Shah Alam LRT Delayed Again, December Now In Sight
Commuters hoping to ride the new Shah Alam LRT will need to wait a little longer. The 37km line, once scheduled to open on September 30, is now aiming for a December launch, The Star reported.
The delay centres on the project’s toughest hurdle, known as the fault-free run.
Each train must clock thousands of kilometres without breaking down before the line can open to the public. If even one significant fault appears, the entire mileage resets to zero, forcing the test to start all over again.
In a memo to staff, Prasarana Malaysia’s new president and CEO Amir Hamdan called for patience and even prayers.

Photo: The Star.
“God willing, the project will enter the fault-free run on August 25. We pray this test goes smoothly with no more delays so that we can complete the project in time for launch,” he wrote in a note titled 'Call to Prayer', which was sighted by The Star.
The first train must successfully complete 4,000 kilometres of testing, while the remaining sets must each log at least 2,000 kilometres.
The trains also need to run the full stretch from Johan Setia in Klang to Bandar Utama in under an hour, with departures every six minutes, in order to move more than 18,000 passengers an hour in each direction. The delay contrasts with recent assurances.
Transport Minister Anthony Loke told Parliament in late July that the project was 99% complete. Yet, days earlier, Prasarana had already hinted that testing would continue until October, suggesting September was always a stretch.
.png)
For now, commuters are left waiting once again. The line is almost complete, but the final test will decide if Klang Valley gets a smoother ride by the end of the year.
Source: The Star.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQP5018
SELANGOR
BSN1663
JOHOR
JYS7620
PULAU PINANG
PSA4012
PERAK
APF7637
PAHANG
CFF6469
KEDAH
KGE6756
NEGERI SEMBILAN
NEJ7143
KOTA KINABALU
SJQ6803
KUCHING
QAB3866N
Last updated 11 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing
All 33 technical problems identified on the Shah Alam Line have proposed fixes, but full testing is still underway.
31-12-2025
LRT3 Enters Final Testing Phase, Govt Targets Dec 31 Opening
LRT3 line is now in its final round of safety and reliability tests, with its launch date hinging on Dec results.
18-11-2025
LRT 3 Will Cost RM9.7 Billion Less Despite 5 Key Station Reinstatement
LRT 3 will cost RM9.72 Billion less even with the reinstatement of five key stations compared to initial 2015 cost quoted.
29-10-2024
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far
The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.
05-03-2026
LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays
The Shah Alam LRT3 line is targeted to begin operations by June 2026, with contractors liable for RM2.73 million per day in delay penalties.
24-02-2026
LRT3 Shah Alam Line Expected To Open In June
After years of delays, the LRT3 Shah Alam Line could finally begin operations in June, pending final safety tests.
05-02-2026
LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing
All 33 technical problems identified on the Shah Alam Line have proposed fixes, but full testing is still underway.
31-12-2025
Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.
15-12-2025
Latest News
Sepang Dates Confirmed: Catch Team Porsche Malaysia in Action on 21–23 August
While the 2026 Porsche Carrera Cup Asia (PCCA) season kicks off in Shanghai this weekend, Malaysian fans are already looking ahead to the highlight of the year: the homecoming.
10-03-2026
Iran-US War Day 10: It’s Not Just Fuel — Malaysia’s Automotive Industry Faces New Risks
While the BUDI95 subsidy program is already feeling the heat of oil prices flirting with US$120 a barrel, the true threat to our automotive sector lies beneath the surface.
09-03-2026
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far
The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.
05-03-2026
EV King is Here: How Proton e.MAS 5 Dethroned Popular Petrol Cars in 60 Days
PRO-NET has announced that the Proton e.MAS 5 has officially surpassed the 5,000-unit delivery milestone in just two months.
05-03-2026
Wolfgang Egger’s Masterpiece: Denza Z9 GT Confirmed for Malaysia Launch in Q2 2026
BYD Malaysia has officially confirmed that the Denza Z9 GT is set to launch in the local market in early 2026 (expected Q2). As the flagship luxury "shooting brake" for the brand, the Z9 GT is designed to offer a tech-forward alternative to the Porsche Panamera and BMW 5 Series Touring.
03-03-2026
Kelana Jaya LRT trains “out of service” but line running normally - RapidRail
Rapid Rail clarified that temporary train withdrawals on the Kelana Jaya LRT line are part of standard safety procedures.
27-02-2026
Leapmotor C10 Plus Debuts In Malaysia - 299 hp, 510 km Range, From RM139k
The 2026 Leapmotor C10 PLUS and exclusive Night Edition arrive in Malaysia with longer range, faster charging, and upgraded performance.
27-02-2026
Chery Malaysia Teams Up with Lee Chong Wei for Youth Badminton Cup
Chery Malaysia joins forces with Lee Chong Wei to sponsor the inaugural national youth tournament with RM100,000 in prizes.
27-02-2026
Show More
trending_flat