ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals

KS

3 hours ago

Share via

495363432_1267422741405957_4719761365907232200_n.jpg


The East Coast Rail Link (ECRL) project is now 82.45% complete as of April 2025. The 665km railway is on track, with the Kota Bharu–Gombak stretch due by Dec 2026 and the Gombak–Port Klang section by Dec 2027.

Track installation from Maran to Kota Bharu, spanning 400 KM, finished ahead of schedule with work on the Maran–Bentong stretch beginning this month and is set to complete by June.

Electrification works started in May 2024, with over 9,000 OCS poles installed and around 2,700 left. Tunnel boring has reached 38 of 41 tunnels, with the 16.39km Genting Twin Tunnel expected to break through in Q3 this year.


GoqT8wbbMAAWTGk.jpeg


Station construction is progressing well and is set for completion by mid-2026. Testing and commissioning of the system will begin in June 2026.

Transport Minister YB Anthony Loke Siew Fook shared these updates during the launch of the ECRL’s Operations & Maintenance (O&M) workforce training under the PLKI-ECRL programme.

Once operational in January 2027, the ECRL will require around 1,800 workers, with 80% being Malaysians. The aim is to build a skilled local workforce for modern rail operations.

The PLKI-ECRL programme is now focused on training for the O&M phase. A total of 3,200 trainees will benefit, starting with 210 Malaysians this year.


GoqT9UCacAI3zXE.jpeg


Of that, 102 trainees will begin one-year training in Liuzhou, China, from 15 May. They’ll learn technical and operational skills for various ECRL roles.

Trainees are guaranteed jobs upon completion and the programme is supported by a RM12 million sponsorship from China Communications Construction Company Ltd (CCCC).


495463645_1267422871405944_6737999489992028850_n.jpg


ECRL will use 11 EMU train sets and 12 electric locomotives from CRRC Dalian. The first units are expected by year-end. These new trains will run up to 160 km/h, cutting travel time from Kota Bharu to Gombak to just four hours.

Loke also added that ECRL will help shift cargo from road to rail - an eco-friendly, cost-effective move in line with national transport goals.

He added that efforts are underway to ensure passenger fares remain affordable when operations begin.



Tagged:

East Coast Rail Link (ECRL)
China Communications Construction Company Ltd (CCCC)
Electric Multiple Unit (EMU)
ECRL Operations & Maintenance (O&M)
Minister of Transport YB Anthony Loke
Share This Article

Written By

KS

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well! https://www.linkedin.com/in/kumeran-sagathevan/

Share via

Related News

Auto News
ECRL to Boost East Coast Growth, Strengthen Malaysia-China Ties

ECRL to Boost East Coast Growth, Strengthen Malaysia-China Ties

The ECRL project is set to unlock new growth for Malaysia’s east coast and strengthen links with China.

29-04-2025
Auto News
ECRL Railway Construction Along Kota Bharu-Selangor Over 80% Complete

ECRL Railway Construction Along Kota Bharu-Selangor Over 80% Complete

ECRL project along Kota Bharu-Selangor alignment is over 81% complete and remains on track for completion in Dec 2026.

18-04-2025
Auto News
ECRL Concludes 38 Tunnel Excavations Ahead Of Schedule

ECRL Concludes 38 Tunnel Excavations Ahead Of Schedule

MRL announces the completion of excavation work for 38 tunnels along the ECRL rail line.

09-04-2025
Auto News
ECRL 80% Complete, Shifting To Above-Ground Work

ECRL 80% Complete, Shifting To Above-Ground Work

The ECRL project, which is nearing 80% completion, is transitioning from the underground construction phase to above-ground work.

27-03-2025
Auto News
MOT Developing Policy To Encourage Cargo Companies To Use ECRL

MOT Developing Policy To Encourage Cargo Companies To Use ECRL

MOT will implement a policy to incentivize the industry to use the ECRL service.

06-03-2025
Auto News
ECRL: Port Klang Stretch Will Be Upgraded to Double-Track System

ECRL: Port Klang Stretch Will Be Upgraded to Double-Track System

The 25-KM stretch of the ECRL at Port Klang will be upgraded to a double-track system with no extra cost, MOT says.

18-02-2025
Auto News
ECRL: Phase 1 Testing & Certification Will Begin in June 2026

ECRL: Phase 1 Testing & Certification Will Begin in June 2026

The testing and certification phase for the ECRL Phase 1 from Kota Bharu to Gombak will begin in June 2026.

05-02-2025
Auto News
ECRL Kelantan LIne 87.8% Complete, On Track for 2026 Completion

ECRL Kelantan LIne 87.8% Complete, On Track for 2026 Completion

ECRL project makes swift progress to reach 87.8% completion, and it appears on track for planned 2027 launch.

16-01-2025

Latest News

Auto News
Proton Posts Strong April Sales, e.MAS 7 Leads EV Market

Proton Posts Strong April Sales, e.MAS 7 Leads EV Market

Proton recorded a 14.7% YOY sales growth in April 2025, buoyed by strong demand for e.MAS 7 EV.

06-05-2025
Auto News
Malaysia Autoshow 2025 Charges Up Ahead Of May 9 Opening Day

Malaysia Autoshow 2025 Charges Up Ahead Of May 9 Opening Day

Malaysia Autoshow 2025 (MAS 202) gears up as May 9 opening day looms closer, tickets are still available online from RM20 onwards.

06-05-2025
Auto News
ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals

ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals

ECRL, Malaysia’s largest rail project is nearing completion, with passenger service set to begin by Jan 2027.

06-05-2025
Auto News
Man Warns About Car Battery Thefts Near Glenmarie LRT Station

Man Warns About Car Battery Thefts Near Glenmarie LRT Station

A TikTok video by @bateriku.com_ttdi warns the public about increased car battery thefts near the Glenmarie LRT station.

06-05-2025
Auto News
New Professional Affiliates Programme By Jaecoo Malaysia Targets Professionals And Corporations

New Professional Affiliates Programme By Jaecoo Malaysia Targets Professionals And Corporations

Jaecoo Malaysia launches new Professional Affiliates Programme, targets both corporations and professionals through which.

06-05-2025
Auto News
Govt Urged To Delay Targeted RON95 Subsidy Due To US Tariffs

Govt Urged To Delay Targeted RON95 Subsidy Due To US Tariffs

Lawmakers are urging the government to postpone its proposed RON95 subsidy rationalization due to US tariffs.

06-05-2025
Auto News
Toyota GR86 Cup Car On Sale In Malaysia – 30 Units Only, RM208,315 Each

Toyota GR86 Cup Car On Sale In Malaysia – 30 Units Only, RM208,315 Each

Toyota GR86 Cup Car now in sale locally through Haro Sports and Entertainment Sdn Bhd, just 30 units available at RM208,315 each.

06-05-2025
Auto News
Ekovest Gets Green Light for LIKE and KBL Expressway Projects

Ekovest Gets Green Light for LIKE and KBL Expressway Projects

Ekovest has received government approval to proceed with the LIKE and KBL expressway projects under its highway expansion plan.

06-05-2025