjang, eyeing cross-border rail links with Thailand.
23-07-2025
Kuantan-Bound KL-Karak Lanes Diverted For ECRL Work Until Aug 31
Kuantan-bound lanes (KM25.75–KM26.39) are being diverted for ECRL works until Aug 31.
10-07-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Finishes Excavation Of 30 Tunnels Ahead Of Schedule
The ECRL project made three tunnel breakthroughs in a single day in the Bentong district and finished excavating 30 tunnels along its rail alignment.
14-03-2024
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
Jalan Kuala Terengganu-Kuantan Closed For ECRL Works
The Dungun district police has announced a road closure on Jalan Kuala Terengganu-Kuantan for ECRL project.
03-04-2023
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%
ECRL project's Kuantan Tunnel will be completed by the end of April.
08-03-2023
Latest News
Ferraris, Lambos Among 1,000 Untaxed Vehicles - JPJ
JPJ flags over 1,000 luxury cars, including Ferraris and Lambos, for missing road tax and insurance.
05-08-2025
MoF: Fuel Subsidy Rollout Under Testing, Launches End-Sept
MoF is finalising the targeted fuel subsidy system, with full rollout details expected by end-Sept.
05-08-2025
KLIA Apologises After Aerotrain Breaks Down Again
KLIA’s Aerotrain stalled for 15 minutes due to a door glitch, prompting an apology and public frustration.
05-08-2025
Amir Hamzah: PADU at the Core of RON95 Subsidy Implementation
With over 30 million individual profiles, PADU will guide MOF’s effort to roll out a more precise RON95 petrol subsidy.
05-08-2025
KPDN Probes SG Driver Sighted Pumping RON95 in Johor
KPDN is probing a viral incident where a Singapore-registered car was seen pumping subsidised RON95 fuel.
04-08-2025
Traffic Diversion On Bukit Gambir-Tangkak From Aug 5
Traffic along the NSE near Tangkak will be diverted in both directions from Aug 5 for bridge construction.
04-08-2025
1,489 Summonses Issued in VEP Enforcement Operation – JPJ
JPJ has issued a total of 1,489 summonses during an enforcement operation on VEP at the JB-Singapore land border.
04-08-2025
No Green Light Yet For Cross-Border Ride-Hailing Between SG, JB.
Singapore holds off on cross-border ride-hailing plans, opting instead to improve its existing taxi scheme with Malaysia.
04-08-2025
Show More
trending_flat