"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
According to Transport Minister Anthony Loke, the East Coast Rail Link (ECRL) is currently 42.06% complete. Loke stated today, while visiting the Genting ECRL Tunnel construction site, that the rail line's construction progress is on track to be completed by December 2026. However, Loke also stated that the ECRL project is currently facing a difficult challenge with the completion of the Genting ECRL tunnel, a twin tunnel spanning 16.39km in length that connects Bukit Tinggi, Pahang with Gombak, Selangor.
According to Loke, the tunnel will be built using a tunnel boring machine (TBM) rather than the drilling and explosives used in other ECRL tunnels. “I am confident with the management and workforce for the ECRL project to complete the project using two TBMs which were made in China. "When the construction crosses the Titiwangsa Range, these highly technological machines will be able to face engineering challenges and geological conditions," Loke said.
Construction on the first Genting tunnel has already begun, and approval to use the TBM for the second tunnel was obtained in November. “Boring works for the first Genting ECRL Tunnel have already reached a depth of 2.602km while the second reached 2.497km.
"For your information, the Genting ECRL Tunnel construction site spans 11.6ha in width and employs over 300 people."
"We hope that by January 2027, the ECRL will be fully operational, saving three hours of travel time from Kota Baru to Gombak," Loke added.
Gallery
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPG3557
SELANGOR
BSF4862
JOHOR
JYA4580
PULAU PINANG
PRR4765
PERAK
ANW6448
PAHANG
CFC1284
KEDAH
KGA9320
NEGERI SEMBILAN
NEG2305
KOTA KINABALU
SJL2927
KUCHING
QAB5093L
Last updated 17 Jun, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.07
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.74
EURO 5 B7
RM 2.94
Last updated 12 Jun, 2025
Related News
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%
ECRL project's Kuantan Tunnel will be completed by the end of April.
08-03-2023
ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide
Selangor Forestry Department found that the alleged land clearing activities in the Selangor State Park are part of the ECRL project.
06-02-2023
Kelantan And Terengganu ECRL Project Affected By Floods
The floods last week impacted around 70% of the construction work at sections 1 and 2 of the East Coast Rail Line (ECRL), which spans 82 kilometres from Tunjong here to Setiu in Terengganu.
28-12-2022
ECRL Will Continue - Loke Siew Fook
The federal government will continue the RM50 billion East Coast Rail Link (ECRL) project, according to Loke Siew Fook, the minister of transportation.
07-12-2022
Latest News
PRO-NET Opens Three New Proton e.MAS & smart Dealerships
PRO-NET has expanded both its Proton e.MAS and smart dealer network by opening three new outlets in Malaysia.
17-06-2025
FT Dept, JPJ Told To Deal With Abandoned Vehicles
FT Dept and JPJ ordered to review and improve laws on abandoned vehicle disposal in KL and Putrajaya.
17-06-2025
Gerik Crash: PSV Licence Suspended, RM1.7M Aid Raised
JPJ suspends Gerik crash bus driver’s PSV licence as investigations rule out technical failure.
17-06-2025
PLUS Opens Three New Lanes At Rawang Selatan Toll Plaza
PLUS has announced the addition of three new lanes at the Rawang Selatan toll plaza (Exit 115).
16-06-2025
RON95 Petrol Subsidy Rationalisation Will Proceed – PMX
The government will proceed with the RON95 fuel subsidy rationalisation, says Prime Minister Anwar Ibrahim.
16-06-2025
Car Wash Worker Severely Injured After Vehicle Plunges From 3rd Floor
A car wash worker driving a customer’s Toyota Camry crashed through the wall of a building in Old Klang Road on Sunday.
16-06-2025
Roslan Abdullah Joins GWM Malaysia As New COO
Former deputy CEO of Proton Roslan Abdullah appointed as new COO at GWM Malaysia.
16-06-2025
Mustang, BMW Owners Caught With Expired Road Tax, Citing Financial Issues
Financial issues cited by Mustang and BMW X5 owners caught with expired road tax during JPJ operation.
16-06-2025
Show More
trending_flat