Central Spine Road Connecting Pahang To Kelantan 63.35% Complete

As of July 10, 63.35% of the300 KM-long Central Spine Road (LTU) connecting the East Coast Expressway (LPT) junction in Bentong, Pahang, to Kuala Krai, Kelantan, has been completed.
Works Minister Datuk Seri Alexander Nanta Linggi reported a slight delay of 0.39% from the scheduled 63.74%, accounting for the approved extension of time (EOT). He however assured that all delays and challenges will be managed following best construction practices and current regulations.
To date eleven projects have been completed, fourteen are currently under construction, and one is in the procurement process.
![]()
Nanta also provided updates on the various packages of the project:
- Package 1: Kuala Krai to the Sungai Lakit Bridge, is 11.59% complete.
- Package 2: Sungai Lakit Bridge to Gua Musang, is 22.40% complete.
- Package 3: Gua Musang to Kampung Relong, is 84.25% complete.
- Package 4: Kampung Relong to Raub, is 63.69% complete.
- Package 5: Raub to Bentong has been opened to users.
- Package 6: Bentong to LPT Junction, is 30.07% complete.

He also highlighted the Ministry of Works' (KKR) plans to upgrade the East-West Corridor from Pasir Puteh, Kelantan, to Gerik, Perak, and from Simpang Pulai, Aring to Kenyir, Terengganu, under the 2030 Highway Network Development Plan (HNDP 2030).
Nanta mentioned that the Third Rolling Plan (RP3) and the Fourth Rolling Plan (RP4) under the 12th Malaysia Plan (RMK-12) for these projects have been approved. RP3 includes upgrading the route from Kampung Pak Badol to Kampung Banir Belikong in Pasir Puteh and replacement of two bridges in Jeli. RP4 involves upgrading the East-West Highway from Section 113 to Section 151 in Gerik, Perak.
Additionally, projects under the East Coast Economic Region Development Council (ECERDC) including the FT482 Pasir Puteh - Tok Bali route is under RMK-12 land acquisition.
Nanta was addressing a supplementary question from Nik Mohamad Abduh regarding KKR’s plans to upgrade the East-West Corridor, specifically from Pasir Puteh to Gerik and from Simpang Pulai, Aring to Kenyir, Terengganu.
Source: BERNAMA
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VRB2241
SELANGOR
BSQ5146
JOHOR
JYX7317
PULAU PINANG
PSC6874
PERAK
APH8711
PAHANG
CFG6712
KEDAH
KGG3319
NEGERI SEMBILAN
NEK5516
KOTA KINABALU
SJS1879
KUCHING
QAB9310N
Last updated 06 Jun, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
KKR Seeking RM20 Million To Build R&R Along LTU Highway
Works Ministry seeks RM20 million budget allocation to set-up R&R along LTU Highway.
11-10-2024
Pahang Govt. Identifies Two R&R Locations Along The LTU Expressway
Pahang govt. identifies two locations along the LTU Expressway to house new R&Rs.
12-04-2024
LTU Section 5A: Raub Bypass Opens On Friday
The Section 5A: Raub Bypass of the Lingkaran Tengah Utama (LTU) Expressway opened last night, Friday, at 12:01
08-03-2024
Gua Musang Main Routes Closed For A Month For Lingkaran Tengah Project
The main entrances to Gua Musang were closed for a month beginning yesterday for the installation of bridge piles for the Lingkaran Tengah Utama Project (LTU).
31-03-2023
Two Million Road Users Set To Enjoy Toll-Free LTU
A total of two million road users are expected to enjoy the toll-free Lingkaran Tengah Utama (LTU) Expressway.
27-01-2023
50% Toll Discount Nationwide for CNY 2026
50% toll discount on selected highways from Feb 14–15 to ease CNY travel.
09-02-2026
Federal Highway Won’t Be Upgraded, Costs Deemed Too High
Despite worsening traffic conditions, the Federal Highway will not be upgraded, with the government citing high costs.
15-12-2025
MEX II Putrajaya-KLIA Extension Could Cost RM449 Million – Nanta
Works Minister Dato Sri Alexander Nanta Linggi said the MEX II extension project could cost as much as RM449 million.
03-12-2025
Latest News
RM200k Rebates?! Test Drive 9 Brands At The Sime Motors MotorExpo 2026 This Weekend
Hit up the free-entry Sime Motors MotorExpo 2026 at XOX Arena this weekend for massive RM200,000 rebates and test drives from 9 major brands.
05-06-2026
Chery Just Dropped Prices Across Their Entire Lineup, Now Starting From RM80k!
Chery Malaysia launches its 3rd Anniversary Mega Rewards promo, slashing prices across its SUV lineup including the Tiggo Cross, O5, Tiggo 7 Pro, and Tiggo 8 PHEV starting from RM80,800.
04-06-2026
No Car On Campus? Perodua Launched A New App So Uni Students Can Rent Cars To Go To Class
Perodua launches UCar-e, an app-based campus car-rental service for students at UUM, UPM, and UTM, offering an affordable alternative to car ownership.
04-06-2026
Zeekr Turned First-Time Track Drivers Into "Confident Pros" At This Supervised Sepang Event
The inaugural Zeekr Dynamic event at Sepang International Circuit turned first-time track drivers into confident pros through supervised performance and safety exercises.
04-06-2026
Expect Higher Maintenance Costs? Suppliers Warn Of Upcoming Price Revisions For Tyres & Spare Parts
Malaysian vehicle owners should expect higher car servicing, tyre, and spare parts costs starting June due to global energy market volatility. Find out how to beat the price hike.
03-06-2026
Buying A Car Soon? 5 Big Changes That Took Effect On 1 June That You Need To Know
Buying a car in Malaysia? The Hire-Purchase Amendment Act 2026 took effect on 1 June. Here are 5 new rules on EIR and car loan interest you must know.
03-06-2026
No Extra Cost, But Check Your Filter? 4 Essential Things Every Diesel Driver Needs To Know About The B15 Rollout
Malaysia officially rolled out the B15 biodiesel blend on June 1. Find out if your Hilux, Ranger, Triton, or Mazda diesel engine is compatible based on latest manufacturer statements.
03-06-2026
APAD Demands Answers: Prasarana Ordered To Submit Urgent Report Following Scary LRT Derailment In KL
APAD launches an immediate independent investigation into Prasarana following the Ampang Line LRT train derailment near Chan Sow Lin station due to a faulty track switch.
29-05-2026
Show More
trending_flat