LOKE : LRT3 86% Complete, To Begin Service 1 March 2025 - 67,000 Daily Capacity
KS
5-7-2023
Yesterday, Transport Minister YB Anthony Loke delivered an update on the Light Rail Transit 3 (LRT3) project's development. Loke reported that construction is progressing quickly, with completion at 86%, including the installation of the signalling system.
Currently, 22 sets of three-coach trains are being tested thoroughly. LRT3 operations are expected to begin on March 1, 2025, which is approximately 18 to 19 months from now. Loke expressed confidence in the project's successful implementation, emphasising the significance of collaboration among all stakeholders to fulfil the target deadline.
The LRT3 is intended to assist nearly two million Klang Valley people, notably those living between Petaling Jaya and Klang. As a densely populated and developed region, tens of thousands of passengers are expected to utilise the LRT3.
With a capacity to accommodate 18,630 passengers per hour per direction, the project will include two interchange stations. Bandar Utama will connect the MRT Kajang Line to LRT3, while Glenmarie will connect the Kelana Jaya Line to LRT3. A flyover will connect these two stations, improving the system's overall connection.
Loke emphasised that the 22 train sets are all brand new, luxurious, and outfitted with environmentally friendly "green technology." They are currently in the last stages of testing to ensure their readiness for the approaching opening.
During a site visit to the depot and LRT3 operation control center, Loke personally conducted a test drive on the trial route using one of the trains. He emphasised that the LRT3 is an important addition to public transportation in the Klang Valley, with the goal of encouraging more people to use public transportation in the area.
Once completed, the LRT3 line would be approximately 37 kilometres long, with 2 km running underground. Over 2000 parking spots would be offered in 6 stations to assist travellers who choose to Park & Ride. The route would also service 67,000 people every day, with a 6-minute average wait time.
Source: MalayMail
Gallery
Written By
KS
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well! https://www.linkedin.com/in/kumeran-sagathevan/
JPJ Running Numbers
KUALA LUMPUR
VPE5103
SELANGOR
BSF1029
JOHOR
JXY3826
PULAU PINANG
PRQ9759
PERAK
ANW1678
PAHANG
CFB8524
KEDAH
KGA7044
NEGERI SEMBILAN
NEG439
KOTA KINABALU
SJK9999*
KUCHING
QAB4306L
Last updated 28 May, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.10
+0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.80
+0.03
EURO 5 B7
RM 3.00
+0.03
Last updated 22 May, 2025
Related News
ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals
ECRL, Malaysia’s largest rail project is nearing completion, with passenger service set to begin by Jan 2027.
06-05-2025
Direct KL-Bangkok Train Service To Return By Year-End
Malaysia and Thailand plan to bring back the direct train line from Kuala Lumpur to Bangkok by the end of 2025.
05-05-2025
BYD Charges Up MOT Staff EV Adoption Effort
“Jom Pandu BYD Bersama MOT” effort sees ministry team up with BYD to drive EV transition from the inside out.
22-04-2025
JPJ Will Not Be Cowed By Threats From Tontos - Loke
Transport Minister Anthony Loke warned "tontos" that the JPJ will not be intimidated by their threats against enforcement officers.
22-04-2025
JPJ Merges Motorcycle and Car Theory Modules
JPJ will introduce integrated theory module, one KPP01 theory class will cover both motorcycle and car licences.
21-04-2025
Train Services In North Severely Hit By Cable Theft
KTMB is experiencing major disruptions and safety issues in the northern sector due to the rise in signal cable theft.
26-03-2025
12 New Trains For KTM Komuter Utara, First Delivery In 22 Months
KTM Komuter Utara will receive 12 new trains, with the first delivery in 22 months
25-03-2025
JPJ Pre-Hari Raya Ops: 11 Unfit Buses Found And Issued Notices
JPJ intensifies road safety measures, inspects over 500 buses ahead of the Hari Raya travel surge.
24-03-2025
Latest News
Road Users in Johor Now Eligible for Damage Compensation
Road users involved in accidents caused by damaged roads in Johor are now eligible to claim compensation from authorities.
27-05-2025
Hannah Yeoh: Funding Gap Slows Motorsports Growth
Despite its rising popularity, motorsports remains underfunded and overlooked in Malaysia’s sports development agenda.
27-05-2025
Smart Selangor Operator’s Blunder Strands Subang Jaya Commuters
APAD: Smart Selangor permit delays were due to the operator’s late application, not agency backlog.
27-05-2025
APAD Urged To Revoke Licenses Of Transport Companies Failing To Ensure Vehicle Safety
JPJ urged APAD to revoke the licenses of any transport company that fails to ensure the roadworthiness of its vehicles.
27-05-2025
Gov't Set To Use MyKad For RON95 Subsidy, Citing Success With Sara
The government has decided to use MyKad for targeted subsidies, citing its effective use in the Sara aid program.
27-05-2025
Suzuki Cars Malaysia Opens First Flagship Showroom in Petaling Jaya
Naza Eastern Motors has opened its first Suzuki Cars flagship showroom in Petaling Jaya, located along the Federal Highway.
26-05-2025
JPJ KL Seized Vehicles Auction Collects Over RM245,500
Latest JPJ KL auction sees a range of seized vehicles sold, tipper truck and scrap motorcycles included, successfully raises over RM245,000 too.
26-05-2025
Free Street Parking For Senior Citizens In Shah Alam
MBSA is giving free street parking to senior citizens through a "golden parking" program to celebrate the city's 25th anniversary.
26-05-2025
Show More
trending_flat