Shah Alam LRT Delayed Again, December Now In Sight
Commuters hoping to ride the new Shah Alam LRT will need to wait a little longer. The 37km line, once scheduled to open on September 30, is now aiming for a December launch, The Star reported.
The delay centres on the project’s toughest hurdle, known as the fault-free run.
Each train must clock thousands of kilometres without breaking down before the line can open to the public. If even one significant fault appears, the entire mileage resets to zero, forcing the test to start all over again.
In a memo to staff, Prasarana Malaysia’s new president and CEO Amir Hamdan called for patience and even prayers.

Photo: The Star.
“God willing, the project will enter the fault-free run on August 25. We pray this test goes smoothly with no more delays so that we can complete the project in time for launch,” he wrote in a note titled 'Call to Prayer', which was sighted by The Star.
The first train must successfully complete 4,000 kilometres of testing, while the remaining sets must each log at least 2,000 kilometres.
The trains also need to run the full stretch from Johan Setia in Klang to Bandar Utama in under an hour, with departures every six minutes, in order to move more than 18,000 passengers an hour in each direction. The delay contrasts with recent assurances.
Transport Minister Anthony Loke told Parliament in late July that the project was 99% complete. Yet, days earlier, Prasarana had already hinted that testing would continue until October, suggesting September was always a stretch.
.png)
For now, commuters are left waiting once again. The line is almost complete, but the final test will decide if Klang Valley gets a smoother ride by the end of the year.
Source: The Star.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQJ5481
SELANGOR
BSL9184
JOHOR
JYQ3080
PULAU PINANG
PRY105
PERAK
APE4955
PAHANG
CFE8961
KEDAH
KGD9718
NEGERI SEMBILAN
NEJ3570
KOTA KINABALU
SJP8461
KUCHING
QAB837N
Last updated 25 Jan, 2026
Fuel Price
Petrol
RON 95
RM 2.54
+0.02
RON 97
RM 3.10
+0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.88
+0.04
EURO 5 B7
RM 3.08
+0.04
Last updated 22 Jan, 2026
Related News
LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing
All 33 technical problems identified on the Shah Alam Line have proposed fixes, but full testing is still underway.
31-12-2025
LRT3 Enters Final Testing Phase, Govt Targets Dec 31 Opening
LRT3 line is now in its final round of safety and reliability tests, with its launch date hinging on Dec results.
18-11-2025
LRT 3 Will Cost RM9.7 Billion Less Despite 5 Key Station Reinstatement
LRT 3 will cost RM9.72 Billion less even with the reinstatement of five key stations compared to initial 2015 cost quoted.
29-10-2024
LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing
All 33 technical problems identified on the Shah Alam Line have proposed fixes, but full testing is still underway.
31-12-2025
Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.
15-12-2025
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.
12-12-2025
LRT3 Enters Final Testing Phase, Govt Targets Dec 31 Opening
LRT3 line is now in its final round of safety and reliability tests, with its launch date hinging on Dec results.
18-11-2025
LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report
The LRT3 Shah Alam line opening could be delayed until Oct 31 instead of the planned launch date of Sept 30.
04-08-2025
Latest News
UPSI Bus Crash: Brake Fade, Speed Cited as Key Factors
Mechanical faults, speeding, and poor oversight behind deadly Gerik bus crash, according to report.
23-01-2026
Volvo Teases ES90 Launch With ‘SELAMAT’ Campaign
Volvo Malaysia briefly presented “SELAMAT” as a new brand before revealing it as a safety-themed teaser campaign ahead of the ES90 launch.
23-01-2026
LEPAS Confirms 20-Outlets Ahead of 2026 Malaysia Launch
LEPAS signals serious intent ahead of its 2026 launch, confirming 20 sales and service outlets across Malaysia.
23-01-2026
JPJ Lifts Travel Proof Rule for Physical Driving Licence
JPJ lifts the travel proof rule, allowing motorists to apply for a physical licence without overseas travel justification.
23-01-2026
KL’s Lalaport Hub Nears Approval for Singapore Express Buses
KL’s Lalaport transport hub nears approval, set to streamline express bus travel to Singapore by February.
22-01-2026
Overloaded Lorry Crackdown Reduces Road Deaths
Stricter JPJ checks on overloaded lorries are helping make Malaysian roads safer with fewer fatal accidents.
22-01-2026
Bukit Chagar RTS Link Station Roof Completed, Final Facade Works Underway
Bukit Chagar station reaches a major milestone as the RTS Link roof is completed.
22-01-2026
Puspakom - New Brake Inspection Rules for Heavy Vehicles
Puspakom’s new brake inspection rules for heavy vehicles target unsafe brake settings that increase accident risks.
22-01-2026
Show More
trending_flat