Shah Alam LRT Delayed Again, December Now In Sight
Commuters hoping to ride the new Shah Alam LRT will need to wait a little longer. The 37km line, once scheduled to open on September 30, is now aiming for a December launch, The Star reported.
The delay centres on the project’s toughest hurdle, known as the fault-free run.
Each train must clock thousands of kilometres without breaking down before the line can open to the public. If even one significant fault appears, the entire mileage resets to zero, forcing the test to start all over again.
In a memo to staff, Prasarana Malaysia’s new president and CEO Amir Hamdan called for patience and even prayers.

Photo: The Star.
“God willing, the project will enter the fault-free run on August 25. We pray this test goes smoothly with no more delays so that we can complete the project in time for launch,” he wrote in a note titled 'Call to Prayer', which was sighted by The Star.
The first train must successfully complete 4,000 kilometres of testing, while the remaining sets must each log at least 2,000 kilometres.
The trains also need to run the full stretch from Johan Setia in Klang to Bandar Utama in under an hour, with departures every six minutes, in order to move more than 18,000 passengers an hour in each direction. The delay contrasts with recent assurances.
Transport Minister Anthony Loke told Parliament in late July that the project was 99% complete. Yet, days earlier, Prasarana had already hinted that testing would continue until October, suggesting September was always a stretch.
.png)
For now, commuters are left waiting once again. The line is almost complete, but the final test will decide if Klang Valley gets a smoother ride by the end of the year.
Source: The Star.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQD1346
SELANGOR
BSK7332
JOHOR
JYM5289
PULAU PINANG
PRW4560
PERAK
APD2532
PAHANG
CFE4090
KEDAH
KGD3779
NEGERI SEMBILAN
NEH8412
KOTA KINABALU
SJP2260
KUCHING
QAB7215M
Last updated 10 Dec, 2025
Fuel Price
Petrol
RON 95
RM 2.66
+0.03
RON 97
RM 3.29
+0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.08
EURO 5 B7
RM 3.28
Last updated 04 Dec, 2025
Related News
LRT3 Enters Final Testing Phase, Govt Targets Dec 31 Opening
LRT3 line is now in its final round of safety and reliability tests, with its launch date hinging on Dec results.
18-11-2025
LRT 3 Will Cost RM9.7 Billion Less Despite 5 Key Station Reinstatement
LRT 3 will cost RM9.72 Billion less even with the reinstatement of five key stations compared to initial 2015 cost quoted.
29-10-2024
LRT3 Enters Final Testing Phase, Govt Targets Dec 31 Opening
LRT3 line is now in its final round of safety and reliability tests, with its launch date hinging on Dec results.
18-11-2025
LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report
The LRT3 Shah Alam line opening could be delayed until Oct 31 instead of the planned launch date of Sept 30.
04-08-2025
PRIDE, SPX Launch Smart Lockers at Five LRT Stations
PRIDE and SPX Express aim to add convenience for commuters with new automated lockers primed in five LRT stations.
30-09-2025
Rapid Rail Set To Launch Real-Time Crowd Tracking & AI Security
Rapid Rail will introduce a live tracker showing coach crowd levels so commuters can board with less stress.
23-09-2025
Kelana Jaya Line Signalling Works Delayed, Phase 2 Work Starts Sept 6
Kelana Jaya Line Phase 2 and 3 signalling works will now begin on Sept 6, with select stations opening later on affected dates.
07-08-2025
Ten LRT KJ Line Stations Set for Upgrade – Open From 9 AM on Weekends
Ten LRT stations on the Kelana Jaya line will be upgraded, and their operation times will be affected on weekends.
28-07-2025
Latest News
Johor Bahru Set To Launch Free Self-Driving Bus In 2026
Johor Bahru will launch a free self-driving bus in early 2026, using AI and 5G to make city travel easier.
10-12-2025
MBSA Will Tow Abandoned Cars From Jan 2026
From Jan next year, MBSA will remove unclaimed vehicles left in public parking, especially by workshops.
10-12-2025
Unpaid Summonses Won’t Affect BUDI95 Subsidy - MOT
MOT clarifies that traffic fines and BUDI95 eligibility are not linked and operate under separate systems.
10-12-2025
WCE: Six New Toll Plazas Planned Along Melaka’s 69 KM Stretch
WCE set to add six new tolls along Melaka’s 69 KM stretch to ease congestion and spread out traffic flow.
10-12-2025
BYD Malaysia Charts Over 25,000 Units Sales In Just 3 Years
BYD Malaysia reveals it has shifted over 25,000 units of BYD and Denza vehicles in Malaysia in just under 3 years.
09-12-2025
Perodua Traz/Nexis D66B Teased Online – Launching Soon?
Perodua has published a short video teaser featuring the upcoming Traz/Nexis D66B SUV. Launch imminent?
09-12-2025
“Pay Early, Pay Less” Can Curb Habitual Traffic Offenders - Experts
Experts agree the new “pay early, pay less” system could improve compliance and road safety.
09-12-2025
KTMB’s ETS3 To JB Sentral Launches Dec 12 with 30% Discount
KTMB will start operating its ETS3 to JB Sentral on 12 Dec 202 with a 30% discount for travel on this route.
09-12-2025
Show More
trending_flat